Earned Value Management Flashcards

1
Q

Budget at Completion (BAC)

A

Original budget of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Planned Value (PV)

A

PV = Planned % Complete × BAC

Amount of money worth of work that should have been done on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value (EV)

A

EV = Actual % Complete × BAC

Amount of money worth of work you’ve actually done on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Actual Cost (AC)

A

Amount of money you’ve already spent on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Variance (CV)

A

CV = EV - AC

The difference between the work done and the money spent. This value should be positive for under budget. Negative values indicate over budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Performance Index (CPI)

A

CPI = EV / AC

The rate of how we are spending to actually earning on the project. This value should be 1 and over for projects under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule Variance (SV)

A

SV = EV - PV

The difference between the amount of work we should have done vs. the amount actually done. This value should be positive for ahead of schedule. Negative values indicate behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule Performance Index (SPI)

A

SPI = EV / PV

The rate of how we are meeting the project schedule. This value should be 1 and over for a project to be ahead of the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate at Completion (EAC)

A

EAC = BAC / CPI

Forecasting the total cost of the project at the end based on the current spending rate of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate to Completion (ETC)

A

ETC = EAC - AC

Forecasting the amount that will be needed to complete the current project based on the current performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Variance at Completion (VAC)

A

VAC = BAC - EAC

The difference between the original budget and new forecasted budget. This value should be positive for projects that may end at or under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To-Complete Performance Index (TCPI)

A

TCPI = (BAC - EV) / (BAC - AC)

The performance index that needs to be met to finish the project within budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly