RFQ
Request for Qualifications
RFP
Request for Proposals
Types of selection procedures for bid
Lowest bid, Best value bid, Qualifications-based
Design-Bid-Build
Competitively bid, lump sum construction contracts based on complete CDS; 3 players: owner, designer builder; 2 separate contract O-A, O-B; lowest responsible bid, market price
CM@R
Construction Manager oversees project management & building technology issues, may also be GC; GMP (Guaranteed Max Price), through at-risk agreements the CM@R becomes CM/GC; 3 players: owner, designer, CM@R; 2 Separate contracts: O&D, O&CM@R; overlapping phases
At Risk
Construction Manager holds trade contracts & takes performance risk; sometimes cost guarantee or GMP
Design-Build
owner contracts with single entity, Designer-Builder; fast track of design & construction; cost or solution basis for selection