Project Closeout Flashcards
Project closeout
Structure is made ready for occupancy and remaining documentation is finalized
contractor begins close out by
Notifying arch in writing and submitting list of items till to be completed
punch list
• List of items made by architect as a result of inspection to determine if a project is substantially complete
Second inspection to determine completion
g704
• Certificate of substantial completion
• Arch should include a time in which contractor has to complete any remaining items and list any nonconforming work the owner has accepted
Submitted to owner and contractor
after contractor has completed all remaining work
• Notifies the arch for final inspection • Final application for payment • Final cleaning • Show owners rep how to operate systems • Keying for locks and turn over keys Deliver attic stock
final completion
Documentedby architects issuance of the final certificate for payment
documents to be recieved by arch before final payment
• Affadavit - all expenses have been paid • Cert proving insurance to remain • Written statement by cxr that insurance will be renewed • Consent of surety to final payment • Satisfy contract obligations • Warrantees certs and bonds • All documentation • As builts • Cert of occupancy Extra stock
add services
• Any Architects duties after substantial completion
building commissioning
• Designing installing testing verifying and documenting of building systems
• Usually by a third party
Agent involved throughout design process
commissioning process in 3 stages
• Determined by size function time and money
• Determining performance reqs
• Planning the commissioning process
Performance and functional testing
determining performance requirements
• Determining performance requirements
○ Begins during predesign or design phase - which systems will be commissioned
○ Agent developes owners project requirements which is then developed into a basis of design during design phase (explains how opr have been satisfied by design)
§ Opr broad
Bod technical
planning the commissioning process
Determines the scope of activities, budget, schedule, specs and a written plan
performance and functional testing
○ Systems are started up and tested to determine if they meet design criteria
○ Operations and maintenance are demonstrated and training is conducted for owners operators
○ Commissioning report summarizes results of tests and describes maintenance instructions
○ Commissioning should continue into post occupancy - testing should occur one year after initial occupancy
Should relate to contractors warranty
building systems that require commissioning will depend on
- Complexity and needs of owner
* Hospital will require more thorough commissioning than an office building
CxP or CxA
• Commissioning provider or agent responsible for coordination of commissioning a lg building
• Independent third party agent who is hired by owner
• May also be a cm as advisor (not part of contractors firm)
B211 is used if arch firm provides services