Construction Administration Flashcards
Architects roles with CM as Adviser
• Joint administration of contract
• B132 and a232
• Architect and CM rep observe construction
• Owner and contractor communicate through CM with copies to arch
• Arch and CM have authority to require inspections and testing and rejecting work
• Submitalls are reviewed by cm and arch
• Cm prepares change orders
• Cm reviews RFIs, arch prepares dwgs if necessary
Arch remains as IDM
Architects roles with CM as Constructor
• Very similar to design bid build
• B133 and a201
• Arch must advise and consult cm and owner
• Arch responsibilities begin with owners acceptance of cm’s GMP, control estimate, or notice to proceed
• Cm submits applications for payment to arch
Cm issues cert for payment to owner but uses more complex method to calculte progress
Architects roles with Design Build
• B143 roles defined in exhibit to the agreement
• CA for arch’s portion of work
• Review contractor questions and issue supplementary dwgs
• Site visits on behalf of DB for arch portion of work only
• Reject non conforming work and require testing if necessary
• Review contractor app for payment
• Review submittals for arch portion of work
• Change orders
• Substatial completion observations
• Process final payment requests
Relay docs from contractor to DB
Architects roles with Integrated Project Delivery
• Construction admin duties are the same as a traditional project
• Focus on quality control and cost monitoring
• Not so much coordination bc it is usually taken care of in previous phases
Fewer onsite problems and RFIs
Preconstruction conference
• All the major players come to determine how construction will proscede
• Organized by architect
Site access, communications, insurance, non conforming or changing work, coordination and other requirements
Project Meetings
• Can be organized by owner arch or cxr
• All major players can attend but only necessary ones for each meeting
Arch is required
Construction observation overview
• Arch visits site at intervals agreed to in owner arch agreement
• Purpose is to
○ Become generally familiar and keep owner informed
○ Guard owner against defects in work
○ Determine if work is according to contract docs
Communication is established through General conditions of contract for construction
Number and timing of site visits based on
• Size and complexity
• Type of contract
Exact schedule of construction operations
Field reports
• Complete notes of observations taken at each site visit
• G711
• Should include
○ Report name and project number
○ Filed report number
○ Date time and conditions
○ Work in progress
○ Estimate of number of workers on site
○ Observations made
○ Assessment of conformance with schedule and % completion
○ List of items to verify
○ List of attachments and who is making the report
Copies are sent to contractor and owner
Uncovering and correction of work
• If arch specifies to leave work uncovered and cxr covers it anyway - cxr must pay to uncover and replace
• If arch does not specify and
○ Work is nonconforming - cxr pays
Work is conforming - owner pays
Field Tests
• Contractor is responsible for paying for field tests
• Contractor must make sure to give arch notice so that they can observe
• If additional tests beyond what is asked for in contracts is reqd. owner pays
Contractor pays all costs if tests show portion of work does not conform, including costs for extra tests and architectural services
Sustainability plans include
• Sustainable measures • Strategies to implement • Responsibilities assigned • Info about reviews and testing Documentation and formatting
Architects responsibilities for sustainable project
• Keep owner and contractor informed of progress and changes
• Respond to contractor rfis
• Register project with certifying authority - reimbursable
• Collect and organize sustainability documentation
• Applications and responses to certifying authority
If given enough notice - prep for appeals or interpretations
Voluntary acceleration
Cxr accelerates work on own accounts bc they have fallen behind and want to meet the deadline
Constructive acceleration
Uncontrolable delays (weather or deliveries) - but cxr does not ask for more time
Directed acceleration
Owner directed and agrees to pay through change order
Minor change in work document
G710 arch supplemental instructions