1
Q

What is aggregate planning?

A

task of identifying plans to produce products, expressed in specific quantities and dates, to fulfil a series of anticipated product demands and customer orders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are sales requirements in MPS?

A

the need to have a wide range of products constantly available to deal with high level of customer demand changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are financial requirements in MPS?

A

limit-lead time between production and sales in order to reduce the financial resources tide in stocks and finished goods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are production requirements in MPS?

A

to maintain a constant rhythm of production and manufacturing large lots to reduce production costs and of system set-ups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the resources and labour requirements in MPS?

A

achieve a smooth resources and manpower utilisation profile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is the MPS usually laid out?

A

in the form of a list of jobs with associated due dates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the objective of manufacturing scheduling?

A

efficient allocation of machines and other resources to jobs, and subsequent time phasing of these jobs on specific machines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly