Procurement of construction projects Flashcards
4 types of construction project contracts
traditional contract
design and build contract
management contracting
construction management
What is a traditional contract
Construction and design are separate. Building contractors hired for construction and professional consultants hired for design.
what is a design and build contract
The construction and design elements are in one contract. A building contractor is responsible to hire for both. May use own team or sub-contractors. Employer may create designs and then transfer them through novation to construction and design teams.
what is novation
the transfer of rights and responsibilities within a contract
what is a managing contract
Employer appoints a managing contractor who appoints contractors. They have limited liability to employer for failure of works contractors
Construction management
employer appoints construction manager and professional consultants. Construction manager is responsible for managing the construction but employer enters into contracts with trade contractors even though manager organised them (this bit makes it different to managing contract
obligations of an employer during construction
give up possession of premises and don’t interfere
obligations of contractor during construction
complete works set out in specifications
When does a contractor get paid
when the architect issues a certificate of practical completion the contractor is paid in full minus an retention monies withheld for snagging matters. The retention money is paid when a final certificate is issued.
can the employer claim damages for delay
yes for amount agreed in contract but cannot be disproportionate to amount needed to enforce the obligations otherwise it would be an unenforceable penalty.
Must the materials be of a particular standard
Yes S4 supply of goods and services act 1982 implies obligations to quality and fitness of building materials
Must the works be of a particular standard
Yes S13 of the supply of goods and services act 1982 - implies a term that the contractor will exercise reasonable care and skill to see that works will be of satisfactory quality and reasonably fit for intended purpose.
what standard of duty does the architect, consultant engineer and quantity surveyor owe the employer
standard of ordinary skilled man exercising and profession to have skills.
Duty by contract to carry out work with reasonable care, skill and diligence.
how are contractual damages assessed
Hadley v Baxendale - c can recover:
losses arising naturally from the breach
losses in the reasonable contemplation of the parties at the time of contracting as possible results of breach
what does the contracts ( rights of third parties) act 2000 allow
Allows a party to enforce the contract as if they were a party to it