Procurement of construction projects Flashcards

1
Q

4 types of construction project contracts

A

traditional contract
design and build contract
management contracting
construction management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a traditional contract

A

Construction and design are separate. Building contractors hired for construction and professional consultants hired for design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what is a design and build contract

A

The construction and design elements are in one contract. A building contractor is responsible to hire for both. May use own team or sub-contractors. Employer may create designs and then transfer them through novation to construction and design teams.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what is novation

A

the transfer of rights and responsibilities within a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is a managing contract

A

Employer appoints a managing contractor who appoints contractors. They have limited liability to employer for failure of works contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Construction management

A

employer appoints construction manager and professional consultants. Construction manager is responsible for managing the construction but employer enters into contracts with trade contractors even though manager organised them (this bit makes it different to managing contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

obligations of an employer during construction

A

give up possession of premises and don’t interfere

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

obligations of contractor during construction

A

complete works set out in specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When does a contractor get paid

A

when the architect issues a certificate of practical completion the contractor is paid in full minus an retention monies withheld for snagging matters. The retention money is paid when a final certificate is issued.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

can the employer claim damages for delay

A

yes for amount agreed in contract but cannot be disproportionate to amount needed to enforce the obligations otherwise it would be an unenforceable penalty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Must the materials be of a particular standard

A

Yes S4 supply of goods and services act 1982 implies obligations to quality and fitness of building materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Must the works be of a particular standard

A

Yes S13 of the supply of goods and services act 1982 - implies a term that the contractor will exercise reasonable care and skill to see that works will be of satisfactory quality and reasonably fit for intended purpose.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what standard of duty does the architect, consultant engineer and quantity surveyor owe the employer

A

standard of ordinary skilled man exercising and profession to have skills.
Duty by contract to carry out work with reasonable care, skill and diligence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

how are contractual damages assessed

A

Hadley v Baxendale - c can recover:
losses arising naturally from the breach
losses in the reasonable contemplation of the parties at the time of contracting as possible results of breach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what does the contracts ( rights of third parties) act 2000 allow

A

Allows a party to enforce the contract as if they were a party to it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Requirements for the contracts ( rights of third parties) act 2000 to apply

A
contract entered into after 11 may 2000
contract must expressly confer right or purport to confer benefit 
must be expressly identified in the contract by name, class or description 
party doesn't have to exist at the time of contracting
17
Q

can liability for pure economic loss be recovered in tort

A

Not normally. only under Headley Byrne v Heller which allows pure economic loss to be recovered where a special relationship of close proximity exists which creates a duty of care to avoid loss due to negligent misstatement. a duty is owed to exercise reasonable care if he knew or ought to know that reliance was being placed on skill and judgement

18
Q

what is a collateral warranty

A

an agreement where they accept a duty of care towards someone they wouldn’t usually owe one to.

19
Q

Can you claim for pure economic loss under a contractual warranty

A

yes if loss suffered as a result of breach could have reasonably been contemplated at the time. Would need to show that contractual duty of care was breach and damage has ensued.

20
Q

Ways that a tenant or buyer can enforce the employers rights

A

assignment of rights
declaring a trust of rights (where employer retains interest in property)
forced enforcement of remedies (where employer agrees to enforce their rights against the contractor)