when is planning permission needed
development or change of use
what is development - s55 TCPA 1990
any building, engineering, mining or other operations in, on or over land or any material change in use of building or land
do you need planning permission for a change of use within the same class
no this isn’t development
when is planning permission not required
affecting only interior of building or not materially altering the external appearance
what does the TCPO allow
for some developments to be approved automatically - no need to apply for permission for these
How to exclude the application of the TCPO
article 4 direction from LPA or S of S
How to know if the TCPO applies to your development
apply for a certificate of lawfulness from LPA under s192 TCPO. If refused then apply for planning permission
Classes of use
industrial commercial residential learning / community Class E - retail, sale of goods except hot food, sale of food and drink for consumption on premises, financial and professional services, and uses which can be carried out in a residential are without detriment to its amenity eg offices, research and development
for how long is an enforcement notice effective after service
28 days
what to do before serving a stop notice
serve an enforcement notice
how long does a temporary stop notice last
28 days
what is issued following inspection to show you have met the building regs
certificate of compliance or self certification for traders
how to search for building consents and certificates
CON29
who can prosecute for breach of building regs and how long do they have following completion of work
local authority within 2 years
what to do if building regs not met
ask seller for a regularisation certificate from LA listing work needed to bring it up to standard