Procurement Document Terms (AHPP pg 704) Flashcards

1
Q

Procurement Documents consist of three elements, which are…?

A

Project manual, contractor drawings and addenda

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Instructions to Bidders (A710-1997)

A

tell bidders what constitutes a responsive bid. Includes the date when bids are due, date and location of a pre-bid conference, last date when bidders can ask questions and the process for submitting questions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bid Bond (A310-2010)

A

guarantees that if the lowest bidder withdraws after selection but before execution of the contract, the owner will be reimbursed for the amount between the lowest bid and the second lowest bid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Bid form

A

format for bidders to present their cost, schedule, unit price, or other requirements info. a bid with an incomplete form is “nonresponsive”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Owner-Contractor Agreement

A

stipulates contract conditions between O&C such as cost of construction, project schedule and scope of work (i.e. A101-2017)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

General Conditions to the contract

A

sets the rights, responsibilities and relationships of the OAC. also defines procedural requirements to be used throughout construction period (ie payments, modifications to the contract, insurance, correction of defective work). A201-2017 is often the foundation of this general conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Supplementary Conditions to the Contract

A

project-specific modifications to general conditions. There is no standard AIA form, but A503-2007 has guidelines for developing these.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Specifications

A

in narrative form describe the qualitative, performance and installation requirements for products, materials and workmanship. also specifies administrative procedures that govern each trade.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Contract Drawings

A

graphic illustration of the project. drawings bound separate from project manual.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Addenda

A

modifications to contract documents (drawings, project manual or both). can be issued in response to questions from bidders or proposers or to reflect architect/owner initiated changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are some additional documents that can be included with the procurement documents for Bidders to review?

A

site survey, geotechnical report, hazardous material survey