Basic Service or Additional Service?! Flashcards
Based on AHPP Table on page 956. NOTE: this is based on B101-2007. make sure to research the updates in 2017 version.
Estimate of the cost of the work at all phases of design
Basic Service
Equipment layout at DD Phase
Basic Service
If requested by owner, reproduce and distribute the
bidding documents.
Basic Service
Consider allowable substitution requests
Basic Service
Organize and participate in a pre-bid conference
Basic Service
Answer questions from bidders by addenda
Basic Service
Organize and conduct the bid opening
Basic Service
Assist the owner in analysis of the bid results
Basic Service
Issue supplemental drawings as appropriate at CA phase
Basic Service
Review and certify certificates for payment
Basic Service
Review and take appropriate action on the contractor’s
submittals
Basic Service
Order minor changes in the work
Basic Service
Prepare and issue change orders
Basic Service
Prepare and issue construction change directives
Basic Service
Conduct inspections for substantial and final completion
Basic Service
Revisions to the architectural documents caused by
changes in instructions or prior approvals from the
owner
Additional Services
Changes to the drawings required by the enactment of
new codes, laws, or regulations
Additional Services
Non-timely decisions by the owner
Additional Services
Changes to the project size, quality, complexity, schedule, or budget
Additional Services
Extra work caused by performance failure by owner, contractor, or owner consultants
Additional Services
Preparation for and attendance at public hearings or dispute resolution proceedings
Additional Services
Review of contractor’s out-of-sequence submittals
Additional Services
Responses to RFIs where the information requested is in the contract documents
Additional Services
Change orders requiring revisions to the contract documents
Additional Services
Services related to fire or other damage
Additional Services
Review of an extensive number of claims
Additional Services
Evaluation of substitutions where revisions to the contract documents are required
Additional Services
Preparation of alternate bid or proposal requests
Additional Services
Construction contract administration services occurring more than 60 days after the originally scheduled date of substantial completion
Additional Services