Procurement And Tendering Flashcards

1
Q

What is the difference between procurement and tendering?

A

Procurement is the strategy by which goods and services are attained for a project.
Tendering is a process within the procurement strategy, and it is about how a price is obtained for the goods and services e.g. a bidding process and how the contractor will be appointed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is tendering?

A

The method of obtaining a price and resources to carry out required works for a project. A bidding process to obtain a price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What key procurement routes are there?

A

Traditional
Design and Build
Management Contracting
Construction Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What factors govern the procurement route selection?

A

It is based on the clients requirements for time, cost, quality and risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is traditional procurement and when will it be used?

A
  • Traditional is a linear form of procurement where the design is completed by the Client’s team, prior to any engagement with a contractor.
  • It is the longest procurement method as there is no overlap between the construction and
  • Provides cost certainty before the construction works commence.
  • Quality tends to be higher as the Client is in control, however the Client takes on the risk for the design.
  • Time certainty is obtained at tender as the works are fully designed.
  • The information created by the team can be with or without bills of quantities, includes the drawings and specifications.
  • This route is beneficial as post contract changes are easier to arrange and value.
  • This route does not allow for buildability or ECI (unless a 2 stage tender process)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Design and Build and when will it be used?

A
  • Design and Build is a procurement method where the Client’s team develop a set of Employer’s Requirements for the contractor to then develop the design and build to accordingly.
  • It allows time benefits as the construction works can start on site whilst the design is progressing.
  • The contractor takes on the risk of the design
  • There is a risk of quality being compromised as the contractor could derogate for commercial benefit
  • Whilst cost certainty can be obtained early, the price tends to be higher as the contractor prices for risk of taking on the design.
  • There is a single point of responsibility for the design and construction
  • Benefit from Contractors expertise
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Management Contracting and when is it used?

A

Management Contracting is a procurement method whereby the works are undertaken by different trade contractors and a management contractor is appointed to manage them. There is therefore one single point of contact for the packages.
The route has substantial time benefits as construction works can commence quickly.
It is used when works need to start ASAP. Based on this, there is little cost certainty until the last package is contracted.
Beneficial for large and complex or specialists projects, where it is best suited to appoint individual sub-contractors for the package.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How can a project be tendered?

A

Open Tendering
Selective Tendering
Serial Tendering
Negotiated Tendering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is serial tendering?

A

Used when a client has regular programme of works, or a number of phases of similar work. The first phase of works is competitively tendered, then following phases are negotiated based on the original schedule of rates so the cost is based on prices based on the competition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is open Tendering?

A

Where the tender is open to all. There is no control over the quality of tenders to be received. The best way to obtain the most competitive price and is therefore required for public projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is selective tendering?

A

When a pre-selected list of contractors are invited to provide a price for the works (typically no more than 6).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is single stage tendering?

A

Obtaining a competitive price of the whole of the works. Tenderers bid for a full designed package.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Two-stage tendering?

A

A contractor is selected in the 1st stage via a competitive tender based on prelims, OH&P, construction programme and method statement. It allows early engagement of the contractor. The 2nd stage is then negotiated to obtain the price for the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the main methods of choosing a contractor?

A

Open Tendering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is open tendering?

A

Any contractor is allowed to bid for the projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the advantages of open tendering?

A

Really competitive prices can be received

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the disadvantages of open tendering?

A

Quality of tenderers is not controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is selective tendering?

A

Restricts the number of tenderers who can bid for the job by pre-selecting a limited number to tender

19
Q

What are the two types of selective tendering?

A

Single Stage and Two Stage

20
Q

What is single stage tendering?

A

Process whereby all contractors bid for the works against a full completed design package.
Advantages include:
Competitive Price is obtained
Price is based on the same tender information so easier to undertake a comparative analysis

21
Q

Why was traditional deemed as the best route for Leadenhall and single stage negotiated tender?

A

Traditional was the best as it allowed the client to retain control of the design. The cost and programme certainty is attained prior to entering into contract.

Single Stage was the best route as it enabled the design to be completed prior to pricing exercise, therefore enabling cost and programme certainty (subject to no changes).

22
Q

Leadenhall - What procurement options were considered?

A

Traditional and Design and Build.

23
Q

Leadenhall - Providing examples, explain how you analysed each procurement option against some of the objectives?

A

Time - D&B would allow works to commence quicker with design and construction overlapping. Traditional requires the design to be fully complete prior to tendering therefore longer procurement process.
Cost - Traditional provides cost certainty prior to works commencing on site and post contract changes are easier to value. D&B has design risk built in and requires contractor pre-construction fee if appointed on 2-stage.
Quality - Traditional enables control of the design throughout the process therefore higher quality. The client had specific requirements of the design. D&B quality can only really be controlled if works are tendered at Stage 4.
Risk - Client retains design risk with traditional. D&B, risk is transferred.

24
Q

Leadenhall - How did the choice of procurement route impact quality?

A

Enabled quality to be prioritised during the design as Client retained control.

25
Q

Leadenhall - Explain how you negotiated the fees with the consultants to ensure best value for your Client?

A

Rates were compared with previous projects, and fee was analysed as a percentage against the previous floors. E.g. last project was 2 floors, fees are expected to be approx. 50% of previous floors.

26
Q

Leadenhall - When negotiating the costs with the contractor, how did you undertake this process?

A

This was led by the QS, however the process consisted of negotiating against the rates of the previous works which were competitively obtained, and undertaking an open book approach to ensure the most competitive sub-contract is included in the CSA.

27
Q

Leadenhall - Do you believe the Client go best value for this project when all parties were negotiated into the contract and appointment rather than going out to market?

A

I believe the Client obtained value through the knowledge of the team that was retained by negotiating with the existing team. But going out to market always provides more competitive options.

28
Q

Leadenhall - Did you produce the tender documents?

A

The tender documents were produced by the team and collated by the QS. I managed the process and aided with providing existing building information and ensuring the design team’s information was issued on time.

29
Q

Leadenhall - What was the content of the tender documents?

A
Preliminaries
Form of Tender
Pricing Document
Drawings and Specifications
Existing Building Information
Pre-Construction Information
Contract Document & Schedule of Amendments
30
Q

Leadenhall - Given the contractor was selected rather than tendered, did the tender documents include the schedule of contract amendments you mention?

A

Yes, to advise the contractor on which basis the works will be tendered.

31
Q

What is the form of tender?

A

A document prepared by the Client and their team that must be signed by the contractor as formal acknowledgement that they understand and accept the terms and conditions of the tender documents. It typically includes:

  • Latest return date and time
  • Acceptance of the tender T&C
  • Name, address etc.
  • Limitation period of the price
  • Contract sum being offered to complete the works
  • Signatory details.
32
Q

What does bona fide tender mean?

A

Tender provided in good faith that it is complete and signed by someone who has legal authority to sign such a bid. the bidder has not colluded with another party when compiling the documents.

33
Q

How did you decide which contractors to go out to?

A

This suitable for the project based on previous experience recommendations from team members and following a PQQ process the tenders are selected

34
Q

What is a preliminary enquiry letter and what would you include?

A

Enquiry letter is sent out to prospective tenders to confirm their interest in tendering on the job.

35
Q

What would you include in the pre–qualification questionnaire?

A
  • Details of Insurance Cover
  • Financial Information
  • Relevant Experience
  • Management Structure / Details of the Company
  • Health & Safety Policy
  • Environmental Management Policy
  • References
  • Quality Assurance Policy
36
Q

What is electronic tendering?

A

Where all the procurement and tendering processes are conducted through an online portal, Helps to streamline process and reduce cost of admin for tendering.

37
Q

Do you know of any e–tendering services?

A

Ted retendering

38
Q

What are the advantages of e–tendering?

A

I have no experience with e-tendering but I would review the RICS Guidance Note on e-tendering within the RICS Black Book

39
Q

How many contractors would you include on a tender list?

A

4-6 contractors

40
Q

How would you determine the duration of the tender period?

A

Depends on the size, value and complexity of the object, but also should be determined within the programme.

41
Q

What code of practice are you aware of relating to procurement and tendering?

A

BS:8534 - do not know in detail but will review on the British Standards Website.

42
Q

What happens if a tender is late?

A

Generally not accept. If public it is not accepted, if private then it is client discretion.

43
Q

What happens if tenders are returned and are higher than cost plan, pre–tender estimate?

A

Could be market problems, need to reconcile to identify major differences, VE process could take place on those elements.