Q

21) True or False: Team members entered into the RFIs Responsible Party field will receive notification emails regarding the RFI.

A

b. False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

38) True or False: Subcontracts with the status of Out for Bid or Out for Signature will be reflected on the budget.

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

32) True or False: Observations can only be created using an observation template.

A

b. False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

2) Notifications are automatically sent to bidders when bid documents are updated.
a. True
b. False

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

8) If you see this icon next to a drawing, what does it mean?
a. The drawing has sketches associated with it
b. The drawing has related items associated with it
c. Markups have been added to the drawing
d. The drawing can be viewed in fullscreen mode

A

c. Markups have been added to the drawing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

39) True or False: When creating a purchase order and filling out the contract company, you must select a vendor/company who exists in the project directory.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

34) True or False: A Budget Modification allows you to move budgeted costs to different line items.

A

a. True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

1) Bidders log in to ________ to view a bid package and submit a bid.
a. the project’s Bidding tool
b. the Company Level Planroom tool
c. their private email account

A

b. the Company Level Planroom tool

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

15) True or False: When you delete a specification from the Specifications list page, you will delete the specification and all of its revisions.

A

b. False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

26) True or False: Punch List templates are only available for use on Procore’s mobile application.

A

a. True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

23) True or False: You can only create follow-up meetings from a meeting in “Agenda” mode.

A

b. False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

10) Who can view drawing markups on the “Personal” layer?
a. Only you
b. You and ‘Admin’ level users on the Drawings tool
c. You and the project’s architect
d. All users that have access to the drawing

A

a. Only you

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

9) True or False: When you click a project’s Drawings tool, you should expect to see the project’s “current set” of drawings. (i.e. The most recently uploaded revisions of each drawing.)

A

a. True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

40) A purchase order with which of the following status will appear in the Committed Costs column on the budget?
a. Draft
b. Closed
c. Processing
d. Partially Received
e. Approved

A

e. Approved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

33) True or False: You can upload your budget into Procore by using a designated import template.

A

a. True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

25) Who can view a ‘Private’ punch list item?
a. The creator of the punch list item
b. The assignee of the punch list item
c. Users with ‘Admin’ permissions to the Punch List tool
d. Users that are on the punch list item’s Distribution list
e. All of the above

A

e. All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

6) How do you add a document to a project?
a. Send a file to the project’s unique email address
b. Upload a file using Procore’s Windows Desktop application, Procore Drive
c. Drag and drop a file into a folder’s designated “Upload Queue” section
d. Click the “Browse” button to select a file from your local computer
e. All of the above

A

e. All of the above

18
Q

30) True or False: You can create an observation from an inspection item.
a. True
b. False

A

b. False

19
Q

17) Who is the Submittal Manager? (select best answer)
a. The person who configured the Submittals tool on the project
b. A user who is in charge of contacting the external contractor when the submittal has been approved
c. The creator of the submittal
d. A user who is the gatekeeper of the submittal and is in charge of facilitating a submittals workflow making sure that it is collected and reviewed by all appropriate people.

A

d. A user who is the gatekeeper of the submittal and is in charge of facilitating a submittals workflow making sure that it is collected and reviewed by all appropriate people.

20
Q

11) Which of the following can you do when viewing a drawing on a mobile device?
a. Search for text
b. Compare differences between two drawing revisions
c. View attachments that have been added to the drawing
d. B and C
e. All of the above

A

e. All of the above

21
Q

18) What happens when the ball in court on a submittal switches to you?
a. You will receive an email notifying you that the submittal requires your attention
b. You will see a response box above the general information in the submittal
c. The submittal will appear in the “My Open Items” section on your home page
d. All of the above

A

d. All of the above

22
Q

36) How do you create a schedule of values in Procore’s Prime Contract tool?
a. Import the schedule of values (SOV) from a CSV file
b. Copy the schedule of values from the Budget
c. Manually add each line item
d. All of the above
e. Both A and B

A

d. All of the above

23
Q

42) True or False: A change event listed as “Out of Scope” means that the change falls within the scope of the original contract.

A

False

24
Q

3) True or False: Only entire folders can be attached to the bid package.

A

False

25
Q

28) Which of the following is a toolbar option in the Models tool?
a. Settings
b. Objects
c. Views
d. Measure
e. All of the above

A

e. All of the above

26
Q

12) True or False: You can publish multiple drawing markups at one time.

A

a. True

27
Q

35) What does the “Forecast to Complete” column show?
a. Money that you expect to be spent in addition to the projected costs in order to complete that scope of work
b. Sum of all known and expected costs that may be required to complete the scope of work
c. The difference between the projected budget and what you expect the total cost of completion to be at the end of the project

A

a. Money that you expect to be spent in addition to the projected costs in order to complete that scope of work

28
Q

22) True or False: When you link an RFI to a drawing, you will see the drawing linked on the RFI’s view page.

A

a. True

29
Q

20) What is the RFI Manager?
a. The person who configured the RFIs tool on the project
b. A user who is in charge of contacting the external contractor when the RFI has been resolved
c. The creator of the RFI
d. A user who will receive notification emails when the RFI is responded to or updated

A

d. A user who will receive notification emails when the RFI is responded to or updated

30
Q

4) True or False: You can create a commitment directly from an awarded bid.

A

True
In Procore, you can create a commitment directly from an awarded bid. Once a bid has been awarded, you can use the information from that bid to generate a commitment, which formalizes the agreement between the contractor and the subcontractor or vendor. This process helps streamline project management by ensuring that all relevant details from the bid are carried over to the commitment, reducing the need for duplicate data entry and minimizing the risk of errors.

31
Q

29) True or False: True or False: Daily Log entries can be entered for a future date.
a. True
b. False

A

b. False

32
Q

7) True or False: There is no way to validate whether or not a user (who has access to view the file) has downloaded the file from Procore.

A

False

33
Q

24) True or False: When a meeting is in “Draft” mode, you will not be able to distribute the agenda to any attendees.

A

a. True

34
Q

13) What are the best practices you should communicate to the Design Team about the formatting of the spec book?
a. The table of contents should be in the first 25 pages of the spec book
b. The spec section number and description should be in the header and footer of every page
c. There shouldn’t be any other string of numbers that looks like a spec section number in the header and footer of the page (e.g. a project ID)
d. All of the above

A

d. All of the above

35
Q

37) Which of the following accurately describe the Prime Contract?
a. A place you can manage profit and loss for all internal stakeholders
b. A Place where you can manage all contract-related work and share financial data with your owner or client

A

b. A Place where you can manage all contract-related work and share financial data with your owner or client

36
Q

41) When should you create a change event?
a. Once you create an RFI
b. Once you think an issue may have a cost associated with it
c. Once you create a change order
d. Before you create a budget modification

A

b. Once you think an issue may have a cost associated with it
In Procore, a change event should be created as soon as you identify an issue or potential change that may have a cost associated with it. This allows you to track the potential financial impact of the issue and manage it appropriately through the project’s lifecycle.

37
Q

5) What is the best way to be notified of changes made to a file or folder?
a. Manually check the file daily
b. Make a file or folder private
c. Use the built-in file tracking feature
d. Place it in the “Emailed Documents” folder

A

c. Use the built-in file tracking feature

38
Q

14) Why are some action buttons inactive and gray?
a. Because the action is no longer supported by Procore’s application
b. Because an ‘Admin’ user manually disabled the action
c. Because certain actions require that you first select one or more spec sections before the button becomes active and orange (i.e. clickable)
d. Because another user has already performed that action

A

c. Because certain actions require that you first select one or more spec sections before the button becomes active and orange (i.e. clickable)

39
Q

27) True or False: You can only use one Model joystick at a time.

A

b. False

40
Q

19) What should you do if a submittal is rejected by a member of the workflow?
a. Place the Ball in Court back to the submitter so that the workflow can begin again
b. Close the current submittal, and create a new submittal from the list page
c. Distribute the current submittal, and create a revision from the submittal’s view page
d. Delete the current submittal, and create a new submittal from the list page

A

c. Distribute the current submittal, and create a revision from the submittal’s view page
If a submittal is rejected by a member of the workflow in Procore, the recommended action is to distribute the current submittal to notify all relevant parties of its rejection and then create a revision from the submittal’s view page. This process maintains a clear record of the rejection and allows the submitter to address the issues noted and resubmit the corrected submittal.

41
Q

31) True or False: True or False: Company level inspection templates must be added to a project before any new inspections can be performed for that project.
a. True
b. False

A

a. True

42
Q

16) True or False: When you save a submittal as a draft, no notifications are sent out to the members of the distribution list and workflow.

A