Process Outputs Flashcards

(49 cards)

1
Q

develop project charter

A

-project charter
-assumption log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

identify stakeholders

A

-stakeholder register
-change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

develop project management plan

A

-project management plan
-change management plan
-configuration management plan
-performance measurement baseline
-project lifecycle description
-development approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

plan scope management

A

-scope management plan
-requirements management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

collect requirements

A

-requirements documentation
-requirements traceability matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

define scope

A

-project scope statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

create wbs

A

-scope baseline
-wbs
-wbs dictionary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

plan schedule management

A

schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

define activities

A

-activity list
-activity attributes
-milestone list
-change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

sequence activities

A

project schedule network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

estimate activity durations

A

-duration estimates
-basis of estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

develop schedule

A

-schedule baseline
-project schedule
-schedule data
-project calendars
-change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

plan cost management

A

cost management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

estimate costs

A

-cost estimates
-basis of esimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

determine budget

A

-cost baseline
-project funding requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

plan quality management

A

-quality management plan
-quality metrics

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

plan resource management

A

-resource management plan
-team charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

estimate activity resources

A

-resource requirements
-basis of estimates
-resource breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

plan communications management

A

communications management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

plan risk management

A

risk management plan

21
Q

identify risks

A

-risk register
-risk report

22
Q

perform qualitative risk analysis

A

risk register updates

23
Q

perform quantitative risk analysis

A

risk register updates

24
Q

plan risk responses

A

-change requests
-risk register updates

25
plan procurement management
-procurement management plan -procurement strategy -procurement statement of work -bid documents -source selection criteria -make-or-buy decisions -independent cost estimates -change requests
26
plan stakeholder management
stakeholder management plan
27
direct and manage project work
-deliverables -work performance data -issues log --change request
28
manage project knowledge
lessons learned register
29
manage quality
-quality reports -test and evaluation documents -change requests
30
acquire resources
-physical resource assignments -project team assignments -resource calendars -change requests
31
develop team
-team performanance assessments -change requests
32
manage team
change requests
33
manage communications
project communications
34
implement risk responses
-change requests
35
conduct procurements
-selected sellers -agreements -change requests
36
manage stakeholder engagement
change requests
37
monitor and control project work
-work performance reports -change requests
38
perform integrated change control
approved change requests
39
validate scope
-accepted deliverables -work performance information -change requests
40
control scope
-work performance information -change requests
41
control schedule
-work performance information -schedule forecasts -change requests
42
control costs
-work performance information -cost forecasts -change requests
43
control quality
-quality control measurements -verified deliverables -work performance information -change requests
44
control resources
-work performance information -change requests
45
monitor communications
-work performance information -change requests
46
monitor risks
-work performance information -change requests
47
control procurements
-closed procurements -procurement document updates -work performance information -change requests
48
monitor stakeholder engagement
-work performance information -change requests
49
close project or phase
-final product, service, or result transfer -final report