Formulas Flashcards
1
Q
BAC
A
budet at completion = original budget
2
Q
AC
A
actual cost = amount spent at a point in time
3
Q
EV
A
earned value: actual % complete * BAC
4
Q
PV
A
Planned Value = planned % complete * BAC
5
Q
CV
A
cost variance = ev - ac
6
Q
cpi
A
cost performance index - ev/ac
7
Q
sv
A
schedule variance - ev - pv
8
Q
spi
A
schedule performance index - ev/pv
9
Q
EAC
A
Estimate at completion
= BAC / CPI
10
Q
ETC
A
Estimate to Completion
= EAC - AC
11
Q
TCPI
A
To complete performance index
= (bac - ev) / (bac - ac)