Process Groups Flashcards

1
Q

What are the 5 Process Groups

A
Initiating
Planning
Executing
Monitoring & Controlling
Closing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What Are the 10 Knowledge Areas

A
Integration
Scope
Time
Cost
Quality
Human Resource
Communications
Risk
Procurement 
Stakeholders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What process group is Develop Project Charter

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What process group is Define Scope

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What process group is Identify Stake Holders?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What process group is Develop Project Management Plan?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What process group is Plan Scope Management

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What process group is Collect Requirements

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What process group is Create WBS

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What process group is Plan Schedule Management and Develop Schedule

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What process group is Define Activities and Sequence Activities

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What process group is Estimate Activity Resources and Duration

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What process group is Plan Cost Management

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What process group is Estimate Costs/Determine Budget

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What process group is Plan Quality Management

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What process group is Plan HR Management

A

Planning

17
Q

What process group is Plan Communications Management

A

Planning

18
Q

What process group is Plan Risk Management, ID Risks, Perform Qualitative/Quantitative Risk Analysis, Plan Risk Responses

A

Planning

19
Q

What process group is Plan Procurement Management

A

Planning

20
Q

What process group is Plan Stakeholder Management

A

Planning

21
Q

What process group is Direct and Manage Project Work

A

Executing

22
Q

What process group is Perform Quality Assurance

A

Executing

23
Q

What process group is Acquire/Develop/Manage Project Team

A

Executing

24
Q

What process group is Manage Communications

A

Executing

25
Q

What process group is Conduct Procurements

A

Executing

26
Q

What process group is Manage Stakeholder Engagement

A

Executing

27
Q

What process group is Monitor & Control Project Work

A

M & C

28
Q

What process group is Perform Integrated Change Control

A

M & C

29
Q

What process group is Validate Scope

A

M & C

30
Q

What process group is Control Scope

A

M & C

31
Q

What process group is Control Schedule

A

M & C

32
Q

What process group is Control Costs

A

M & C

33
Q

What process group is Control Quality

A

M & C

34
Q

What process group is Control Communications

A

M & C

35
Q

What process group is Control Risks

A

M & C

36
Q

What process group is Control Procurements

A

M & C

37
Q

What process group is Control Stakeholder Managements

A

M & C

38
Q

What process group is Close Project/Phase

A

Closing

39
Q

What process group is Close Procurements

A

Closing