Integration Management Flashcards
Inputs/Outputs for Develop Charter
I: Statement of Work (SOW)
I: Business Case
I: Project Selection Methods
I: Agreements/Contract
O: Project Charter
Inputs/Outputs for Develop Project Management Plan
I: Project Charter
O: Project Mgt Plan
Inputs/Outputs for Direct & Manage Project Work
I: Project Management Plan
O: Deliverables
O: Work Performance Data
Inputs/Outputs for Monitor/Control Project Work
I: Project Mgt Plan I: Schedule Forecasts I: Cost Forecasts I: Validated changes O: Work Performance Reports
Inputs/Outputs for Perform Integrated Change Controls
I: Proj Mgt Plan I: Work Performance Reports I: Change requests I: Enterprise Envir Factors I: Org Process Assets O: Approved Change Requests O: Change Log O: Proj Mgt Plan Udates O: Proj Documant Updates
Inputs/Outputs for Close Project/Phase
I: Proj gt Plan I: Accepted Deliverables I: Org Process Asses O: Final Product/Service/Result O: OrgProcess Asset Updates
Producing a project plan may best be described as
Creating a document that guides project plan execution
Project management plan updates are NOT an output of
Develop Project Management Plan
Where would you refer someone who is not aware of how to process change requests for a project in execution?
The Project Management Plan
What is the most important item needed in order to complete a project charter and why?
Business case; it explains the justification for the project
The Project Charter is
Developed AFTER the SOW and Before the PM Plan
T/F the PM information system would include a system for identifying stakeholders
FALSE
A defect in the project was brought to the PM’s attention, and now the project team is engaged in repairing it. Which PM process would be the most applicable for this?
Direct and Manage Project Work
What is the single document to guide project execution, M&C, and Closure?
The Project Management Plan
Change Control Meetings are held as part of which process?
Preform Integrated Change Control