Procedures Flashcards

1
Q

PROJECT MANUAL

A

Includes:
• Bidding requirements
• Sample forms
• Conditions of the contract
• Specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

STATEMENT OF RESPONSIBILITY

A

A written statement provided by the contractor to the BUILDING OFFICIAL and the OWNER.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who signs a construction change directive?

A

ARCHITECT & THE OWNER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is included in the CONTRACT DOCUMENTS?

A

• Owner-Contractor Agreement
• Addenda
• Specifications
• Supplementary conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is included in the BIDDING REQUIREMENTS?

A

• Invitation to bid
• Instructions to bidders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How can the Architect issue a MINOR CHANGE IN THE WORK?

A

Can be issued through an ASI along with the G701

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the 1-YEAR CORRECTION PERIOD?

A

Begins at SUBSTANTIAL COMPLETION. The contractor must correct any work found not to be in compliance with the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is shown in the CONTRACTOR’S APPLICATION FOR PAYMENT?

A

• Shows the value of materials purchased BUT NOT INSTALLED.
• It shows the amount of retainage
• It standardizes the payment process.