Pro Practice Flashcards
Architect’s consultants
Structural
MEP
Civil
Landscape
Security
Tech
Lighting
Acoustic
Audio/visual
Cost estimator
Code
Sustainability
A132
CM agent
CM advisor
A-133
CM Constructor / at-risk
A195
IPD Agreement
A201
General conditions of the contract
- drawings
-arch process for keeping schedules
-arch process for contractor pay apps
-defines what constitutes substantial completion
G701
Change order
G702
App for payment
G703
Continuation sheet
G704
Substantial completion
G716
RFI
Invited Bid
Prequalified contractors selected and given opp to bid
Phased Bid
Used during fast-tracked construction to allow systems with long lead times to be bid first (to be fabricated earlier)
Negotiated Bid
Contractor brought on at the beginning of the project to provide feedback, AFTER CDs the bid is NEGOTIATED btwn o + c
Masterformat
Specs organized by material or process (concrete, excavation)
Uniformat
Organized by the system (foundations, stairs)