Days Flashcards

1
Q

3 days (insurance)

A

Bonds to be delivered to owner after execution of contract
A701 7.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

3 days (insurance)

A

Owner - contractor both ways; inform of findings that require insurances will be cancelled or expired (3 business days)
A202-11.1.4 / 11.2.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

4 days (bidding)

A

Addendums no later than 4 days prior to bidder
A701-3.4.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

7 days (bidding)

A

RFIs submitted to architect prior to the bid due date
A701-3.2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

7 days (bidding)

A

Owner to furnish reasonable evidence that financial arrangements have been made prior the the time of the withdrawal of bids
A701-6.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

7 days (legal)

A

Liens
Arch to request info from owner for consultants to evaluate, give notice or enforce lien rights within 7 days of written request.
Also arch furnishes info obtained to consultants
C401-5.9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

7 days (suspension)

A

If arch elects to suspend services, arch should notify the owner within 7 days written notice.
B101-9.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

7 days (termination)

A

Owner - architect can terminate agreement with not less than 7 days written notice if other party fails to perform in accordance with contracts
B101-9.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

7 days (termination)

A

Owner can terminate agreement for convenience with not less than 7 days written notice
B101-9.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

7 days (info)

A

Receiving party may disclose confidential information to the other party.
A201-2.2.4
B101-10.8.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

7 days (payment)

A

Arch issues certificate of payment to owner, 7 days after receiving contractor’s application for payment.
A201-9.4.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

7 days (payment)

A

Contractor to pay subs within 7 days of receiving payment from owner.
A201-9.6.2

And provides evidence of this payment to the owner upon his request
A201-9.6.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

7 days (payment)

A

Owner to pay contractor within 7 days of date established within the contract docs.
A201-9.7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

7 days (stop)

A

Contractor may stop work within 7 days notice if arch fails to issue cert. of payment or owner fails to pay contractor within time limits
A201-9.7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

7 days (termination)

A

Contractor must provide additional 7 days written notice if they want to terminate contract due to owner’s failure to fulfill obligations.
A201-14.1.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

7 days (termination)

A

Owner may terminate for cause with 7 days written notice
A201-14.2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

10 days (bidding)

A

Bidding docs deposit refunded to bidders who return the papers of bidding docs in good condition
A701-5.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

10 days (bidding)

A

Submit substitutions prior to bidding date
A701-6.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

10 days (notice)

A

Owner and contractor can change rep. After 10 days written notice
A101-8.4

Same for owner and design builder
A141-1.2.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

10 days (billing)

A

Arch to review issues with consultants invoices within 10 days of receiving the invoice
C401-11.6

21
Q

10 days (correction of work)

A

If contractor fails to correct the work after 10 days notice from the owner, the owner can carry out the correction of the work.
A201-2.5

22
Q

10 days (payment)

A

10 days for contractor to submit application for payment prior to established progress payment date
A201-9.3.1

23
Q

10 days (claims)

A

IDM to review claims within 10 days of claim reviewed.
If IDM needs info, party to respond within 10 days
A201-15.2.2 & 15.2.4

24
Q

14 days (bidding)

A

Bidder can request the owner to provide evidence that financial arrangements have been made to fulfill owner’s obligations to bidders, prior to withdrawal of bids.
A701-6.2

25
Q

14 days (Info)

A

Certificates should be provided to arch’s review at least 14 days prior to the owner’s requested date of execution
B101-10.4

26
Q

14 days (stop)

A

After commencement of construction, if the owner fails to submit to the contractor, requested evidence of financial arrangements, the contractor can stop the work.
A201-2.2.2

27
Q

14 days (notice)

A

Contractor to inform architect and owner if subsurface conditions differ from contract documents within 14 days written notice
A201-3.7.4

28
Q

14 days (notice)

A

Contractor to notify owner and arch about selected superintendent. Same time frame for arch. To confirm if owner or arch do or do not object
A201-3.9.2

29
Q

14 days (notice)

A

Arch to notify contractor if arch or owner object or not about selected subcontractor
A201-5.2.1

30
Q

15 days (legal)

A

Liens
Owner shall furnish info for the arch to evaluate, give notice, or enforce lien rights within 15 days of receipt of request.
B101-5.15

31
Q

15 days (legal)

A

Liens
Owner shall furnish info for the contractor to evaluate, give notice, or enforce lien rights within 15 days of receipt of request.
A201-2.1.2

32
Q

21 days (notice)

A

Notice of injury or damage from teh responsible party. Shall be notified within 21 days after discovery.
A201-10.2.8

33
Q

21 days (claims)

A

Claims of conditions discovered prior to expiration of the period of correction of work, shall be initiated within 21 days after occurrence or after finding, which ever is later.
A201-15.1.3.1

34
Q

30 days (payment)

A

Owner’s final payment after issuance of arch’s final certificate of payment
A101-5.2.2

35
Q

30 days (payment)

A

If work has been suspended for more than 30 days the subcontractor’s compensation shall be equitably adjusted
A201-5.4.2

36
Q

30 days (termination)

A

Contractor may terminate contract if work is stopped for 30 CONSECUTIVE days through no fault of the contractor
A201-14.1.1

37
Q

30 days (claims)

A

IDM shall provide initial decision within 30 days of claim.

If not, party can demand mediation and binding dispute resolution
A201-15.2.1

38
Q

30 days (claims)

A

Either party may

Within 30 days from the date of the initial decision
Demand

in writing that he other party file for mediation within 60 days of the initial decision

A201-15.2.6.1

39
Q

60 days (claims)

A

If mediation proceeds in advance of dispute resolution, mediations shall be stayed for 60 days pending modification from filing date.
B101-8.2.2
C401-8.2

40
Q

60 days (services)

A

CA services provided 60 days after SC or initial date of the substantial completion in the contract, the architect, shall be entitled to add services
B101-4.2.4

41
Q

60 days (claims)

A

60 days after demand of mediation, dispute resolution can be filed.
A201-15.3.3

42
Q

60 days (termination)

A

Contractor can terminate contract if work is stopped for 60 consecutive days if owner has repeatedly failed to fulfill obligations. Contractor to give 7 days notice
A201-14.1.4

43
Q

90 days (budget)

A

If the procurement phase has not commenced within 90 days after submits the construction docs the owner’s budget should be adjusted
B101-6.4

44
Q

90 days (termination)

A

If owner suspends the project for 90 CUMULATIVE days for reasons other than the fault of the arch, the arch may terminate the agreement
B101-9.3

45
Q

120 days (termination)

A

Contractor may terminate contract if owner delays work more than 100% of total days or 120 days in 365 day period.
A201-14.1.2

46
Q

1 year (correction of work)

A

Contractor shall correct the work not found in accordance with contract docs within 1 year of SC warranty
A201-12.2.2.2

47
Q

1 year (termination)

A

…and suspension.
Except as expressly provided in the prime agreement, it shall terminate 1 year from the date of SC
B101-9.8

48
Q

10 years (claims)

A

Owner and architect shall commence all claims not more than 10 years after SC same as owner and contractor.
B101-8.1
A201-15.1.2