Private Sector Contracts - EXAM Flashcards
Exam Prep
Standard Forms/Yellow Form - What are the Constituent Parts of the Yellow Form of Contract?
- Articles of Agreement
- The Conditions of the Contract
- The Appendix
Standard Forms/Yellow Form - What are the conditions of the Contract?
- The conditions cover matters of Quality of the work, Cost, Time, nominated suppliers, Insurance, Fluctuations, VAT and Dispute Resolutions
- They clarify the rights and responsibilities of parties if a dispute arises
- All amendments to the Articles must be initialled by both parties to confirm no amendment was made post-contract signing
Standard Forms/Yellow Form - What are the key topics covered in The Articles of Agreement?
Article 1 - Basic duty of the Contractor is to execute and complete the works
Article 2 - Basic duty of the Employer is to pay the contractor
Article 3 - Identifies the Architect
Article 4 - Identifies the QS
Article 5 - Is the section where signatures or seals are completed by the parties. A signed contract binds the parties for 6 years, a sealed contract binds the parties for 12 years.
Standard Forms/Yellow Form - What is the Contract Appendix?
- The appendix summarises the variable items that will be particular to a contract.
- This enables a reader to get a concise overview of the details contained within the other sections.
Standard Forms/Yellow Form - What 9 Information points may be contained in the Contract Appendix?
- Designated Date
- Insurances
- Start Dates
- Completion Dates
- Period of Interim Payments
- Lengths of defects liability period
- Value of LADS
- Retention value
- Period of final measurement
Standard Forms/Yellow Form - Explain the Liasion Committee & their recommendations for Standard form of Contracts
The LC is made up of the RIAI, SCSI, CIF, EI & AECI. Their main function is to make recommendations to members on any amendments to the Agreement and schedules of the standard forms of contract.
They also make recommendations relating to Tendering, Producing BOQs, Daywork Rates & dealing with disputes between members.
They strongly advise that amendments are not undertaken without legal advice due to the Contra proferentem rule stating that the most onerous interpretation of the change will be applied against the drafter/draftsman.
What is Clause 21 A
Clause 21A states that the Contractor shall be liable and indemnify the Employer in respect of Loss or Damage to Property and Injury to Persons.
What is Clause 21B Option 1?
Clause 21B Option 1 - states that the Contractor must take out insurance to cover his liability to the employer. The insurance must stay in place for up to 18 months from PC.
These insurance types are:
1. Public Liability - Insurance that covers 3rd parties (general public) if a Contractor becomes liable for injury, death, damages, expenses, costs etc.
2. Employers Liability - Insurance that covers employees if anything happens in the course of them fulfilling their duties.
3. Motor Insurance - Required to cover employees driving company vehicles
What is Clause 21B Option 2?
The same as option 1 but the Employer takes out the Public Liability Insurance on behalf of the Contractor.
What is Clause 22?
All Risks Insurance
Clause 22 - What 5 items does All Risks Insurance Cover?
- Full cost of reinstatement of damaged works
- Cost of Site Clearance
- Professional Fees
- The Works - Building & Site Works
- Ancillary Works - Temporary Works & Materials required to do the job
Clause 22 - Who takes out All Risks Insurance?
Either the Contractor or the Employer. If taken out by the Employer, it will cover the 5 usual items but also include VAT if the Employer is not VAT registered.
1. Full cost of reinstatement of damaged works
2. Cost of Site Clearance
3. Professional Fees
4. The Works - Building & Site Works
5. Ancillary Works - Temporary Works & Materials required to do the job
6. VAT (if required)
Clause 22 - What 6 items are important to note if the Employer takes out All Risk Insurance?
- Insurance Compensation is paid into a joint account
- Compensation less fees are paid
- Architect must certify payments from the account
- Payments are not subject to retention
- If the compensation does not fully cover the costs, the shortfall must be made up by either the contractor or the employer depending who took out the policy
- If reinstatement works cost less due to variation in spec/scope the employer may keep the balance between cost & compensation payment.
What is Clause 23
Insurance Policies - Rules & Stipulations
1. The insurance must be with a Provider approved by both client & employer
2. Insurance must be in the Joint names of the Contractor and employer
3. Insurance must be in place before work begins
4. Insurance Exclusions are listed examples are War Risk, Sonic Boom, Offshore work, terrorism, etc.
Clause 33 - What actions by a Contractor can allow an Employer to determine a Contract?
- If the Contractor suspends the works without reasonable cause.
- Fails to proceed with the works with reasonable diligence
- Persistently fails to carry out instructions
- Fails to build as stated in the contract
- Seriously breaches the contract
- If the Contractor becomes bankrupt