Cost Control Flashcards
What is the difference between Site Overheads and company Overheads?
Variations - What are the ways a variation should be Formulated/Costed?
- By agreement
- Bill of quantity rates
- Adjusted rates - Where work & conditions are dissimilar
- Market Rates - Based on similar work done in same locality & material cost
- Dayworks - Time + plant & materials
- Omitted Work - Credits based on contract values
Cash Flow - How can a Contractor improve Cash Flow at the Tender Stage?
- Money can be loaded into under-measured items
- Money can be loaded into items that will be completed early such as excavation & sub-structures
- Money can be loaded into Prelims
Cash Flow - How can a Contractor improve Cash Flow at the Contract/ Construction Stage
- Ensure claims are submitted on time
- Over-measure the works in progress
- Over-value materials on-site
- Agree on the value of variations ASAP
- Remedy defective work quickly so payment isn’t held back
- Use trade credit facilities cleverly i.e. 30-60 days on materials
Cash Flow - How can a Contractor improve Cash Flow Post-contract
- Submit all documents quickly.
- Make sure there are no delays to retention being released i.e. O&Ms & Health & Safety Files submitted on time.
- Get agreement on the Final Account quickly
- Ensure to collect Retentions as early as possible
Cash Flow - What are the different methods to produce an S Curve & how is it presented?
- S- Curve. Proven by research to work. The S Curve is best applied to projects where Provisional Sums are evenly spread. It does not allow for high-expenditure items early in the project.
- Types of S Curve are - 1/4:1/3 Rule, Cumulative Percentage Value, Bar Chart Programme & The Good Guess Method.
Cash Flow - Explain the 1/4:1/3 Rule
- 1/4 of total expenditure will occur in the 1st 1/3 of the project
- 1/2 of total expenditure will occur in the 2nd 1/3 of the project
- 1/4 of total expenditure will occur in the final 1/3 of the project
On a graph, Project Value (€) will be shown on the Vertical and Time (Weeks/Months) shown on the Horizontal
Cost Control - What are the main sources of Information available to the Contractors QS
- Contract Bills of Quantities - They contain a breakdown of how the job was priced. Not ideal for Civil Projects as BOQs are approximate & full remeasure will be required.
- Estimates of Cost - Provides a better breakdown of the total cost allowed in a BOQ
- Method Statement - Details assumptions made by the estimators & management team
- Master Programme - Contains the sequence and timing of all aspects of the project
Cost Control - What additional items can be added to the 4 main types of information available to QS’s?
- Interim Valuations,
- Financial info on: Labour, Plant Materials, Sub-Contractors, Salaries, All other Site Costs
LADs - What is meant by liquidated and ascertained Damages?
- LADs are essentially a way for a client to safeguard against losses and costs due to a project running on due to delays caused by the Contractor, provided the Contractor has no grounds for an Extension of Time
- A sum of money, specified in the Contract will be deducted from the Contractor’s account to compensate the client.
- LADs must be calculated on a realistic basis and are not a punishment payment.
LADs - What are the benefits of Liquidated Damages
- Certainty - Both parties have a degree of certainty should the programme run over.
- Limitation of Liability - If a contract is breached, the LADs limit the damages available to the client. The Employer cannot seek further damages.
- Saves Time and Expense - The process is much simpler as it is a contract stipulation, rather than the alternative of going through the courts.
- Incentive - Contractors are incentivised to finish the project on time and are unlikely to unnecessarily delay works/completion.
Explain how the following changes are valued under the RIAI Standard Form of
Contract (assume a 65 week contract).
The contract is on programme at week 58 with all the internal doors fixed. The Architect issues an instruction to remove a number of the corridor doors and frames and replace them with acoustic door sets. Delivery of these units is quoted as 14
weeks.
- It needs to be established if the doors installed are as per the contract specification. If they are as per the contract spec, it can be deemed to be a variation. If they are not as per the spec the doors must be removed and replaced by the contractor at his own expense. (Clause 8)
- The substitution of contract works is a variation under (Clause 2).
- Assuming the doors are a variation, the architect’s request must be priced in accordance with Clause 13.
- The Contractor shall be paid for the original door sets and any associated works.
- The Contractor shall be paid for the cost of removing the installed door sets, making good finishes & disposal of doors & frames.
- As no cost available in BOQ for the same door types, the QS must get market rates for purchase & installation or get a supply & install cost from a specialist installer.
- The Contractor will be permitted to add for profit on the Specialist Installers costs.
- The programme will be affected by at least 7 weeks. Additional time must be allowed to complete the remaining contract works and the installation of the doors.
- An Alternative Proposal could be offered. If it suited the client, installing the doors at a later date may cost more for the doors themselves but savings could be made by having the building available to them on the original contract date.