Prince 2 Flashcards

1
Q

A checkpoint report is a ?what? driven control

A

A checkpoint report is a time-driven control because checkpoints happen at regular times throughout a stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which document is used to identify interested parties that need to be informed of a project closure?

A

Communication management approach.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Any change to the products agreed at the start of a stage is monitored as part of the [?] process, on a day-to-day basis.

A

Controlling a stage. (as this is responsible for monitoring the progress of a project)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Prince2 mandates that the project board represents the primary stakeholder interests. Which principle does this follow?

A

Defined roles and responsibilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When is it confirmed whether a project’s objectives have been achieved?

A

During the ‘Closing a project’ process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the difference between project assurance and quality assurance?

A

Project assurance provides assurance to the project’s stakeholders whereas quality assurance provides assurance to the wider corporate, programme or customer organisation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If a baselined product requires modification, the recommended [?] procedure, or equivalent procedure should be used.

A

Issue and Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

According to the ‘manage by exception’ principle, what should be defined to establish limits of delegated authority?

A

The Tolerances for the Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which is the purpose of the ‘controlling a stage’ process?

A

To take action so that the stage remains within tolerance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is likely to be avoided by applying the ‘tailor to suit the project’ principle?

A

Unnecessary management effort.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the responsiblity of the team manager role?

A

To manage a team within the stages. (larger)

> To accept authorised work packages from the project manager. (and deliver them)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In which situation might the ‘controlling a stage’ process be used?

A

To Manage a long initiation stage of a complex project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Prince2’s recommended approach to planning?

A

Identify activities and dependencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is an advantage of applying the ‘learn from experience’ principle?

A

It allows the project team to identify improvements to be made during the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What makes a Prince2 Project?

A

It has project processes that satisfy the objectives of PRINCE2 processes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is risk probablity?

A

A measure of the likelihood of the risk occurring.

17
Q

How would you describe the ‘implement’ step within the recommended risk management procedure?

A

The risk owner and the risk actionee carry out activities to control and deal with the risk.

18
Q

What is AN objective of the ‘initiating a project’ process?

A

To summarize how the organisation’s project management method will be tailored for the project.

19
Q

What is a minimum requirement for the risk theme?

A

To record identified threats in a risk register.

20
Q

Who is responsible for documenting any tailoring of work packages?

A

Project Manager (ie. not Executive, team leader)

21
Q

What is a minimum requirement for applying the quality theme?

A

To define the project’s approach to project assurance. (we must have project assurance) Remember that quality is defined by the customer.

22
Q

What is the purpose of the Quality theme?

A

to look for ways to improve the effectiveness of the management of the project.

23
Q

What is the purpose of the business case theme?

A

A business case is a justification of the expenditure. It is to establish methods to judge whether the ongoing project is justified.

24
Q

Which process provides the project board with the information it requires in order to commit resources to the project?

A

Initiating a project.

25
Q

What is a highlight report?

A

It describes how we are doing right now. Provides a summary of the stage status and it is used by the project board to monitor the progress of the stage and project.

26
Q

Which product provides the version number of all products in a particular stage?

A

Product Status Account. (as it is ALL products)

A Configuration Item record refers to ONE product.

27
Q

Name all of the themes in a PRINCE2 Project. (7)

A
Business Case
Change
Organization
Plans 
Progress
Quality 
Risk
28
Q

What are the aspects of a project? (6)

A
Time
Cost 
Quality
Benefits
Scope
Risk
29
Q

What are the core principals?

hint: 7

A
  • Continued Business Justification
  • Tailoring to suit
  • Learn from Experience
  • Defined Roles and responsibilities
  • Focus on Products
  • Manage by Exception
  • Manage by Stages
30
Q

What is are the processes of a Prince2 project? (7)

A
  1. Starting up a Project
  2. Initiating a project
  3. Directing a project
  4. Managing a stage boundary
  5. Controlling a stage
  6. Managing product delivery
  7. Closing a project
31
Q

What Roles are in the Project Board group?

A
  • Executive
  • Senior User
  • Senior Supplier
32
Q

Name all of the Roles in a Prince2 Project

A
  • Project Board (Executive, Senior User, Senior Supplier)
  • Project Assurance
  • Change Authority
  • Project Manager
  • Project Support
  • Team Manager
33
Q

What is the definition of a project?

A

A temporary organisation that is created for the purpose of delivering one or more business products according to the agreed business case.

34
Q

What must be recorded in the project initiation documention to meet the minimum requirements for applying the progress theme?

A

The overall approach to managing by exception.

35
Q

Which theme establishes mechanisms to monitor and compare actual achievements against those planned?

A

The progress theme.

36
Q

Which role is responsible for the management of the risk assigned to it?

A

Risk Owner

37
Q

Who is responsible for approving or rejecting requests for change within the delegated limits?

A

The Change Authority.

38
Q

What does applying the ‘manage by stages’ principle ensure?

A

That the project is properly initiated before work begins on delivery of the project’s outputs.