Presentation Questions Flashcards

1
Q

Under the SBC, how would you advise your client if the contractor was not actioning an contract instruction that had been issued?

A

Other contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You used the Without Quantities version of the SBC, Why did you choose that over the With Quantities version? Would you consider this to be the correct contract choice for this project?

A

Quantities based on the area not being complete. Perhaps the right contract, client familiarity. Also generally over £1m would be complex enough to require SBC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the timescales involved in the acceptance of a contract instruction under SBC?

A

no. of days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the payment timescales under SBC?

A

5 days // 14 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When issuing a extension of time, is an extension of the contractor’s preliminaries automatically included within the claim?

A

No - L&E

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If you assessed that the contractor was eligible for 8 days, why would you consider the 15 day extension?

A

IMPARTIAL - only if instructed by the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you provide an example of one of the changes that came through the change control procedure?

A

EXAMPLE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What advise did you give to your client at the outset of the project with regard to the change control procedure used on the project?

A

Don’t make changes/reduce procedure - point of the pre-construction phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Where there any provisional sums included within the contract? Can you define a provisional sum?

A

YES

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When you have issued a interim payment certificate, what would you expect to be included?

A

Details of the date of valuation, details of the date of certification and the date of payment. Also, a breakdown of the valuation and how it was reached

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

With regards to the crane lift, who was responsible for managing the operations to allow the crane lift to take place?

A

The contractor was responsible for the management of the crane lift, including all coordination required. All of the details of which were contained within the CPHSP. The only element that the client was responsible for was the oversail agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you please clarify the project team and the budget for the works?

A

Architect, M&E Consultant, QS, PD, Catering Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How would you establish your client requirements?

A

Look at brief development

Feasibility - Cost appraisals, opportunities, risks, statutory requirements, site investigations, environmental impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What form part of a contractors application for payment?

A

Works + Materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Can you talk me through the process of payment for off-site materials?

A

SBC Clause

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a pay-less notice and when would it be issued?

A

Contract definition

17
Q

Explain the process used for monitoring the quality of the work?

A

Regular inspections, Contractor proposals/ERs, Tender documentation, Technical standards (link back to handbook)

18
Q

Talk me through the contractual confirmation of the issuing of the detail.

A

RFI response - 10 days later CI

19
Q

What is the architects liability for missing the detail within the tender documentation? Is there any re-course the client could have taken, and would C&W or the QS have been liable also?

A

LM to help

20
Q

What legislation would you expect to be adhered to in relation to the crane lift?

A

H&S at work - working at height

CDM

21
Q

What is your role in the project under CDM?

A

Designer

22
Q

Do you have to pursue damages as an express provision of the contract?

A

No

23
Q

Can damages be set at any level within the contract?

A

No - genuine pre-estimate of loss