Presentation Questions Flashcards
Under the SBC, how would you advise your client if the contractor was not actioning an contract instruction that had been issued?
Other contractors
You used the Without Quantities version of the SBC, Why did you choose that over the With Quantities version? Would you consider this to be the correct contract choice for this project?
Quantities based on the area not being complete. Perhaps the right contract, client familiarity. Also generally over £1m would be complex enough to require SBC.
What are the timescales involved in the acceptance of a contract instruction under SBC?
no. of days
What are the payment timescales under SBC?
5 days // 14 days
When issuing a extension of time, is an extension of the contractor’s preliminaries automatically included within the claim?
No - L&E
If you assessed that the contractor was eligible for 8 days, why would you consider the 15 day extension?
IMPARTIAL - only if instructed by the client
Can you provide an example of one of the changes that came through the change control procedure?
EXAMPLE
What advise did you give to your client at the outset of the project with regard to the change control procedure used on the project?
Don’t make changes/reduce procedure - point of the pre-construction phase
Where there any provisional sums included within the contract? Can you define a provisional sum?
YES
When you have issued a interim payment certificate, what would you expect to be included?
Details of the date of valuation, details of the date of certification and the date of payment. Also, a breakdown of the valuation and how it was reached
With regards to the crane lift, who was responsible for managing the operations to allow the crane lift to take place?
The contractor was responsible for the management of the crane lift, including all coordination required. All of the details of which were contained within the CPHSP. The only element that the client was responsible for was the oversail agreement.
Can you please clarify the project team and the budget for the works?
Architect, M&E Consultant, QS, PD, Catering Designer
How would you establish your client requirements?
Look at brief development
Feasibility - Cost appraisals, opportunities, risks, statutory requirements, site investigations, environmental impact
What form part of a contractors application for payment?
Works + Materials
Can you talk me through the process of payment for off-site materials?
SBC Clause