Preconstruction Activities Flashcards

1
Q

What are 2 ways a project can be open to bidders? How do you notify bidders for each?

A
  1. open to any contractor / advertisement for bids

2. restricted to a list of pre-qualified contractors / invitation to bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If you issue an addendum, when must it be transmitted to bidders?

A

at least 4-5 days before receipt of bids

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Per AIA A701, when is a bid considered late? What must be done with late bids?

A

A bid is considered late if it is received after the time and date established and it must be returned unopened, even if received before bids have been opened.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What should an architect announce at the bid opening?

What should an architect NOT announce?

A
  • submissions will be evaluated and decision of award will be made within 7-10 days
  • apparent lowest bid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What do Bidding Documents include?

A

Bidding documents: The documents required to bid or negotiate the construction contract, including the bidding requirements, contract forms, contract conditions, specifications, drawings, and addenda.

aka Bidding Requirements & Proposed Contract Documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What do the Bidding Requirements consist of?

A
  • advertisement or invitation to bid
  • instructions to bidders = AIA 701
  • supplementary instructions to bidders
  • the bid form
  • bid security information (bid bond)
  • performance and labor & material payment bond requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What do the Proposed Contract Documents consist of?

A
  • unexecuted O/C Agreement and Exhibits
  • Conditions of the Contract (General, Supplemental, and other)
  • Drawings
  • Specifications
  • Addenda
  • any other documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Per AIA A701, when should an Architect receive from bidders any requests for clarifications or interpretations of the bidding documents?

A

at least 7 days prior to receipt of bids

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Per AIA A701, when should an Architect receive from bidders substitution request?

A

at least 10 days prior to receipt of bids

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Per AIA A701, when must all addenda be issued?

A

no later than 4 days prior to receipt of bids

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the Project Manual? What does it include?

A

The volume usually assembled for the construction work, which may include:

  • Bidding Requirements
  • sample forms
  • conditions of the contract
  • specs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Does this describe CMa or CMc: multiple prime contractors may be used.

A

CMa

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Does this describe CMa or CMc: no bidding or negotiation; CM sets & guarantees guaranteed max price or control estimate.

A

CMc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Does this describe CMa or CMc: bidding or negotiation is used to set final price (aka no prices set by CM)

A

CMa

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Does this describe CMa or CMc: during construction both A and CM provide CA services.

A

CMa

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Does this describe CMa or CMc: only A provides CA services

A

CMc

17
Q

Does this describe CMa or CMc: Architect does NOT provide cost estimating services BUT, if CM’s estimate at end of DD exceeds Owner’s budget and O decides to revise the program, scope, or quality to reduce cost, the Architect must do so without additional compensation

A

both!

18
Q

In IPD, what are the pre-construction phases called?

A
  1. Agency Review: includes standard building code check by AHJ
  2. Buyout: process of selecting suppliers and finalizing price from any remaining subcontractors and vendors not part of IPD process
    - A may be required to answer questions and review prefab studies to ensure integrity of design intent
    - O/C are generally responsible for finalizing other bidding/negotiation efforts
19
Q

What are 3 basic methods of preparing budgets and estimating costs during programming/schematic phases?

A
  1. project comparison method
  2. area method
  3. assembly method / system method
20
Q

What is the Project Comparison Method? When should it be used? How accurate is it?

A

Cost of a project is estimated using costs of past projects of similar scope/function.

  • use EARLY, aka when setting a budget or determining feasibility.
  • typ accurate within 15-25%
21
Q

What is the Area Method? When should it be used? How accurate is it?

A

Average cost per unit of area or volume.

  • use when preliminary design is completed to have a better idea of project size, functional components, and level of quality/complexity
  • typ accurate within 5-15%
22
Q

What is the Assembly Method / System Method? When should it be used? How accurate is it?

A

Historical cost information is applied to each subsystem of the design (foundations, wall finishes, roofing, HVAC, etc), including markups for C’s overhead/profit and other construction admin costs

  • Use during SD, when more is known about space requirements and general configuration
  • Accuracy within 10%
23
Q

What are 3 methods to refine a project budget?

A
  1. Parameter method (sf)
  2. Matrix costing
  3. Unit cost method
24
Q

What is the Parameter Method? When should it be used? By who?

A

Involves expanded itemization of construction quantities and assignment of unit costs to these quantities (ie “floor finishes” → “carpeting, vinyl tile, wood, unfinished concrete, etc”)

  • Use in DD / early CD phases
  • Used most often by Architects to refind the construction budget
25
Q

What is the Matrix Costing method? When should it be used? By who?

A

Matrix shows various alternatives with individual elements that will contribute to final cost. Includes C’s overhead & profit

  • Use in DD
  • Architect
26
Q

What is the Unit Cost Method? When should it be used? By who?

A

Project is broken down into individual building components and labor needed to install them, including material & labor costs, cost of equipment/fees/services, C’s overhead & profit

  • Most accurate, but can only be used when CDs and specs are complete
  • Contractor use when determining bid or negotiated proposal
27
Q

What are 7 variables that determine a Contractor’s bid?

A
  1. Actual cost of subcontractor bids
  2. Cost of contractor’s own labor and materials
  3. Cost of equipment rental
  4. Contractor’s indirect costs
  5. Overhead
  6. Profit
  7. Construction marketplace
28
Q

What is an Alternate? What are 2 types of alternates?

A

A request included in bidding documents asking the contractor to supply a price for some type of variation from the base bid (ie change in material or level of quality, deletion or addition of a component)
- Seldom significantly lower total building cost since they represent a small percentage of large cost items

  1. Add Alternate = adds to base bid amount
  2. Deduct Alternate = deducts from base bid amount
29
Q

What are Unit Prices? When are they used?

A

Set costs for certain portions of work, based on an individual quantity

Used when full extent of portion of work is unknown (ie paving), so a unit cost (ie sf) for that component is requested

30
Q

What are Allowances?

A

A set amount of money estimated by the architect to cover a particular material or equipment when cost cannot be precisely determined at time of bid or negotiated proposal.

  • Stated in specifications
  • Contractor must add to allowance cost of unloading, handling, and installing item, and C’s profit/overhead
  • If actual cost differs from allowance, C’s sum is adjusted by a change order
31
Q

What is Value Engineering (VE) or Value Analysis?

A

An additional service that can be used prior to or after bidding, but is best used earlier in the design process.

32
Q

What are 6 factors that an architect should focus on during bidding that can affect Project Cost, quality, and schedule?

A
  1. marketplace
  2. short bidding period
  3. quality of documents (drawings and specs)
  4. construction methods
  5. short construction period
  6. proposed contract documents
33
Q

Contractor’s overhead and profit typically amount for what percentage of construction cost?

A

15-40%

34
Q

Construction work is divided among the construction trades in accordance with…

A

trade union rules.
the general contractor’s judgment.

NOT
the specifications.
the drawings.