Construction Observation and Administration Flashcards
Who reviews submittals in a CMa project delivery method?
CM and A
Who prepares change orders and construction change directives in a CMa project delivery method? Who must sign the change orders?
CM prepares
O/A/C + CM sign
Who reviews RFIs in a CMa project delivery method?
CM reviews and forwards to A with CM’s recommendations. A issues any supplemental drawings and specs required.
Through whom do O/C communicate during construction in a CMa project delivery method?
through CM with copies to A
What are 2 important meetings during CA?
- Preconstruction conference
2. Project meetings (OAC meetings)
How often does A visit the site during construction? Who decides how often A visits the site? What factors help determine frequency of A site visits?
At intervals appropriate to the stage of construction.
A decides based on:
- size and complexity of project
- type of construction contract used
- exact schedule of construction operations
What are 3 purposes of A’s site visits?
- to become generally familiar with the progress and quality of work & keep O informed
- to endeavor to guard O against defects and deficiencies in the work
- to determine if the work is progressing in such a way that it will be in accordance with contract documents
What is the form which A should use to make notes of observations from site visits?
Field report: AIA G711 Architect’s Field Report
What are 2 situations in which work may need to be uncovered?
- a portion of the work has been covered contrary to A’s request or to specific requirements in the contract documents
- A has not specifically made a request to view a portion of the work that has already been covered
If the uncovered work does conform to contract, who pays the cost?
Owner
If the uncovered work does not conform, who pays the cost?
Contractor
Who/what can require field tests?
Laws/regulations/code
Building departments
Contract documents
If testing is required by the contract documents, who:
- is responsible for arranging the testing agencies?
- pays for the test
- who must be given notice so they can observe the test?
Contractor arranges and pays for required tests.
Contractor must give Architect notice so A can come and observe.
If O/A or public authorities require testing beyond what is required in the contract documents, then:
- how is the testing arranged?
- who pays for the test?
- A instructs C to arrange for testing AFTER obtaining written authorization from O
- Owner pays for costs of testing
If testing is required by IBC, then:
- how is testing arranged?
- who pays for the cost?
- A is required to develop a Statement of Special Inspections and submit to the code official for review and approval
- O (or A as O’s agent) must engage a qualified independent special inspections firm (not C) to do the work
- A must submit the results of inspections/testing to the code official for evaluation and approval
- O pays for the cost
If testing shows that a portion of the work does not conform to contract documents, then who pays for the cost to correct the problem?
Contractor
** this includes additional testing and compensation for A’s services related to the issue
If E204 Sustainable Projects Exhibit is used, who registers the project with the certifying authority and submits application for sustainability certification to the certifying authority?
Architect
If E204 Sustainable Projects Exhibit is used, what should A notify Owner of in field report?
Any deviations from construction documents that may impact the sustainability measures or objective.
What are 3 causes for an accelerated schedule?
- Directed acceleration: Owner instructs C to accelerate work and agrees to pay additional costs through a change order
- Voluntary acceleration: C decides to accelerate work because:
- work has fallen behind original schedule
- C is trying to collect a bonus for finishing early
- C wants to move personnel to another job - Constructive acceleration: a situation occurs that causes an excusable or unavoidable delay (weather, deliveries, change orders, etc), but acceleration is not required by O/C
- C must determine how to accelerate work to meet the project deadline
- C may choose to file a claim for damage is extra time is warranted but not given, and C had to incure extra expenses to complete work on time