Practices questions Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q
  1. A project team member finds an issue not addressed in the LEED reference guide regarding indoor
    plumbing fixtures and submits a suggested approach to the credit during the standard LEED review
    process. What is true about this approach?
    A. They will receive a determination in the review comments at the discretion of the reviewer assigned
    to the project.
    B. The approach will be rejected because it is outside the scope of the review process
    C. The approach will be rejected and a Project CIR will need to be submitted instead
    D. If the approach is accepted it can be precedent-setting and can be used in future project reviews
A

A

When dealing with an issue not addressed in available LEED guidance material, project teams have the
option of submitting a suggested approach during the standard LEED certification process. They will
receive a determination in the review comments at the discretion of the reviewer assigned to the
project.

As with Project CIRs, decisions made in a particular project’s review are not precedent-setting and
therefore cannot be used in future project reviews.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. After project registration you find a credit the project is attempting is listed as applicable under the
    ‘Applicable credits’ section of the Interpretations database. What must the project team do?
    A. Review the interpretation and apply it if it makes sense to do so
    B. Submit a Project CIR
    C. Review the Addenda database
    D. Resubmit the credit
A

A

If a credit that a project is attempting is listed as applicable under the ‘Applicable credits’ section of the
interpretation, the team must review the interpretation and apply it if it makes sense to do so. LEED
project teams can choose to reference LEED Interpretations that do not list their credit as applicable if
the project team believes it is appropriate. A final determination will be made during the certification
review

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. A 10,000 SF tenant space is located in a 150,000 SF high-rise building. The project building includes
    underground parking and an attached parking deck. The tenant shares the parking with other building
    tenants. What would the certification fees be based on?

A. Project gross floor area, excluding parking
B. Project gross floor area, including parking
C. Building gross floor area, excluding parking
D. Building gross floor area, including parking

A

A

ID+C project fees exclude parking areas.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Which action is an example of an overlapping benefit that a project team might find during ongoing
    discovery while iteratively testing alternatives and refining an analysis?
    A. Using the waste heat from a mechanical system to heat hot water
    B. Deciding to increase ventilation by 30%
    C. Removing an underfloor air-distribution system due to cost
    D. Selecting one paint over another for aesthetic reasons
A

A

This is an example of looking for new opportunities in the design that support the project goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Which response is a possible consequence if a project does not comply with the minimum program
    requirements?
    A. An alternative compliance path may be used
    B. If the project has earned a LEED certification, the building’s certification may be revoked
    C. The project team may need to submit a CIR
    D. Additional fees or fines may be incurred
A

B

A project must adhere to the LEED Minimum Program Requirements (MPRs) in order to achieve/retain
LEED certification. Failure to comply with MPRs may result in the certification being revoked. No fees
will be refunded
A project can meet the MPRs prior to certification, then earn project certification, and then later
something may change so that the project no longer meets the MPRs. An example of this scenario is if
the occupancy rate of the building decreases.
Note that after the project is certified (has attained any LEED certification at any level), the project must
continue to meet the MPRs or certification can be revoked. For example, if a hotel is certified, and then
the hotel shuts down, the hotel is not maintaining the minimum occupancy levels required by the MPRs.
The certification could be revoked

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. If the requirements described on a credit form do not match the rating system and/or reference guide
    material, which action should a project team take next?
    A. Contact LEED technical customer service
    B. Submit a project CIR
    C. Submit a LEED interpretation
    D. Submit the issue via the feedback button within leedonline.com
A

D

If a project team needs guidance on an issue before submitting for certification review, the project CIR
process is available to them. The project CIR will be determined by a GBCI Certification Reviewer familiar
with the project’s specific circumstances. The advantage of a project CIR is that the timeline for a ruling
is relatively quick, and the project team can have certainty about the applicability of their strategy early
in the design or implementation process.

This type of formal inquiry is relevant to many projects. These are examples of inquires that, after
receiving a project CIR, would also result in a LEED interpretation if the project team opted into the
LEED-interpretations process.

For assistance with broken prerequisite/credit forms and/or functionality within leedonline.com, submit
issues via the feedback button, found on every page in leedonline.com.
The following are examples of LEED Online issues:
Requirements as described in the form do not match the rating system and/or reference guide material
or the project team member is having problems logging in, joining a team, or accessing projects or
credits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. When developing a LEED Scorecard, on which credits should the team focus first?
    A. Credits with the highest value for the project over the long term
    B. Credits that are the easiest to earn
    C. Credits that are the least expensive to earn
    D. Credits that are the most familiar to the project team members
A

A

The credits selected are primarily based on the goals set in the goal workshop. These goals are of the 
highest importance (and thus value) to the owner.
After picking the highest priority credits, select other credits that have synergies and reinforce the
project goals.
Then select additional credits that get the project to the desired target certification
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. A project has achieved one pilot credit, has earned exemplary performance in three credits, and has
    used a strategy for innovation. How many points would this project earn?
    A. 2
    B. 3
    C. 4
    D. 5
A

C

Innovation earns up to 4 points. The example earned 1.
Pilot credits earn up to 4 points. The example earned 1.
Exemplary performance earns up to 2 points. The example achieved 3 credits, but 2 points is the
maximum number that can be earned.
The maximum for the Innovation credit is 5 points.
One additional point can be earned for LEED AP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. A building owner inquires about how many LEED Pilot credits the project team can pursue. Which
    response is correct?
    A. The project team can pursue an unlimited number of Pilot credits; however, the number of points
    awarded will be limited by the number of Innovation credits.
    B. The project team can pursue only as many Pilot credits as there are Innovation credits.
    C. The project team can pursue an unlimited number of Pilot credits and earn points for every Pilot
    credit achieved.
    D. The project team can pursue up to five Pilot credits and can earn up to three Innovation credits.
A

A

LEED project teams may pursue an unlimited number of pilot credits; however, the number of points
awarded is limited by the number of Innovation credits available (up to 5 for LEED 2009 projects).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Which project strategy would earn an exemplary performance point under IN Credit Innovation
    Option 3 Additional Strategies?
    A. Doubling the highest transit service point threshold for alternative transportation
    B. Achieve a 30% energy savings
    C. Install advanced metering for the entire building
    D. Use 100% non-potable water for all flushing fixtures
A

A

LT Credit Access to Quality Transit can earn exemplary performance for doubling the highest transit
service point threshold.

EA Credit Optimize Energy Performance can earn exemplary performance for 32% or more energy
savings.

EA Credit Advanced Energy Metering doesn’t have exemplary performance.

WE Credit Indoor Water Use Reduction doesn’t have exemplary performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. What options within LEED credits address different geographic and climactic regions while providing
    solutions to challenges faced by projects at a regional level?
    A. Regional Alternative Compliance Paths
    B. Regional priority credits
    C. Innovation credits
    D. Minimum program requirements (MPRs)
A

A

These options address different geographic and climactic regions while providing solutions to challenges
faced by projects at a regional level. The first of these to be released are the Regional Alternative
Compliance Paths for projects using LEED for Existing Buildings: Operations and Maintenance in Europe.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. At a minimum how many potential locations or base building options must be assessed for IP Credit
    Integrative Process as part of the discovery phase for site selection?
    A. 1
    B. 2
    C. 3
    D. 4
A

B

At least two potential locations or base building options must be assessed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. At a minimum what must be analyzed for IP Credit Integrative Process for ID+C projects?
    A. Energy-related and water-related systems only
    B. Site selection and energy-related systems only
    C. Energy-related systems only
    D. Site selection, energy-related systems, and water-related systems
A

B

Site and energy are required and can earn one point, water earns one additional point.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
14. What design decision would have a negative environmental impact in a cooler climate?
A. Task lighting
B. Low-flow fixtures
C. Reflective roof panels
D. Indoor pest management
A

C

In colder climates, reflective roofing can increase the heating requirements when temperatures cool
because the reflective roof panels would reflect heat away from the building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. An office space will include individual occupant controls for lighting. What design strategy would
    most reduce the operational energy use associated with task lighting?
    A. Integrating individual controls with occupancy sensors
    B. Installing higher reflective surfaces
    C. Installing automatic shading devices on windows
    D. Increasing the glazing on windows
A

A

A common problem with task lighting is occupants leave the task lights on when they are away from
their desks, such as for lunch or when leaving for the day/weekend. Integrating task lighting with
occupancy sensors can reduce the energy costs the most.
Surfaces that reflect/absorb light can also have potential energy savings, but integrating task lighting
with occupancy sensors will have a greater impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. An office project will have a 3% energy improvement over a baseline building. The project team is
    considering increasing ventilation. The project uses mechanical ventilation. This change could have a
    negative impact on:
    A. EQ Credit Daylight
    B. EA Credit Optimize Energy Performance
    C. EA Prerequisite Minimum Energy Performance
    D. EA Prerequisite Fundamental Refrigerant Management
A

C

Increasing the ventilation of a building that uses mechanical ventilation will require a larger HVAC
system capacity and greater energy use. Since the baseline building energy performance would change,
EA Prerequisite Minimum Energy Performance will be impacted.
The building has a 3% energy performance improvement which is enough for the prerequisite but falls
short of the minimum for Optimize Energy Performance. Since the project cannot earn Optimize Energy
Performance, this credit will not be affected, but the prerequisite could be

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  1. A project team has hired a LEED consultant to assist them with their first LEED project. What will the
    consultant need to tell the project team to take photographs of if they choose to pursue those credits?
    A. LT Credit Surrounding Density and Diverse Uses
    B. LT Credit Access to Quality Transit
    C. WE Credit Indoor Water Use Reduction
    D. IEQ Credit Construction IAQ Management Plan
A

D

Construction Management IAQ Management Plan requires photos that highlight the implemented
construction IAQ practices.
LT Credit Surrounding Density and Diverse Uses does not require a photo, but a photo is one alternative
for providing the site vicinity plan. Sketches, block diagrams, and maps can also be used.
LT Credit Access to Quality Transit does not require photos.
WE Credits do not require photographs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
  1. If a project team is pursuing both IP Credit Integrative Process and EA Credit Optimize Energy
    Performance, which action should occur first?
    A. A basic energy analysis prior to conducting the energy simulation
    B. Creation of a baseline energy model
    C. Determination the energy costs savings
    D. Use of the exceptional calculation method for unregulated loads
A

A

For option 1 Whole-Building Energy Simulation, if projects are also pursuing the Integrative Process
credit, then the project team must identify the requirements for concept-level energy modeling to determine how to coordinate the overall model of development. The basic energy analysis for the
Integrative Process credit must be done before conducting the energy simulation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  1. A client is assessing the value LEED certification for an office project in a suburban area. All of the
    following are values and benefits of green building except:
    A. Higher property values
    B. Incentives for tax rebates and zoning allowances
    C. Faster lease-up rates
    D. Higher cost of ownership
A

D

LEED-certified buildings cost less to operate, reducing energy and water bills by as much as 40%.
Businesses and organizations across the globe use LEED to increase the efficiency of their buildings,
freeing up valuable resources that can be used to create new jobs, attract and retain top talent, expand
operations and invest in emerging technologies.
LEED buildings have faster lease-up rates and may qualify for a host of incentives like tax rebates and
zoning allowances. Not to mention they retain higher property values

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
  1. A project team has selected an office location in a LEED ND Certified neighborhood that will
    streamline the documentation of the LT credits. What additional documentation needs to be submitted
    for the LT Credit LEED for Neighborhood Development Location?
    A. Vicinity base map with the LEED project boundary and LEED ND certified neighborhood or plan
    boundary
    B. Parking map for the office occupants
    C. Bicycle map identifying bicycle routes for occupants
    D. Public transportation schedules and routes
A

A
EXPLANATION:

This is part of the required documentation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q
21. What is the maximum points a project can earn by selecting a tenant space in a LEED ND Platinum 
location?
A. 8
B. 10
C. 12
D. 18
A

D

18 points max for the credit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q
  1. A LEED AP is collecting information about a site that includes the dwelling units per acre (hectare)
    and total floor-area ratio per acre (hectare) of buildings in the surrounding area. What would this
    information be used for?
    A. LT Credit Surrounding Density and Diverse Uses Option 1 Surrounding Density
    B. LT Credit Surrounding Density and Diverse Uses Option 2 Diverse Uses
    C. LT Credit Reduced Parking Footprint
    D. LT Credit LEED for Neighborhood Development Location
A

A

Dwelling units and floor area ratio are part of the density calculations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q
  1. A LEED AP is documenting five uses within walking distance of the main entrance of an office
    building. What is an acceptable way to document LT Credit Surrounding Density and Diverse Uses?
    A. By including a map showing the project site, location and type of each use, and walking routes from
    the main entrance to each use.
    B. By uploading a project narrative that includes each use name, use type, and address
    C. By creating a map showing the project, project boundary, and walking routes and longitude and
    latitude of each use.
    D. By using the area plan or map to show the project site and location of existing and planned uses
    within a quarter-mile (400-meter) radius of the project site.
A

A

This is how the credit is documente

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q
  1. A project has the following transit service summary:
    Light rail:
    80 weekday trips
    60 Saturday trips
    50 Sunday trips
    Commuter rail:
    40 weekday trips
    12 Saturday trips
    0 Sunday trips
    Given this information, which statement is true about the transit service and the project’s ability to earn
    LT Credit Access to Quality Transit?
    A. The commuter rail would count as having no weekend trips.
    B. The light rail service does not provide enough weekend trips.
    C. The light rail service does not provide enough weekday trips.
    D. The commuter rail weekend trips can be averaged to meet the minimum required.
A

D

The weekend trips can be averaged to 6 to meet the requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q
  1. A project team is reviewing potential sites that have a diversity of transit routes. Which site feature
    would help the project earn more points for LT Credit Access to Quality Transit?
    A. A site served by a bus route and a light rail route for which no one route provides more than 60% of
    the total trips
    B. A site served by light rail that has double the required weekend trips
    C. A site served by a bus route, light rail, and commuter route
    D. A site served by multiple transit types all within a 1/4-mile (400 meters) of any functional entry
A

A

A site that has multiple transit types which do not provide more than 60% of the trips can earn the
project more points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q
  1. A retail clothing project is located in a mall. All of the following would help the project earn LT Credit
    Bicycle Facilities EXCEPT:
    A. Two short term storage spaces
    B. Two long term storage spaces
    C. Coupons for yearly bicycle tune-ups
    D. Map identifying bicycle routes to the project site
    E. Shower
A

E

Retail projects require programs to support bicycle use that must be documented. A bicycle
maintenance or route assistance program is required in addition to two short and two long-term spaces.
Showers are not required for retail projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q
  1. A 2,500 SF (233 m2) store pursuing LEED ID+C: Retail is located near a bicycle network. All of the
    following design decisions would contribute to earning LT Credit Bicycle Network EXCEPT:
    A. On-site supplies for bicycle repair
    B. Bicycle route map posted on the front window for employees and customers
    C. 2 long-term bicycle storage spaces located within 100 feet (30 meters) of the main entrance
    D. 2 short-term bicycle storage spaces located within 100 feet (30 meters) of the employee entrance
A

D

Short term storage must be located near any main entrance. An employee entrance would not be
accessible to customers and is thus not a main entrance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q
  1. A 500,000 SF (46,500 m2) office building pursuing LEED ID+C: Commercial Interiors has 102 regular
    building occupants and 40 peak visitors. How many shower facilities are required for LT Credit Bicycle
    Facilities?
    A. 0
    B. 1
    C. 2
    D. 3
A

C
1 shower/changing room for the first 100 regular building occupants and 1 shower for every 150 more.
They key here is regular building occupants. Visitors don’t count in the calculation. The other point to
remember is to always round up.
The office space has 102 regular building occupants. The first 100 require 1 shower. The next 150
require 1 more. Since we have 102, 2 showers are required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q
  1. When determining the total vehicle parking capacity for a site, which information should be
    included?
    A. Off-street parking available to the project building’s users outside of the project boundary
    B. On-street parallel parking spaces on public rights of way
    C. Motorbike spaces
    D. Parking spaces for fleet vehicles
A

A

See Further Explanation / Total Vehicle Parking Capacity in the reference guide for a full list of how
parking capacity is calculated.

30
Q
  1. In an urban area an existing building has a parking deck with 200 parking spaces. A project for an
    office adjacent to the parking deck will be allowed to share 100 of these spaces. When determining the
    parking capacity for the project, how should the parking capacity be calculated?
    A. By including all 200 spaces
    B. By only including the 100 shared spaces
    C. By not including any of the spaces
    D. By only including the shared spaces less any handicap or preferred parking spots
A

B

When buildings pool parking, include the number allocated for the project

31
Q
  1. A 2,500 SF (233 m2) store pursuing LEED ID+C: Retail is located near a bicycle network. All of the following
    design decisions would contribute to earning LT Credit Bicycle Network EXCEPT:
    A. 2 short-term bicycle storage spaces located within 100 feet of the employee entrance
    B. 2 long-term bicycle storage spaces located within 100 feet of the main entrance
    C. Bicycle route map posted on the front window for employees and customers
    D. On-site supplies for bicycle repair
A

Answer: A. 2 short-term bicycle storage spaces located within 100 feet (30 meters) of the employee
entrance. Short term storage must be located near any main entrance. An employee entrance would not be
accessible to customers and is thus not a main entrance

32
Q
  1. A 6-story office space will be located in an arid region. Installing occupancy sensors would not
    impact which credit?
    A. EQ Prerequisite Minimum IAQ Performance
    B. EA Credit Optimize Energy Performance
    C. EQ Credit Enhanced IAQ Strategies
    D. EQ Credit Thermal Comfort
A

Answer: C. EQ Credit Enhanced IAQ Strategies. Occupancy sensors are not part of monitoring outdoor air
delivery.

33
Q
  1. A 10,000 SF tenant space is located in a 150,000 SF high-rise building. The project building
    includes underground parking and an attached parking deck. The tenant shares the parking with
    other building tenants. What would the certification fees be based on?
    A. Project gross floor area, excluding parking
    ID+C project fees exclude parking areas.
    B. Building gross floor area, excluding parking
    C. Project gross floor area, including parking
    D. Building gross floor area, including parking
A

Answer: A. Project gross floor area, excluding parking ID+C project fees exclude parking areas.

34
Q
  1. A 10-story office building will have many tenant spaces. A building owner and engineer are
    reviewing potential building automation systems for advanced energy metering to allow the
    owner to educate tenants about the energy use their tenant space is using. The team has found a
    system that uses a wireless network, will store all meter data for at least 36 months, and can be
    remotely accessible. What else will need to be included for EA Credit Advanced Energy
    Metering?
    A. Each floor of the building must be submetered separately
    B. Energy meters must record data hourly, daily, monthly, and annually
    C. Each tenant space must be submetered
    D. Each tenant must reduce their energy use by at least 10% for any individual energy end use
A

Answer: B. Energy meters must record data hourly, daily, monthly, and annually

  • The meters must record data at these frequencies at least.
  • The meters must also be permanent and record consumption and demand.
  • The data must have remote access.
  • Data collection must be networked (wireless, wired, cellular).
  • Data collection must be stored for at least 36 months.
35
Q
  1. A 50,000 SF (4,645 m2) retail project has a baseline parking capacity of 4 parking spaces /1,000 SF (4.3/100 m2) from the ITE handbook. The project will earn 1 point under LT Credit
    Surrounding Density and Diverse Uses and 1 point under LT Credit Access to Quality Transit.
    Which is the maximum number of parking spaces the project can have and still earn LT Credit
    Reduced Parking Footprint
A. 200 spaces
B. 80 spaces
C. 40 spaces
D. 120 spaces
E. 160 spaces
A

Answer: D. 120 spaces
- A 20% reduction is required for projects that DO NOT earn points under LT Credit Surrounding Density
AND Diverse Uses and LT Credit Access to Quality Transit.
- A 40% reduction is required for projects that DO earn points under LT Credit Surrounding Density OR
Diverse Uses and LT Credit Access to Quality Transit.
50,000 SF / 1,000 SF = 50 X 4 spaces = 200 space baseline
200 spaces X 40% = 80 space
REDUCTION = 120

36
Q
  1. A 50,000 SF (4,645 m2) retail project has a baseline parking capacity of 4 parking spaces / 1,000 SF
    (4.3/100 m2) from the ITE handbook. The project will earn 1 point under LT Credit Surrounding Density and
    Diverse Uses but not earn LT Credit Access to Quality Transit. The project includes off-street parking. How
    many preferred parking spaces for carpools must the project includes for LT Credit Reduced Parking
    Footprint?
    A. 3 spaces
    B. 5 spaces
    C. 6 spaces
    D. 4 spaces
A

Answer: C. 6 spaces
50,000 SF / 1,000 SF = 50 X 4 parking spaces = 200 space baseline
200 space baseline from the ITE handbook X 60% (40% reduction)
= 120 total spaces
120 spaces X 0.5% preferred parking = 6 spaces

37
Q
  1. Achieving the greatest effectiveness in cost and environmental performance requires that every issue and
    every team member be brought into the project at which of the following points?
    A. Design and construction
    B. Preliminary LEED review
    C. Occupancy, operations, and performance feedback
    D. Discovery
A

Answer: D. Discovery. During the Discovery phase is when everyone needs to gather their ideas and
consider synergies across LEED credits.

38
Q
  1. Achieving the greatest effectiveness in cost and environmental performance requires that every issue
    and every team member be brought into the project at which of the following points?
    A. Preliminary LEED review
    B. Discovery
    C. Occupancy, operations, and performance feedback
    D. Design and construction
A

Answer: B. Discovery. During the Discovery phase is when everyone needs to gather their ideas and
consider synergies across LEED credits

39
Q
  1. After an office space was completed in June, a project team took daylight measurements in all regularly
    occupied spaces. Which action must occur for the project to earn EQ Credit Daylight?
    A. The team must submit a list of compliant spaces with their annual summary values for SDA and ASE.
    B. A daylight modeler must be hired to confirm the results of the measurements.
    C. A narrative must be written listing the compliant spaces with their calculated illuminance values.
    D. A second set of measurements must be taken in October to determine compliant floor areas.
A

Answer: D. A second set of measurements must be taken in October to determine compliant floor areas.

40
Q
  1. After project registration you find a credit the project is attempting is listed as applicable under the
    ‘Applicable credits’ section of the Interpretations database. What must the project team do?
    A. Review the Addenda database
    B. Submit a Project CIR
    C. Resubmit the credit
    D. Review the interpretation and apply it if it makes sense to do so
A

Answer: D. Review the interpretation and apply it if it makes sense to do so.
If a credit that a project is attempting is listed as applicable under the ‘Applicable credits’ section of the
interpretation, the team must review the interpretation and apply it if it makes sense to do so. LEED project
teams can choose to reference LEED Interpretations that do not list their credit as applicable if the project
team believes it is appropriate. A final determination will be made during the certification review.

41
Q
  1. After the owner documents their owner’s project requirements (OPR), the project team will take that
    document to create the basis of design (BOD). What would be contained in the BOD?
    A. Energy efficiency goals, number of occupants, building schedule
    B. Systems and assemblies, governing codes and standards, performance criteria and assumptions
    C. Functional testing, training requirements, issue resolution process
    D. Operating mode tests, sustainability goals, occupant functions
A

Answer: B. Systems and assemblies, governing codes and standards, performance criteria and assumptions

42
Q
  1. All EXCEPT which documentation can be used to report the material ingredients of a product to at least
    0.1% (1000 ppm)?
    A. Health product declarations (HPD)
    B. Type III EPD
    C. Manufacturer inventory
    D. Cradle-to-Cradle analysis
A

Answer: B. Type III EPD. EPDs are not for material ingredient reporting.

43
Q
  1. The architect and other project designers are reviewing material choices for a new office space. Which
    reused materials will NOT contribute to optimization of MR Credit Building Product Disclosure and
    Optimization - Sourcing of Raw Materials?
    A. Furniture that has been leased for 1-year
    B. Cabinets
    C. Beams
    D. Decorative items
A

Answer: A. Furniture that has been leased for 1-year in the case of an owner moving to a new site furniture
that is leased must have been in service for 2-years to count in the current project.

44
Q
  1. As an alternative refrigerant to HCFC a project team is considering HFC-410A. What is the trade-off to
    when using HFC-410A in the HVAC&R system?
    A. It has a higher GWP than HCFC
    B. It has a high flammability
    C. It has a lower refrigerant charge
    D. May require more energy to achieve the same level of cooling as HCFC
A

Answer: D. May require more energy to achieve the same level of cooling as HCFC. It has a lower GWP but
require more energy to achieve the same level of cooling.

45
Q
  1. At a minimum what must be analyzed for IP Credit Integrative Process for ID+C projects?
    A. Energy-related and water-related systems only
    B. Energy-related systems only
    C. Site selection and energy-related systems only
    D. Site selection, energy-related systems, and water-related systems
A

Answer: C. Site selection and energy-related systems only Site and energy are required and can earn one
point, water earns one additional point.

46
Q
  1. At a minimum what must be analyzed for IP Credit Integrative Process for ID+C projects?
    A. Site selection, energy-related systems, and water-related systems
    B. Site selection and energy-related systems only
    C. Energy-related systems only
    D. Energy-related and water-related systems only
A

Answer: B. Site selection and energy-related systems only. Site and energy are required and can earn one
point, water earns one additional point.

47
Q
  1. At which point during a project schedule is the Basis of Design created?
    A. During pre-design phase
    B. At the Cx kickoff meeting
    C. The same time the Cx report is created
    D. During the schematic-design phase
A

Answer: D. During the schematic-design phase

48
Q
  1. At which point in a project’s schedule must the commissioning authority be engaged?
    A. By the end of the design-development phase
    B. By the end of the schematic-design phase
    C. During the pre-design phase
    D. Prior to completion of the Basis of Design (BOD)
A

Answer: A. By the end of the design-development phase

The prerequisite requires engagement by the end of the design development phase.

49
Q
  1. Before construction documents are written for an office project, the project team makes some design
    modifications as a result of value engineering. Who will be responsible for updating the Owner’s Project
    Requirements?
    A. The owner(s)
    B. The design team
    C. The architect(s)
    D. The CxA
A

Answer: A. The owner(s). The owner is responsible for updating the OPR throughout the project if changes
are made. The design team is responsible for the BOD. The CxA is responsible for the Cx plan.

50
Q
  1. A building contractor with limited space on the project site has one construction and wastemanagement bin that commingles concrete, wood, and drywall, as well as a separate bin for land-clearing
    debris. A waste hauler
    takes the dumpsters and separates the concrete, wood, and drywall off site for recycling. Given this
    information, which statement is true?
    A. The concrete, wood, and drywall are considered one waste stream, and
    the land-clearing debris is not counted as one waste stream.
    B. The concrete, wood, and drywall are counted as three waste streams, and the land clearing debris is counted as one waste stream.
    C. The materials are counted as two waste streams.
    D. None of the materials are counted as a waste stream.
A

Answer: A. The concrete, wood, and drywall are considered one waste stream, and the land-clearing debris
is not counted as one waste stream. ADC and land-clearing debris are not counted as waste streams. For
LEED, a waste stream should constitute at least 5% by weight or volume of the project’s totaled diverted
waste. The waste stream can be a material category that is diverted or a mixture of several material
categories that are diverted. The commingled materials count as one stream even though the hauler
separates them out later
off site

51
Q
  1. A building has an existing brick enclosure and steel structure with no drywall or interior finish. How many
    layers would the project team count in reuse calculations?
    A. 2
    B. 3
    C. 1
    D. 0
A

Answer: A. 2
The brick and steel surfaces would count. Up to 3 layers can be counted. For example, if a wall has brick,
steel framing, and drywall, the surface area of all 3 layers can be counted.

52
Q

22.A building owner inquiries about how many LEED Pilot credits the project team can pursue. Which
response is correct?
A. The project team can pursue up to five Pilot credits and can earn up to three Innovation credits.
B. The project team can pursue only as many Pilot credits as there are Innovation credits.
C. The project team can pursue an unlimited number of Pilot credits; however, the number of points
awarded will be limited by the number of Innovation credits.
D. The project team can pursue an unlimited number of Pilot credits and earn points for every Pilot credit
achieved.

A

Answer: C. The project team can pursue an unlimited number of Pilot credits; however, the number of
points awarded will be limited by the number of Innovation credits. LEED project teams may pursue an
unlimited number of pilot credits; however, the number of points awarded is limited by the number of
Innovation credits available (up to 5 for LEED 2009 projects).

53
Q
  1. A chair has the following components, weight percentages, and sustainability criteria:
    Cotton fabric 5% certified by Rainforest Alliance
    Plastic seat 30% none
    Steel frame 65% 40% pre-consumer recycled content
    The chair cost $100. What is the total product value as it applies to Building Product Disclosure and
    Optimization credit?
    A. $70
    B. $0
    C. $31
    D. $26
A
Answer: C. $31
The product value is based on the weight of the components that meet the sustainability criteria as a
percent of the total product weight.
Total product cost ($) X % product component by weight X (%) meeting sustainable criteria
$100 X 5% X 100% = $5
$100 X 30% X 0% = $0
$100 X 65% X 40% = $26
= $31
54
Q
  1. The classification of a sink in a project is unclear. Which action should the LEED AP take when
    performing the indoor water-use calculations?
    A. Exclude the sink from the calculations
    B. Choose the greater of the public or private baselines
    C. Classify the sink as public
    D. Classify the sink as private
A

Answer: C. Classify the sink as public If the classification for public or private use is unclear, default to public
use flow rates when performing the calculations.

55
Q
  1. Commercial kitchen dishwashers must meet what requirement in a hospitality project to earn additional
    points for WE Credit Indoor Water Use Reduction?
    A. Less than or equal to 1.6 gallons per rack (6.0 liters per rack)
    B. Less than or equal to 8 gallons water use per hour (7.5 liters per hour)
    C. Maximum 2 gpm (7.6 lpm) water use
    D. ENERGY STAR or performance equivalent
A

Answer: D. ENERGY STAR or performance equivalent
Note the prerequisite and credit have different requirements for dishwashers. For the credit ENERGY STAR
ratings are required to earn points. For the prerequisite maximum rates exist.

56
Q
  1. The commissioning authority, with the help of the design team and contractors, is writing functional test
    scripts for a new school building. Which order will the test scripts typically follow?
    A. The performance criteria in the Owner’s Project Requirements (OPR)
    B. The sequence of operations developed by the engineers
    C. The design-development guidelines in the Basis of Design (BOD)
    D. The startup, programming, and testing done by the contractor
A

Answer: B. The sequence of operations developed by the engineers Test scripts typically follow the
sequence of operations created by the engineers.

57
Q
  1. A construction waste-management plan must establish diversion goals, target at least how many
    materials to be diverted, and explain diversion plans for those materials?
    A. Five materials (both structural and nonstructural)
    B. Three materials (structural or nonstructural)
    C. Four materials (nonstructural only)
    D. Five materials (nonstructural only)
A

Answer: A. Five materials (both structural and nonstructural)
Five (5) material streams (both structural and nonstructural) must be diverted.

58
Q
  1. A contractor is planning for an occupied flush-out to reduce IAQ problems from the construction of an
    office. The contractor introduces 3,500 cubic feet of outdoor air per square foot of floor area 3 hours prior to
    the first occupants arriving. What will need to be done next to achieve EQ Credit Construction IAQ
    Assessment?
    A. Conduct a baseline IAQ test
    B. Continue the flushout until a total of 14,000 cubic feet per square foot of outside air has been delivered to
    the space
    C. Flush out the space with 3,500 cubic feet of outside air per square foot of floor area each day for a period
    of 7 days
    D. Nothing, the flush-out is complete
A

Answer: B. Continue the flushout until a total of 14,000 cubic feet per square foot of outside air has been
delivered to the space. For an occupied flush-out 3,500 cu. ft. air / sq. ft. must be used prior to occupancy.
Ventilation must begin at least 3 hours prior to occupancy until a total of 14,000 cu. ft. air / sq. ft. of air has
been introduced. Option 1 Path 2 still requires a total volume of air of 14,000 cu. ft. / SF to earn the credit,
after the initial 3,500 has been introduced.

59
Q
  1. A CxA has been selected who is a subcontractor of the general contractor with construction
    responsibilities. What tasks do not need to be performed for fundamental commissioning?
    A. Develop and incorporate commissioning requirements into the construction documents
    B. Envelope commissioning
    C. Complete a summary commissioning report
    D. Review the basis of design
A

Answer: B. Envelope commissioning

Envelope commissioning is part of Enhanced Commissioning, not Fundamental Commissioning

60
Q
  1. A CxA is developing an ongoing Cx plan as part of a ten-month review. Which information must be
    included in the ongoing Cx plan? (pick 3)
    A. Blank functional performance tests
    B. Trends in building operations
    C. Direction on how to test any retrofitted equipment
    D. Seasonal testing results
    (Seasonal testing is part of the commissioning process)
    E. A schedule for recommissioning as-built systems
    F. Interviews with occupants
    (This is part of the ten-month review
A

Answer: A. Blank functional performance tests
C. Direction on how to test any retrofitted equipment
E. A schedule for recommissioning as-built system

61
Q
  1. The CxA is working with the building owner to outline the requirements of a systems manual for EA
    Credit Enhanced Commissioning. What should the systems manual include?
    A. As-built drawings, equipment operations and maintenance manuals, final commissioning report
    B. Equipment preventative maintenance schedules, minimum outside air requirements, construction
    checklists
    C. Recommended schedule for recommissioning, basis of design, issues log
    D. As-built sequence of operations, defined roles and responsibilities, blank testing materials
A

Answer: A. As-built drawings, equipment operations and maintenance manuals, final commissioning report.
See Step-by-step guidance for the complete list of what goes into a systems manual.

62
Q
  1. The CxA is working with the building owner to outline the requirements of a systems manual for EA
    Credit Enhanced Commissioning. What should the systems manual include?
    A. Recommended schedule for recommissioning, basis of design, issues log
    B. Equipment preventative maintenance schedules, minimum outside air requirements, construction
    checklists
    C. As-built sequence of operations, defined roles and responsibilities, blank testing materials
    D. As-built drawings, equipment operations and maintenance manuals, final commissioning report
A

Answer: C. As-built sequence of operations, defined roles and responsibilities, blank testing materials.

63
Q
  1. The design team in a charrette is discussing an office project that will be located in a hot southern
    climate. What building attributes best address occupant comfort, reduced cooling loads, and lighting? (pick
    2)
    A. Light shelves
    B. Building fenestration
    C. Photovoltaic membranes
    D. Glazing
A

Answer:
B. Building fenestration
D. Glazing
Building fenestration impacts occupant comfort by the quantity of heat let in from these openings. Glazing
affects the heat let into the building (occupant
comfort and cooling load) and lighting. Light shelves will help but the building fenestration will make a
greater impact and is therefore a better choice.

64
Q
  1. A design team is working on water use reduction strategies for a new LEED ID+C: Hospitality project.
    What could the project team include to help reduce appliance and process water use for WE Prerequisite
    Indoor Water Use Reduction?
    A. Garbage disposals
    B. Undercounter 1.6 gallon/rack (6.0 liters/rack) dishwasher
    C. Use of municipal supplied recycled water to offset potable water use
    D. ENERGY STAR refrigerator
A

Answer: B. Undercounter 1.6 gallon/rack (6.0 liters/rack) dishwasher. Retail and Hospitality projects have
additional requirements for water-consuming appliances, equipment, and processes. Dishwashers, food
steamers, and combo ovens must meet the standards for appliances.

65
Q
  1. A developer for an office project in an urban area is reviewing potential sites that would reduce vehicle
    distance traveled. Which site would help with this goal and with achieving LT Credit Bicycle Facilities?
    A. A site within 3 miles bicycling distance to 10 diverse uses on a bicycle network
    B. A site adjacent to an existing 10-mile mountain biking trail
    C. A site adjacent to an existing bicycle network that connects to a jobs center 8-miles away
    D. A site within a 1/4-mile walking distance of a bicycle network that connects to a light rail station within a
    1-mile bicycling distance.
A

Answer: A. A site within 3 miles (4800-meters) bicycling distance to 10 diverse uses on a bicycle network

66
Q
  1. A developer for an office project in an urban area is reviewing potential sites that would reduce vehicle
    distance traveled. Which site would help with this goal and with achieving LT Credit Bicycle Facilities?
    A. A site within a 1/4-mile walking distance of a bicycle network that connects to a light rail station within a
    1-mile bicycling distance.
    B. A site adjacent to an existing bicycle network that connects to a jobs center 8-miles away
    C. A site within 3 miles bicycling distance to 10 diverse uses on a bicycle network
    D. A site adjacent to an existing 10-mile mountain biking trail
A

Answer: C. A site within 3 miles bicycling distance to 10 diverse uses on a bicycle network
Design or locate the project such that a functional entry and/or bicycle storage is within a 200-yard walking
distance or bicycling distance from a bicycle network that connects to at least one of the following:
- at least 10 diverse uses
- a school or employment center, if the project total floor area is 50% or more residential or
- a bus rapid transit stop, light or heavy rail station, commuter rail station, or ferry terminal.
*All destinations must be within a 3-mile (4800-meter) bicycling distance of the project boundary.

67
Q
  1. A developer is considering retail space located in an area with the following uses:
    Services Category: 2 restaurants, 1 bank, 1 laundromat Community-Serving Retail Category: 1 pharmacy
    Given this information, which statement is true about the project’s ability to earn LT Credit Surrounding
    Density and Diverse Uses?
    A. The project would earn the credit.
    B. The project would earn the credit if another use in any category was within walking distance.
    C. The project would not earn the credit because the supermarket cannot count as a service.
    D. The project could earn the credit if another use in a different category was within walking distance.
A

Answer: D. The project could earn the credit if another use in a different category was within walking
distance.
Here are the important points to remember about uses:
- A minimum of 4 uses
- A use type only counts once
- Uses must come from at least 3 of the 5 categories, exclusive of the building’s primary use
- No more than two uses of each type
- Uses that are planned count if they are available within one year of LEED occupancy.

68
Q
  1. During the construction phase a contractor has painted a wall with high VOC paint. What is the process
    to use to correct the error or submit information to qualify for EQ Credit Low-Emitting Materials?
    A. Paint over the high VOC paint with an approved low VOC paint
    B. Include the volume of high VOC paint in both the baseline and design case VOC calculations
    C. Subtract the high VOC paint from any calculations
    D. Subtract the high VOC paint from the design case calculations
A

Answer: B. Include the volume of high VOC paint in both the baseline and design case VOC calculations.
VOC budgets require a baseline and design case.

69
Q
39. Each item would be developed for EA Prerequisite Fundamental Commissioning and Verification except
which of the following?
A. A simple box energy model
B. Current facilities requirements
C. An operations and maintenance plan
D. A commissioning report
A

Answer: A. A simple box energy model. This is created as part of the Integrative Process credit.
In addition to these documents, the OPR and BOD are created for the prerequisite.

70
Q
  1. Early in a design process what does a project team need to ensure that the tenant space complies with
    for EA Prerequisite Minimum Energy Performance? (pick 3)
    A. Reduced lighting power density
    B. HVAC efficiency
    C. ASHRAE 90.1-2010 compliance
    D. Glazing systems
    E. ENERGY STAR products
A

Answer: A. Reduced lighting power density
C. ASHRAE 90.1-2010 compliance
E. ENERGY STAR products
The correct choices are the minimum required for certification. The other choices are optional for the credit