Practice-Wide Delivery of Services (PcM) Flashcards

PcM

1
Q

What factor most often determines the design method used to produce a project?

A

Cost is a frequent factor in determining this process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a control estimate?

A

This estimate is the construction manager’s estimate of the cost of the work plus the construction manager’s fee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the term for the concept of combining the design-bid-build process and the design- build process?

A

Bridging combines these two processes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What kind of project delivery system might be preferred by a real estate developer?

A

Design- build project delivery system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What options are availble to an architect if the owner’s budget is lower than the architect’s estimated cost but the project would be a good addition to the firm’s portfolio?

A

Reducing the profit margin and limiting the scope of work or the project might be responses to this situation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the architect’s options if the architect’s fee exceeds the amount budgeted by the owner?

A

In this case, the architect can propose to reduce the scope of the project or the scope of his or her services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What financial stake does an architect have in a typical design-bid-build project?

A

As the agent for the owner, an architect has no financial stake in this type of project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the owner’s obligations if the owner chooses to contract directly with the architect’s consultants?

A

If the owner chooses to do this, the owner must be directly involved with the work of the consultants.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What additional construction contract administration responsibilities does the owner assume in the design-build process?

A

These are all the owner’s responsibilities, not the architect’s, in this construction delivery method.
* Reviewing and approving submittals
* Approving changes
* Visiting the site
* Rejecting non-conforming work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

During the predesign phase, the architect should be involved with what team-building activity?

A

The architect needs to assemble and coordinate a team of professional consultants during this phase of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What steps should an architect take before signing a contract with a new client?

A
  • Determine the budget and scope of work
  • Verify that the project is a good fit for the abilities and experience of the firm.
  • Investigate the reputation and reliability of the client
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the advantages of fast-tracking?

A

The advantages of this delivery method are
* Reduced time
* Lower budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why would a client hire a construction manager as an adviser (CMa)?

A

Reason to hire a construction manager as an adviser
* Determine the constructability of the design
* Provide early cost estimating
* Provide value analysis
* Determine scheduling
* Assist with contract negotiations
* Manage mulitple construction contracts
* Make early material purchases
* In some cases, provide guaranteed price and completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What should an architect do if asked to replace another architect on a project?

A

Before an architect can begin this process, the first thing that the architect needs to determine is whether a contractual relationship exists between the owner and the first architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly