Practice Test Questions Flashcards
Producing a project plan may BEST be described as:
A) Creating a network logic diagram that identifies the critical path
B) Using a software tool to track schedule, cost and resources
C) Creating a document that guides project plan execution
D) Creating a plan that contains the entire product scope
C) Creating a document that guides project plan execution
Project management plan updates are NOT an output of: A) Perform Integrated Change Control B) Develop Project Management Plan C) Direct and Manage Project Work D) Monitor and Control Project Work
B) Develop Project Management Plan
You are meeting with a new project manager who has taken over a project that is in the middle of executing. The previous project manager has left the company and the new project manager is upset that change requests are streaming in from numerous sources including his boss, the customer, and various stakeholders. The project manager is not even aware of how to process all of these incoming change requests. Where would you refer him?
A) Project Scope Statement
B) Project Management Plan
C) The previous project manager
D) Project Charter
B) Project Management Plan
Centurion Corp has initiated a new project to modernize their HR Records and to bring them into compliance. A manager at Centurion is drafting the project charter for review. which of the following would be the most important item that she would need in order to complete this task and why?
A) Managerial approval to proceed, because it may affect whether or not the project moves forward
B) A scope statement, because it will set the parameters for he product scope
C) A scope statement, because it will set the parameters for the project scope
D) A business case, because it explains the justification for the project
D) A business case, because it explains the justification for the project
The project charter is:
A) Developed before the project statement of work, and after the project management plan
B) Developed after the project statement of work, and before the project management plan
C) Developed before the contract, and after the project management plan
D) Developed before the contract, and before the project management plan
B) Developed after the project statement of work, and before the project management plan
The project management information system would likely include all of the following except:
A) A scheduling tool
B) An information distribution System
C) A system for collecting information from team members
D) A system for identifying stakeholders
D) A system for identifying stakeholders
A defect in the product was brought to the project manager’s attention, and not the project team is engaged in repairing it. Which project management process would be the most applicable to this?
A) Perform Integrated Change Control
B) Monitor and Control Project Work
C) Direct and Manage Project Work
D) Close Project or Phase
C) Direct and Manage Project Work
If you are creating a single document to guide project execution, monitoring and control, and closure, you are creating: A) The execution plan B) The project management plan C) The integration plan D) The project framework
B) The project management plan
Change control meetings are held as part of which process?
A) Direct and Manage Project Work
B) Monitor and Control Project Work
C) Perform Integrated Change Control
D) Evaluate Requested Changes
C) Perform Integrated Change Control
Which of the following statements is not true regarding the project charter?
A) The project charter justifies why the project is being undertaken
B) The project charter assigns the project manager
C) The project charter specifies any high-level schedule milestones
D) The project charter specifies what type of contract will be used.
D) The project charter specifies what type of contract will be used.
Which of the following represents the project manager’s responsibility regarding change on a project?
A) Influence the factors that cause project change
B) Ensure all changes are communicated to the change control board
C) Deny change wherever possible
D) Prioritize change below results
A) Influence the factors that cause project change
The project management plan is made up of:
A) The other planning outputs
B) The other planning outputs, tools and techniques
C) The aggregate outputs of approved software tools
D) The business case, key value justification and the GANTT chart
A) The other planning outputs
When changes are approved and made to the project, they should be:
A) Tracked against the project baseline
B) Incorporated into the project baseline
C) Included as an addendum to the project plan
D) Approved by someone other than the project manager
B) Incorporated into the project baseline
Which statement about the project statement of work is true?
A) The project statement of work is generally used to define the business case for the project
B) The project statement of work is generally created only when one or more portions of the project are being procured from outside the organization
C) The project statement of work is generally created before the project is formally initiated
D) The project statement of work is generally considered to be an enterprise environmental factor
C) The project statement of work is generally created before the project is formally initiated
The project statement of Work is an input into the process Develop Project Charter, which formally kicks off the project. This means that the charter is created before there is even an official project.
Work performance information is used for all of the following reasons except:
A) It provides information on resource utilization
B) It provides information on which activities have started
C) It shows what costs have been incurred
D) It is used to help identify defects
D) It is used to help identify defects
The work performance information is all about how the work is being performed, but it is not used in identifying defects.