PMP Exam Guide Glossary Flashcards
Acquire Project Team
An executing process focused on getting the right people to work on the project at the right time. Acquire Project Team is executed according to the human resource plan.
Acceptance
The act of approving the deliverables. Acceptance is usually performed by the project manager and the customer or sponsor at the end of the project, project phases, or at predefined milestones. Acceptance of the product, service, or result is formal.
Activity
Also called Schedule activity. An activity is a task that must be performed in order to complete work on the project. Activities are created by further decomposing the work packages. Under current guidelines, the primary difference between a work package and an activity is that a work package is a component of the scope and describes some aspect of the deliverable, while an activity describes the work that must be done in order to complete the work package. Schedule activities are first defined, then sequenced and estimated for duration.
Activity attributes
The informational components that accompany each schedule activity. These may include information on dependencies, leads and lags, assignments, accountability, requirements, constraints and
assumptions.
Activity on Arrow (AOA)
A type of graphical project network diagram where schedule activities are represented by lines with arrows. The lines are connected by notes, usually represented by circles. AOA diagrams are seldom used in practice today and have been replaced by AON.
Activity on Node (AON)
A type of graphical project network diagram where schedule activities are represented by nodes (usually rectangles), and their interdependencies are represented by lines with arrows.
Activity List
The list of all schedule activities to be performed, derived by decomposing the work packages into their schedule components. The activity list is a primary output of the Define Activities Process.
Activity Resource Requirements
The resources required to complete the activities in the activity list. Typically these are physical, human, and organizational resources but do not include financial resources.
Actual Cost (AC)
Also know as Actual Cost of Work Performed (ACWP). A term used in earned value management. Actual Cost represents the amount that has been spent by the project up to a point in time. It is often contrasted with earned value to show the difference between the amount of value earned on the project (represented by the earned value) and what was spent to earn that value (represented by the actual cost).
Actual Cost of Work Performed (ACWP)
Actual Cost of Work Performed represents the amount that has been spent by the project up to a point in time. It is often contrasted with earned value to show the difference between the amount of value earned on the project (represented by the earned value) and what was spent to earn that value (represented by the actual cost).
Agreements
A document, defining intentions around the project or some component of the project, that has been accepted by both parties. It is helpful to think of agreements as contracts for purposes of the exam.
Allowable Costs
Costs that are allowed under the terms of the contract. Typically, allowable costs become relevant under certain types of cost-reimbursable contracts where the buyer reimburses the seller’s allowable costs. If there are non-allowable costs in a contract, the buyer is not obligated to reimburse the seller for these.
Alternatives Generation
A tool used in the Define Scope process to identify multiple possible approaches to solving a problem.
Analogous Estimating
Also known as “Top-Down Estimating.” An estimating technique that uses the historical information from previously performed activities that are similar in nature, to estimate the effort, duration or cost needed to complete an activity.
Analytical Techniques
A logical approach that looks at the relationship between outcomes and the factors that can influence them.
Application (exam)
The application for the PMP or CAPM exam which requires the applicant to document an adequate combination of education and experience in project management. The application must be received and processed by the Project Management Institute before the applicant is eligible to schedule his or her certification exam.
Arrow Diagramming Method
The method that produces activity on arrow (AOA) diagrams.
Assumption
Anything that is considered to be true while planning. Assumptions should always be documented and validated, and they are often closely linked to constraints.
Backward Pass
A technique used to calculate slack, or float, that begins with the last node of a project network diagram and logically works backward to the start. Using the backward pass technique, each schedule activity’s late start and late finish dates are determined.
Bar Chart
A term in project management that equates to a Gantt Chart. In a bar chart, horizontal bars represent lengths of time for schedule activities. A calendar of dates represents the horizontal (X) axis.
Baseline
The original approved scope, cost, or schedule, plus all approved changes. Baselines represent the approved plan, and they are especially useful for measuring how actual results deviate from the plan. It is important to remember that the baselines can, and typically do, change throughout the life of the project as changes are approved. Baselines occasionally apply to other measured areas such as performance and quality.
Basis of Estimates
The backup detail showing how cost or schedule estimates were derived, where they came from, who was involved, what information was used, and what estimating technique was used.
Benchmarking
Using data from other projects, departments, or organizations to measure performance of the project or product.
Bottom-up Estimating
A technique for estimating overall project duration, effort, or costs by estimating the lowest levels of the schedule or work breakdown structure (WBS) and and aggregating those numbers up to the summary nodes on the WBS. Bottom-up estimating is widely considered to be a relatively accurate, but often tedious, technique for estimating. This technique is the opposite of top-down or analogous estimating.