Practice Management - AIA Contracts Flashcards
1
Q
AIA B101-2017
A
AIA B101-2017 is the contract document titled, Standard Form of Agreement Between Owner and Architect.
2
Q
AIA C401-2017
A
AIA C401-2017 is the contract document titled, Standard Form of Agreement Between Architect and Consultant.
3
Q
AIA A701-1997
A
Instructions to Bidders.
4
Q
What are Waivers of Subrogation?
A
This is the contractual provision given where the owner and the contractor waive all rights against the architect for damages caused by fire or other cause of loss.