PR S 47118 Flashcards

Inspection and testing of signal support work

1
Q

What is done with a signal support package once completed and equipment is booked back into use

A

it is sent to the regional signalling representative and signal support engineer within 48 hours of completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what needs to be completed after certifying a points job

A

monthly lock returns.
points history card

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what needs to be completed after certifying a track circuit job

A

track circuit history card

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what are the 10 parts of a signal support works package

A

Authorisation
Scope of works
Signalling scope of work/ safeworking permits
Work instruction register
Work instructions
Signalling support log
Signal support status certificate
Working documents
Spare forms
Competencies and Roster