PR S 47114 Flashcards

1
Q

what is inspection and testing for

A

to ensure the installation is
-physically and functionally in accordance with design.
-failsafe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Minimum insulation values for brand new cables

A

60 Mega ohm/ kilometre - core to core/core to earth
5 Mega ohm/ kilometre - sheath to earth

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Preference for testing circuits

A

testing as a complete circuit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What test is done first Insulation resistance or continuity

A

continuity is conducted first to ensure the correct wire is being tested and terminated correctly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you prove the integrity of the test earth

A

by connecting the IR tester to one end of the cable and to the test earth, and connecting the other end to a remote earth.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How to conduct a bell continuity test

A

remove fuse and negative pin
remove all relays
bell each wire individually from both ends
follow series paths before doing parallel paths
conduct a wire count at the same time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what is usually carried out with a continuity test

A

a wire count

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

when is the null count conducted and what is its purpose

A

when the bell continuity and wire count has been completed.
to find any rouge connnections

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what is the purpose of the circuit function test

A

to verify that fuses, links and controlling devices are effective in controlling the circuit function

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what is the superior version of a circuit function test and why

A

a strap and function test. it proves the specific contacts of controlling devices in the circuit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

requirements of a strap for strap and function testing

A

450mm minimum length
brightly coloured preferably orange
registered and labelled in sets
kept in a locked box

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the exceptions to conducting an out of correspondence check on points

A

when there are separate inputs for each end in CBI installations
where the points are physically connected mechanically.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Communication protocols for testing

A

contacts - front or back, open or closed
relays - up or down
points - LH switch open, RH switch closed and vice versa
trainstops - up or down
signals - name and colour over colour, trainstop up or down
rail vehicle detection - occupied, clear
ask non leading questions, be clear and confirm message

How well did you know this?
1
Not at all
2
3
4
5
Perfectly