PPP Flashcards

1
Q

What are the five methods of cost estimating?

A
  1. Project Comparison Method
  2. Area or Volume Method
  3. Assembly or System Method.
  4. Parameter Method (Matrix Costing)
  5. Unit Cost Method
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the five step process for Programming described by William Pena in Problem Seeking?

A
  1. Establishing Goals
  2. Collecting and Analyzing facts
  3. Uncovering and testing concepts.
  4. Determining Needs
  5. Stating the Problem
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the four considerations for Programming described by William Pena in Problem Seeking?

A
  1. Form
  2. Function
  3. Economy
  4. Time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly