PMPCh7.3 - Determine Budget Flashcards

1
Q

ITTO

A

Answer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is 7.3 Determine Budget

A

process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

key benefit of 7.3 Determine Budget

A

determines the cost baseline against which project performance can be monitored and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Insert 7.3 ITTO

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Memory 7.3 Determine Budget: Input

A

RAPS COBRA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Memory 7.3 Determine Budget: TT

A

CHEF Ramsey

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Memory 7.3 Determine Budget: O

A

1 Potato 2 Potato C?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Input of Determine Budget (9)RAPS COBRA:

A

Risk Register, Activity Cost Estimate, Project Schedule, Scope baseline, Cost mgmt plan, OPA, Basis of estimates, Resource Calendar, Agreements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

TT of Determine Budget (4) CHEF R:

A

Cost aggregation, Historical relationships, Expert judgement, Funding limit reconciliation, Reserve analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Output of Determine Budget (3): P, P, C

A

Project funding requirements, project doc updates, cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does a project budget contain

A

budget includes all the funds authorized to execute the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a cost baseline

A

approved version of the time-phased project budget, but excludes management reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Input of Estimate Costs (9)RAPS COBRA: Cost Management Plan

A

describes how the project costs will be managed and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Input of Estimate Costs (9)RAPS COBRA: Scope Baseline

A

Project Scope Statement, WBS, WBS Dictionary. Scope Stmt: formal limits on expenditure of project funds mandated by org, agreement, govt. Funding constraints are in scope stmt. WBS - relationship among deliverables and components. Dictionary: identify deliverables, description of work in each WBS component required to produce each deliverable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Input of Estimate Costs (9)RAPS COBRA: Activity Cost Estimates

A

Cost estimates for each activity within a work package are aggregated to obtain a cost estimate for each work package.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Input of Estimate Costs (9)RAPS COBRA: Basis of Estimates

A

Supporting detail that specifies any basic assumptions dealing with the inclusion or exclusion of indirect or other costs in the project budget.

17
Q

Input of Estimate Costs (9)RAPS COBRA: Project Schedule

A

includes planned start and finish dates for the project’s activities, milestones, work packages, and control accounts. This information can be used to aggregate costs to the calendar periods

18
Q

Input of Estimate Costs (9)RAPS COBRA: Resource Calendars

A

includes planned start and finish dates for the project’s activities, milestones, work packages, and control accounts. This information can be used to aggregate costs to the calendar periods

19
Q

Input of Estimate Costs (9)RAPS COBRA: Risk Register

A

Used to consider how to aggregate the risk response costs.

20
Q

Input of Estimate Costs (9)RAPS COBRA: Agreements

A

Applicable agreement information and costs relating to products, services, or results

21
Q

Input of Estimate Costs (9)RAPS COBRA: OPA

A

Existing formal and informal cost budgeting-related policies, procedures, and guidelines; Cost budgeting tools; and Reporting methods

22
Q

TTof Estimate Costs (5)CHEF R: Cost Aggregation

A

Cost estimates are aggregated by work packages in accordance with the WBS. Then aggregated Cost estimates are aggregated by work packages in accordance with the WBS

23
Q

TTof Estimate Costs (5)CHEF R: Reserve Analysis

A

establishes contingency reserves and management reserves for the project

24
Q

TTof Estimate Costs (5)CHEF R: Expert Judgment

A

helps to determine budget. Includes stakeholders, customers, prof/tech associations, industry groups, other units within performing organization

25
Q

TTof Estimate Costs (5)CHEF R: Historical Relationships

A

parametric estimates or analogous estimates involve the use of project characteristics (parameters) to develop mathematical models to predict total project costs. Most reliable when historical info accurate, parameters used are readily quantifiable, models are scalable (large, small, phase of project)

26
Q

TTof Estimate Costs (5)CHEF R: Funding Limit Reconciliation

A

expenditure of funds should be reconciled with any funding limits on the commitment of funds for the project. A variance between the funding limits and the planned expenditures will sometimes necessitate the rescheduling of work to level out the rate of expenditures. This is accomplished by placing imposed date constraints for work into the project schedule.

27
Q

Outputs of Estimate Costs (3): Cost Baseline

A

approved version of the time-phased project budget, excluding any management reserves, which can only be changed through formal change control procedures and is used as a basis for comparison to actual results

28
Q

Cost Baseline components - how they work

A

Activity cost estimates for the various project activities along with any contingency reserves for these activities are aggregated into their associated work package costs. WPC get added to contingency reserves for work packages into Control accounts. Control accounts get summed into the baseline. Enables time phased view of cost baseline; S curve. Baseline + management reserves = project budget

29
Q

Add figure 7-8 showing how Cost Baseline Components relate to Project Budget

A

Add figure 7-8 showing how Cost Baseline Components relate to Project Budget

30
Q

What are the 3 types of reserves

A

Activity contingency reserve, work package contingency reserve, cost baseline mgmt contingency reserve

31
Q

Outputs of Estimate Costs (3): Project Funding Reqt

A

Total funding requirements and periodic funding requirements (e.g., quarterly, annually) are derived from the cost baseline. Cost baseline will include projected expenditures plus anticipated liabilities. Funding occurs in increments. Total funds = cost baseline + mgmt reserves

32
Q

Outputs of Estimate Costs (3): Project Doc Updates

A

Includes Risk register,Activity cost estimates, and Project schedule.