PMPCh7.2 - Estimate Costs Flashcards

1
Q

Question

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Definition of Estimate Costs

A

process of developing an approximation of the monetary resources needed to complete project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Benefit of Estimate Costs

A

determines the amount of cost required to complete project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What else is included in Estimate Costs

A

consideration of costing alternatives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How are Estimate Costs expressed

A

currency, hours, days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

ROM Estimate

A

-25% - 75%, narrows later to -5%-10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Costs include what?

A

labor, materials, equipment, services, and facilities, as well as special categories such as an inflation allowance, cost of financing, or contingency costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Costs can be presented in what 2 forms

A

acitivity level of summary form

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Insert ITTO 7.2

A

Insert ITTO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Input of Estimate Costs (7):

A

Input of Estimate Costs (7): Cost Mgmt Plan, HR Mgmt Plan, Scope baseline, Project schedule, Risk Register, EEF, OPA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

TT of Estimate Costs (10) BATPE, Project Vendors Reserve the Cost of Group Decision Dinner:

A

Bottom-up Estimating, Analogous Estimating, Three-point estimating, Parametric estimating, Expert Judgement, Project mgmt software, Vendor bid analysis, Reserve Analysis, Cost of quality, Group Decision making techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Output of Estimate Costs(3) BAP (Batman and project vendors like to eat bimbimbap):

A

Output of Estimate Costs(3): Basis of cost estimates, Activity Cost estimates, Project doc updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Input of Estimate Costs (7)CHORE SP: Cost Mgmt Plan

A

defines how project costs will be managed and controlled, level of accuracy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Input of Estimate Costs (7)CHORE SP: HR Mgmt Plan

A

staff attribute, rates, reward

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Input of Estimate Costs (7)CHORE SP: Scope Baseline

A

project scope stmt, wbs, wbs dictionary. Project scope stmt: product description, acceptance criteria, key deliverables, project boundaries, assumptions, and constraints about the project. Assumption: direct vs indirect cost, Examples of other constraints are required delivery dates, available skilled resources, and organizational policies. WBS - relationships among all the components of the project and the project deliverables. Dictionary - detailed information about the deliverables and a description of the work for each component in the WBS required to produce each deliverable. Contains contractual and legal implications, such as health, safety, security, performance, environmental, insurance, intellectual property rights, licenses, and permits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Input of Estimate Costs (7)CHORE SP: Proj Schedule

A

determining the availability of staff, the number of staff hours required, and quantities of material and equipment needed to perform schedule activities. It is closely coordinated with cost estimating. Incl Activity duration estimates.

17
Q

Activity Duration Estimates (part of Project Schedule, Input), from Time Mgmt

A

ex: Union labor with regularly expiring collective bargaining agreements ex: Union labor with regularly expiring collective bargaining agreements

18
Q

Input of Estimate Costs (7)CHORE SP: Risk Register

A

consider risk response costs Threats/opportunities. Threats = negative risk, increase cost of project

19
Q

Input of Estimate Costs (7)CHORE SP: EEF

A

Market conditions - what products, services, and results are available in the market, from whom, and under what terms and conditions. Published commercial information - Resource cost rate information is often available from commercial databases that track skills

20
Q

Input of Estimate Costs (7)CHORE SP: OPA

A

Cost estimating policies,Cost estimating templates,Historical information, andLessons learned.

21
Q

TT of Estimate Costs (10) BATPE: Bottom Up Estimating

A

a method of estimating a component of work. Detailed cost is then “rolled up” to higher levels for subsequent reporting

22
Q

TT of Estimate Costs (10) BATPE: Analogous Estimating

A

Use previous, similar projects as the basis for estimating the cost of the current project. Used when limited amount of info about project, relies on expert judgement. Less costly, less time, less accurate. Ensure similar in fact and not appearance.

23
Q

TT of Estimate Costs (10) BATPE: Three point estimating

A

considering estimation uncertainty and risk and using three estimates to define an approximate range for an activity’s cost: Most likely*4, optomistic, pessimistic….then take average = PERT

24
Q

TT of Estimate Costs (10) BATPE: Parametric estimating (parachute from construction bldg)

A

statistical relationship between relevant historical data and other variables (e.g., square footage in construction) to calculate a cost estimate for project work. Higher levels of accuracy

25
Q

TT of Estimate Costs (10) BATPEr: Expert Judgement

A

used to determine whether to combine methods of estimating and how to reconcile differences between them.

26
Q

TT of Estimate Costs (10) Project Vendors Reserve the Cost of Group Decision Dinner: Project Mgmt Software

A

software applications, computerized spreadsheets, simulation, and statistical tools are used to assist with cost estimating

27
Q

TT of Estimate Costs (10) Project Vendors Reserve the Cost of Group Decision Dinner:Vendor Bid Analysis

A

based on the responsive bids from qualified vendors, additional cost estimating work may be required of the project team to examine the price of individual deliverables and to derive a cost that supports the final total project cost.

28
Q

TT of Estimate Costs (10) Project Vendors Reserve the Cost of Group Decision Dinner:Reserve Analysis

A

contingency reserves based on identified risks, rework is unknown and could be risk, can apply to activity or project…should be on cost documentation, part of cost baseline and overall funding requirements for project. Mgmt reserve not in cost baseline but part of overall project budget/funding reqt. When mgmt reserve is actually used, it is added to cost baseline, requiring approved change to cost baseline.

29
Q

TT of Estimate Costs (10) Project Vendors Reserve the Cost of Group Decision Dinner:Cost of Quality (COQ)

A

Section 8…how much does it cost to ensure quality

30
Q

TT of Estimate Costs (10) Project Vendors Reserve the Cost of Group Decision Dinner:Group Decision-Making Techniques

A

brainstorming, the Delphi or nominal group techniques…engaging team members to improve estimate accuracy and commitment

31
Q

Output of Estimate Csots (3) BAP: Basis of Estimates

A

amount and type of additional details supporting the cost estimate. should provide a clear and complete understanding of how the cost estimate was derived. Ex: Documentation of the basis of the estimate (i.e., how it was developed), all assumptions made,any known constraints, range of possible estimates (e.g., 10,000 (±10%) to indicate that the item is expected to cost between a range of values), and Indication of the confidence level of the final estimate.

32
Q

Output of Estimate Csots (3) BAP: Activity Cost Estimates

A

quantitative assessments of the probable costs required to complete project work in summary form or in detail, for all resources like direct labor, materials, equipment, services, facilities, information technology, and special categories such as cost of financing (including interest charges), an inflation allowance, exchange rates, or a cost contingency reserve. Indirect costs, if they are included in the project estimate, can be included at the activity level or at higher levels.

33
Q

Output of Estimate Csots (3) BAP: Project Doc updates

A

ie. risk register