PMP3 Flashcards
Who is responsible for obtaining funding, committing resources, and approving deliverables?
Project sponsor
What is a Hybrid life cycle
Combines predictive and adaptive aspects. Elements that ar well-known or have fixed requirements follow predictive. Evolving elements follow adaptive
What are the 5 tiers to Maslow’s Hierarch of Needs?
Physiological, safety, belonging, esteem, self-actualization
What is the nominal group technique for managing stakeholders?
enhances brainstorming by allowing users to rank the most useful ides
What is a pre-mortem meeting?
Look at possible things that can cause failure during a project before they take place
What is an Artifact?
Template, document, output, or deliverable. Quantifiable
What are the 4 steps in the Change Control Process?
Assess the change > identify options for implementing the change > approve or reject the change (change control board (ccb)) > record the change
From a communication perspective, what are the 3 key activities that must occur during the Initiate and Plan processes?
Identify stakeholders and their needs, create a project communication plan, identify project performance metrics
What are 3 ways of collaboration in an Agile methodology?
Pairing, Swarming, and Mobbing
What is Decision Tree Analysis
Lists various options with their benefit or cost. lists outcomes with their probability of occurrence. Choose the least cost and least probability impactSquare represents a decision, circle is a chance of an event occurring
Define: appraisal costs, internal failure cost, and sunk cost
AC = cost of auditing/checking workIFC = defects before releaseSC = wasted money.
A project has a baseline schedule of 180 days and a budget of $250,000. After 21 days, the project has spent US $60,000 and earned a value of $75,000. What is the CPI for this project?
75000 / 60000 > 1, so under budget
When a change is requested, who does the PM talk to first before implementing?
Change Control Board, not the product owner, sponsor or development team
What is the Hawthorne effect?
the act of measuring something that makes people take notice and adjust their behavior
What are the 5 stages of a retrospective?
Set the stage, gather data, generate insights, decide what to do, close the retro
What is Discrete Effort?
Activity that can be linked to a specific WBS output
What is a project business case?
Explains why a project is needed with analysis of costs and benefits (also called an economic feasibility study)
What is a vanity metric?
Measure that shows data but does not provide useful information for making decisions
What is Agile Unified Process (AgileUP)?
Accelerated cycles and less heavyweight processes than Unified Process
Regarding stakeholders, what are power/interest grids, power/influence grids, and impact/influence grids?
Graph of the two components from low to high along two axis. Low power, low interest = monitorLow power, high interest = informHigh power low interest = satisfyhigh power, high interest = manage closely
What is the Schedule Performance Index? What does the number mean?
Shows how the schedule is progressing against the plan. Less than 1 = behind, greater than 1 = ahead
What are the 5 stages of team development in a Tuckman Ladder Model? List key characteristics of each and PM’s involvement
Forming (new team, behave independently; PM directs), Storming (trust and conflict arise; PM coaches), Norming (team begins to achieve goals; PM supporting), Performing (team is autonomous and makes decisions independently; PM delegates), Adjourning (team dissolves)
What is Design of Experiments (DOE) in terms of quality?
Statistical process for identifying variables that can most impact quality
What is Student Syndrome?
Wait until last minute to get the work done
What is quality control?
Analyze and evaluation the project deliverables against the requirements
What is the Project Procurement Plan?
Includes management and control processes for developing and administering agreements, such as contracts, PO’s, memorandum of agreement (MOAs), or SLAs. Does no include negotiation authority (that’s in the project charter)
Who is responsible for writing user stories?
Product owner
What model did Virginia Satir develop?
How people cope with change
What is the difference between resource leveling and resource smoothing?
Resource Leveling = start and finish dates are adjusted to accommodate critical resources, including changing the project start and end dates. Uses available float (slack)Resource Smoothing = Used after resource leveling to optimize resources when you cannot extend the schedule. Tries to move around activities
Regarding specialization and generalization, what are I-Shaped, T-Shaped, and Broken Comb/Paint Drip models?
I-Shaped = 1 specializationT-Shaped = 1 specialization, but good collaboration skills Broken Combe/Paint Drip = many specializations. Diverse knowledge
What are the 3 approaches to project work of a servant leader (in order)
Purpose (define why) > people (encouragement) > process (do not follow perfect process; look for results)
In Agile, what is Shu Ha Ri?
Concept that describes the path to mastery. Shu = follow rules, Ha = move away from rules to break free. Ri = unconsciously finding an individual path, to go beyond/transcend
What are the four phases of the product life cycle?
introduction, growth, maturity, retirement
Why would a sprint be canceled? Who can cancel it?
Goal of the sprint is obsolete. PO
Project-oriented project organization, list PM Authority, PM Role, Resource Availability, and who manages the project
High/total, full-time, high/total, project manager
What is Earned Value (EV)? How is it calculated?
Measures the actual work complete (as opposed to plan) against the budget. EV = actual percent complete x budgetIf the actual percent complete is 25% and the task budget is $10,000, the amount spent should be $2500
What is the Halo Effect
Cognitive bias in which our overall impression of a person influences how we feel and think about their character
What is parametric estimating for scheduling?
Two or more parameters are used in an algorithm to determine schedule, like 1000 sqft/painter/day
What is Expected Monetary Value (EMV) analysis?
Calculates average outcome when future scenarios may or may not happen. Decision tree analysis or make-or-buy analysisE.g. Develope New or Improve Existing -> Develop New ($300k), Improve Existing ($100k)Develop New = 75% success at $800k, 25% at -$100kImprove = 90% success at $300k, 10% failure at -$50k
What is Earned Value Management (EVM)?
Takes the EVA (the numbers) and uses them to show trends and forecasts
What are Test-Driven Development (TDD) or Behavior Driven Development (BDD)
Automated tests written before product
Define Deliverable
A unique and verifiable product, service, or result
What is included in the Final Report?
After a project is formally closed, the final report provides a summary of the project performance and any products, services, or results that were delivered
In Agile, what is a Spike?
Timeboxed research or experiment. If PO is unsure of dependencies, PO can request the team to spike the feature to understand risks. Architectural spike = proof of concept. Risk-based spike - reduce or eliminate risk
Define work performance data, information, and report
Data = measurement on project work (KPI’s, story points); information = information collected from the data (like the velocity); report = generate decisions or raise issues
Define the following risk terms: Project ResilienceRisk AppetiteRisk ToleranceScenarioData AnalysisQuantitative Risk AnalysisSecondary RiskResidual RisksBubble ChartTornado Chart
Project Resilience - emerging risk is becoming clearRisk Appetite - level of uncertainty an organization is willing to take on. Documented in Risk Management PlanRisk Tolerance - amount of risk an organization is willing to takeScenario - scenarioData Analysis - root cause analysis, assumption and constraint, SWOT, etc.Quantitative - used for large projectsSecondary - risk in response to another riskResidual Risk - left over risks after a planned response has been executedBubble Chart - displays 3 dimensions of dataTornado Chart - compares and prioritizes relative impact of different risks (sensitivity analysis)
What is Mclelland’s 3 need theory?
achievement, power, affiliation
Define the following agile terms: 1. Ideation 2.02. Kano analysis3. Highest paid person’s opinion (HIPPO)4. Design the product box5. Affinity estimating
- New approaches to solutions you encounter in your daily routine2. Classify customer satisfaction into: exciters, satisfiers, dissatisfiers, and indifferent3. Decision making where people agree with the highest paid person4. Stakeholders provide the most valuable features (the ones you’d put on the product box)5. T-shirt sizing
Matrix Weak project organization, list PM Authority, PM Role, Resource Availability, and who manages the project
Low, part-time, low, functional manager
What are the 4 directions of influence regarding the project?
Upwards (management, steering committee), downwards (project team), outwards (shareholders, governments, etc.), sidewards (peers)
What is the most important indicator of a successful project?
Value
Define Crashing
Adding more resources to a project
What is a Change Management Plan
Document describing the process for submitting, evaluation, and implementing changes. How does a request start, who does it go to
What is a Resource Breakdown Structure?
Hierarchical list of team and physical resources related by category and resource type (project > personnel/material/equipment; Personnel = Role 1/2/3; Role 1 = Level 1/2)
When should stakeholders be identified?
As soon as the project charter is approved
What is the agile methodology?
Both iterative and incremental, meaning feedback is regularly given on work and there are multiple small deliverables
What is bottom-up estimating for determining a schedule?
Work from the lowest items on the WBS on up. Time consuming but accurate
What are the 9 types of project organization/authority?
Organic/Simple, Functional/Centralized, Multi-divisional, Matrix Strong, Matrix Weak, Matrix Balanced, Project-oriented, virtual, hybrid
Define Risk Management Plan
Includes a risk budget, risk resources, risk tolerance levels, and how to implement risk response
What is a multicriteria decisions analysis?
Uses a decision matrix to provide a systematic analytical approach. Basically listing features and analyzing which/how much to implement (phone price, screen size, storage space, appearance). May use a voting process
What is Acceptance Test-Driven Development (ATDD)
entire team gets together to discuss the acceptance criteria in order to drive defects down
In Agile, what is Little’s Law?
Cycle times are proportional to queue lengths. Can predict lead time based on production rate and amount of work in process
List project management process groups
Initiating, Planning, Executing, Monitoring and Controlling, Closing. These are not project phases
What is a Pareto Chart (80/20 rule)?
Frequency of defects and cumulative impact. Identify areas to focus on first in process improvement. Histogram. 20% of the cause problems when addressed eliminate 80% of the current challenges
What is Large Scale Scrum (LeSS)
Framework for organizing several development teams towards a common goal
What is the Definition of Done
Establishes the quality criteria for a delivery. When can we show the product to the product owner?
Who attends a sprint review? Retro?
Literally anyoneTeam
What is a “weighted shortest job first (WSJF)” model used for?
A mathematical model used to objectively prioritize projects
Define the following three risk evaluation parameters:Data Quality AssessmentProbability AssessmentImpact Assessment
Degree to which the data is accurateLikelihood a risk will occurImpact if a risk does occur on schedule, cost, quality
What are the four steps in an iterative life cycle?
Analyze > analyze/design (prototype loop) > build test (refine loop) > deliver
What is the difference between iterative and incremental methodologies?
Iterative allows feedback on unfinished work and delivers a single product at the end of the cycle. Incremental provides finished deliverables that the customer may use immediately (frequent, small deliveries). Both are good for unpredictable scope, but incremental is better when speed is important
What happens in the Monitoring and Controlling process?
Project performance is monitored, measured, and verified (also reporting). Runs in parallel with the Executing process.
What is the To-complete performance index (TCPI)?
Future projects cost efficiency to complete the project within the project budget. Based on the Budget at Completion (BAC): (BAC - EV) / (BAC - AC)To calculate future cost performance: (Remaining work) / (Remaining Funds) - (BAC - EV) / (BAC - AC)
Define Risk Register
List of potential obstacles
When is a time and materials (T&M) contract most suitable?
Scope of work is not well-defined and contractor duration is not fixed
Define Issue Log
List of real obstacles faced or facing
What is the Cost Performance Index (CPI)? What does the number mean? How is it calculated?
Measure financial performance. Less than 1 = over budget. Over 1 = under budget. CPI = Earned Value (completed features value to date; EV) / actual costs to date (AC)
What is a Configuration Management System?
Established methods, system, and procedures to control the change process (like SharePoint for version management)
What is Gulf of Evaluation?
What one person describes is often different from how another interprets
Define cadence
Rhythm of activities conducted throughout the project.
What are the different components that make up a project budget (the breakdown of a project budget)?
Project Budget = Cost Baseline + Management ReserveCost Baseline = total of control accountsControl accounts = work package costs + contingencyWork package costs = activity costs + activity contingencyContingency reserves = identified risksManagement reserves = unidentified risks
When should you escalate issues to the sponsors or management
For the exam: (usually) NEVER reach out to management. Escalate to sponsor if: problem impacts funding, resources, or project success, lacks support in organization. A decision requires authorization to change scope
What is the output of stakeholder identification?
Stakeholder register
What is the Definition of Ready?
Checklist of what needs to be done to a product backlog item before the team can start implementing in the next sprint
What is hybrid team feedback?
Feedback is required on regular and continuous basis. Shorted the feedback cycle as much as possible
Define the following types of risks: Event RiskNon-Event RiskVariability RiskAmbiguity RiskEmergent Risk
Event - possible event, identified riskNon-Event - uncertain future event that may or may not occur (includes next 3)Variability - set number of outcomes, don’t know which one. Use Monte Carlo analysisAmbiguity - results from lack of knowledge or understandingEmergent - emerges from blind spot. Unknowable unknowns
What happensin the Planning process?
Objectives are determined and how to reach those objectives with given contraints
What are the 5 scrum values?
Commitment, Courage, Focus, Openness, Respect
What is a Design for Excellence (DfX) in terms of quality?
Prioritize specific aspect of the design like reliability cost, safety, etc
Define Stakeholder Engagement Plan
Documents how involved and influential the stakeholders are. Includes communication plan and how much information will be delivered
From a communication perspective, what is the key activity that must occur during the Closing processes?
Communicate project results
What is a requirements document?
Defines what is needed from the product
Define the 3 types of PMO
Supportive - resource for projects. Provides templates, best practices, training, lessons learned. Repository. Low control | Controlling - provides support but requires compliance (specific frameworks or methodologies, specific templates or tool). Moderate control. | Directive - directly manages the projects
What are some key differences between a project charter and a project management plan?
The charter is a high-level summary of the project outlining the goal, authority, and possible success metrics. Developed by the PM. It authorizes the project. The project management plan outlines the scope, timelines, budget, and methodology to be used. Developed with the project sponsors
Define project governance
provides direction, establishes decision-making procedures, defines metrics for evaluation project.
What is a Flow Charts?
Shows the process from start to finish, including decision points and people, departments and systems involved
Virtual project organization, list PM Authority, PM Role, Resource Availability, and who manages the project
Low to moderate, full-time, low to moderate, mixed
What is a Precedence Diagramming Method (PDM) or Activity On Node (AON)
Graphical tool for scheduling activities in a project plan (typical workflow diagram)
What are the four questions asked during a Kanban standup?
What do we need to do to advance this piece of work? Is anyone working on anything not on the board? What do we need to finish as a team? Are there any bottlenecks or blockers?
What are the 7 steps to developing a Scope Baseline?
Create a WBS > define the project scope (I guess this comes after because you need to see what work you can handle or something?) > create scope statement > get WBS/dictionary and scope statement approved > baseline is ready > create scope management plan to monitor scope > create change management plan to control changes
What is a stakeholder communication channel calculation?
Number of potential communication channels in a project. Increases as the number of stakeholders grows
What is included in the Procurement Management Plan?
How procurement works, timetable, metrics, responsibilities, assumptions and constraints, legal jurisdiction, and currency
What is Brooks’ Law (scheduling)?
Adding more people later in a project can actually push out the date further due to increased coordination costs
What is the difference between start-to-start (SS) and start-to-finish (SF) scheduling methods?
SS = similar to FF. Activities can run in parallel, but B can’t start until A does (you can’t level concrete until the foundation has been poured, but it doesn’t have to be all the way poured to start)SF = Task A cannot finish until task B starts. Like cutting over a new system - you can’t close out the legacy system until the new system is online. Not commonly used
Key words associated with: Executing Phase/Process
Manage/conduct/implement
What are the three broad categories of stakeholders?
Internal, connected (shareholders), external (government, etc.)
On the PMP exam, what are clues for either a triangular estimate or PERT/Beta estimate?
Triangular: new projects, no experience, not much reliable dataPERT/Beta: team of experts, similar to triangular, but need more accurate estimate (since it uses weights)
What is “Stale Sandwich”
Using outdated and inappropriate feedback mechanisms
What are the primary goals of the following approaches: Predictive, Iterative, Incremental, Agile
Manage cost, correctness of solution, speed, customer value via frequent deliveries and feedback
What is the correlation between a scope statement, WBS, work package, and activity list?
Decomposed into Scope Statement > WBS > Work Package > Activity List
What are the three types of fixed-price contracts?
Firm fixed price (FFP) - one lump sum. All risks with sellerFixed price incentive fee (FPIF) - seller is offered performance based incentive for meeting targetFixed price with economic price adjustments (FPEPA) - Cost is adjusted over long periods of time
What is the difference between a Work Breakdown Structure and a WBS Dictionary?
The WBS provides a breakdown of the work packages (groups of related tasks). The dictionary assigns responsibility and dates
What is the OSCAR model?
Outcome, situation, choices, actions, review. Adapt leadership style to support individuals for personal growth. Whittlworth and Gilbert
Define the two types of schedule compression
Fast-tracking: activities are performed in parallel. May increase risk of rework, but does not inherently increase cost. This is used before crashingCrashing: Additional resources added to project. Always increases cost and may increase risk. Use this when there is extra money (CPI is greater than 1). This could be overtime.
What is a RACI Assignment Matrix?
Matrix of people vs activities. Lists who is responsible, accountable, consulting, and informing. Only one person should be accountable.
What is Resource Optimization?
Method of flattening the schedule when resources are over-allocated or allocated unevenly. Resource Leveling and Resource Smoothing
What types of rewards can a PM provide?
Maslow’s hierarchy of needs: monetary, development and growth, acknowledgement and recognition
What are the 12 agile principles?
- Highest priority to satisfy the customer through early and continuous delivery2. Welcome changing requirements; harness for competitive advantage3. Deliver working software frequently4. Buisiness people and developers work together daily5. Build projects around motivated individuals6. Face to face conversations7. Working software is the primary measure of progress8. Agile processes promote sustainable development. Maintain a constant pace9. Continuous attention to technical excellence and good design10. Simplicity - maximize the amount of work not done11. Self organizing teams12. Regular reflection
From a communication perspective, what are the 4 key activities that must occur during the Control and Execute processes?
Gather/analyze status, compile status, disseminate status, monitor stakeholder information needs
List various data representation techniques used for quality control (various types of charts, etc.)
Control charts, flow charts, logical data model, matrix diagrams, mind mapping, cause and effect diagrams, histogram, affinity diagrams, scatter diagrams
What is Value Stream Mapping and Value Stream Analysis?
Shows where the value delivery is slowing down and exposes opportunities to create better alignment. Analysis examines the steps to take a product or service from the beginning to end.