PMP Questions Flashcards

1
Q

A project is in its execution and the Research & Development Team communicates to the project manager that the requirements and features for the product have changed following a market survey report published by the Consumer Behaviour Research Team. These changes were not anticipated and may affect the sales, and the overall project scope significantly. What action should the project manager take?

  1. Option A - Perform a triple constraint analysis and trigger Perform Integrated Change Control
  2. Options B - Arrange a meeting to revisit the project charter
  3. Option C - Review the risk management plan to identify risk responses
  4. Option D - Plan to use the contingency reserve and update the risk mitigation plan
A

A - This option aligns with the principles of change management and integrated change control. Performing a triple constraint analysis (examining the impact on scope, time, and cost) is essential when facing unexpected changes. It is followed by initiating the Perform Integrated Change Control process, where the project manager, along with the change control board, evaluates the impact of the change on the project’s overall objectives and constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

An agile team has been working efficiently on a new product launch. The first version of the product needs to be released within four months to avoid additional feature integrations due to a new upcoming legislation. The product owner puts forward an additional feature update request accordingly to complete the project before new laws become applicable. However, the project is stretched on time but flexed on budget.

What should the project manager do to tackle this?

A. Hire additional resources externally to complete the feature update

B. Negotiate with the customer to evaluate the need for the update

C. Evaluate a best value option with the project sponsor

D. Take the new legislation requirements into account in line with project compliance

A

A. Hire additional resources externally to complete the feature update (correct):

  • Correct: In this situation, where the project is stretched on time but has budget flexibility, hiring additional resources externally can help expedite the completion of the feature update. This aligns with the PMBOK concept of resource optimization, which involves acquiring additional resources to meet project objectives when needed. It acknowledges the importance of time constraints and the need for swift action to meet project deadlines.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Eight months into an agile project closely linked to the expansion strategy of a company, the Board of Directors is closely monitoring its progress. The Chief-Information-Officer however, expresses frustration that the last weekly burn-up chart records show the projected completion date significantly moving back & forth several times.

How can the project manager estimate the completion date with more accuracy & certainty?

A Reduce the frequency of burn-up chart reports sent to the board of directors
B Organize a training session for the board of directors about the flexible nature of agile planning
C Plan for variable-sized iterations according to story load and complexity
D Ensure upcoming backlog items are elaborated on in more detail with the team

A

Option 4 (Correct): Ensure upcoming backlog items are elaborated on in more detail with the team. Erratic progress curve variations are typical of inconsistent or uninformed story point estimates. If the required level of granularity is not found in the backlog tasks, there will always be ‘guesstimations’ and ’80:20 estimations’ happening. This will cumulate over backlogs exponentially & will cause the final date of the project to swing within a huge range. This is similar to a ‘bull-whip’ effect in Supply Chain Management (Check Bull Whip Effect video lecture below).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

You are working as a project manager in a government organization where ‘agile’ is not fully integrated into the culture. What should be your best approach as a project manager while leading an agile-driven project in an organization where agile terms and language do not fit the organizational culture?

A. Explain Agile in terms of lean thinking, small batch sizes, frequent reviews:
B. Modify the terms to meet the culture of the organization, but still keeping the necessary intent & outcome of every work process:
C. Adopt a Hybrid approach since that will ensure a smooth transition:
D. Build center of competencies to help provide guidance and build domain knowledge:

A

B. Modify the terms to meet the culture of the organization, but still keeping the necessary intent & outcome of every work process:

  • This approach recognizes the importance of adapting to the existing organizational culture while preserving the fundamental principles and values of Agile. It involves modifying Agile terminology and practices to align with the organization’s culture while still achieving the Agile project’s intended outcomes. This approach promotes flexibility and integration, allowing for a smoother transition to Agile in a non-Agile culture.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

As the project manager for a governance project involving local council authorities as key stakeholders, an enthusiastic Customs & Duty department stakeholder seeks more frequent and detailed project updates and offers assistance, prompting you to inquire further about his background.

Which project artifact should you refer to before going into further discussion with this stakeholder?

A. Project charter:
B. Stakeholder register:
C. Stakeholder engagement plan:
D. Resource Management Plan:

A

B. Stakeholder register:

  • The stakeholder register is a project management document that contains detailed information about all project stakeholders. It includes their identification, roles, interests, expectations, and their level of influence or involvement in the project. When a new stakeholder, such as the individual from the Customs & Duty department, expresses interest in the project, the stakeholder register is the go-to document for project managers to learn more about that stakeholder’s background and interests.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

While studying the release burndown chart for a scrum team before the morning sprint review meeting, it was noticed that at a point, the graph moves below X-axis. Chose the best conclusion:

A. This is normal. The project is delayed, and the team is not able to complete story points as per schedule:
B. This is normal. The team should have had extra scope added by the customer:
C. This is normal. The development team underestimated the time required to complete each story point:
D. This is not normal. There have been errors in plotting the chart. The graph can touch the x-axis but cannot go below it:

A

D. This is not normal. There have been errors in plotting the chart. The graph can touch the x-axis but cannot go below it:

  • In agile project management, a burndown chart is used to track the progress of the project by showing the amount of work remaining over time. The chart represents the work (typically story points) on the y-axis and time on the x-axis. If the chart goes below the x-axis, it suggests a graphical error or an issue with how the chart was plotted. In a valid burndown chart, the graph may touch or intersect the x-axis at zero, indicating that the work is complete, but it should not go below it.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The project manager is creating a schedule to automate a pick-and-place operation with COBOTs (collaborative robots). The operations manager questions the 3-week installation estimate. The project manager justifies it using historical data and variable analysis.

Which estimating technique the project manager has used here?

A. Expert judgment:
B. Analogous estimating:
C. Parametric estimating:
D. Three-point estimating:

A

C. Parametric estimating:

  • Parametric estimating is a technique that uses statistical relationships between historical data and other variables to calculate estimates. In this scenario, the project manager has utilized a statistical relationship between historical data (eg. past automation installations) and the variable (eg. the number of people from the supplier involved in the COBOT installation) to estimate the duration of the site installation. Parametric estimating allows for a more data-driven and mathematical approach to estimating.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

You are the project manager for rolling out a new cloud-based Learning Management System (LMS) at East Coast University. The project also involves progressive phaseout of the old LMS systems (local) and phase-in of the new one (cloud-based). The client expectation is a seamless transition between the two systems. In your daily stand-up meeting, you have been notified of four issues today.

Which is the most critical issue that needs to be prioritized by the project manager?

A. Office lighting overhaul:
B. Java-script training for programmers:
C. Major fault in server communication:
D. Additional funding for a new module:

A

C. Major fault in server communication:

  • In the context of rolling out a new cloud-based Learning Management System (LMS), the most critical issue is the major fault in server communication. This issue directly impacts the project’s objective of transitioning to the new cloud-based LMS. If the campus servers cannot communicate with the cloud servers, it jeopardizes the seamless transition and functionality of the new system.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You are the project manager for the construction of a new office building. The project is nearing the handover to the client. The final piece, which is landscaping in & around the new building is about to start. You are reviewing the project schedule and the interdependencies between the activities.

You see that the landscaping could be scheduled to start 2 weeks prior to the scheduled start of the handover process the office building. This would be shown as a finish-to-start with a 2-week______? Fill in the blanks

A. Lag:
B. Lead:

A

B. Lead:

  • In the context of project scheduling, a “lead” represents a scheduling technique where the successor activity is allowed to start before the predecessor activity has fully completed. In this case, scheduling the landscaping to start 2 weeks prior to the handover process of the office building suggests that the landscaping can commence before the building handover is finished.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In the planning stage of an NGO sanitation project, the project manager is developing the project management plan. The plan awaits baseline updates from cost and schedule before seeking sponsor approval. However, a civil engineer alerts the PM that the sanitation layout must change due to interference with a future highway construction, impacting scope and time significantly. What is the next best step for the project manager now?

A. Start the process of raising a formal change request using the change control process:
B. Work out the impact on cost, scope & time, revise those baselines, and the project management plan:
C. Start a root causing session with your team members to understand why this input was missed initially:
D. Keep moving as per the base plan. You will have time to sort it out later with the Highways Authority:

A

B. Work out the impact on cost, scope & time, revise those baselines, and the project management plan:

  • In this scenario, the civil engineer has identified a significant change in the project, indicating a scope change due to interference with future highway construction. This change will also have an impact on the project’s schedule and cost. Therefore, the project manager’s next step should be to assess and understand the full impact of this change on cost, scope, and time. Once the impact is clear, the project manager should update the project baselines (scope, schedule, and cost) to reflect the new reality and revise the project management plan accordingly. This is a fundamental step in change management and aligns with project management best practices.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Any event or issue that can cause a risk to your project is called a project hurdle. Types of project hurdle vary based on industry, stakeholder, business environment, and the project itself. Arrange the definition of the following project hurdles with their names. Note: In your PMP Exam, you will be required to drag & drop boxes containing the definitions to match the names

Hurdle Names:

(1) Impediment

(2) Blockers

(3) Obstacles

Definitions:

(A) External factors, issues, event or conditions that can cause stoppages in the work or any further advancement

(B) Issues that completely halt or block progress on a task or project, often rendering it impossible to continue work until the issue is resolved

(C) Situations, conditions, and actions that slow down or hinder progress but can be sorted out with some level of planning & execution

A

1C 2B 3A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In projects with evolving requirements, high risk, or significant uncertainty, the scope is not understood at the beginning of the project or it evolves during the project. Agile methods deliberately try to spend less time defining and agreeing on the scope in the early stages of the project and spend more time establishing the process for its ongoing discovery and refinement. How do agile teams validate scope and refine requirements?

A Through prototyping and version releases
B developing a strong scope baseline
C created a WBS
D Collecting user stores

A

Option 1: Prototyping is the standard way of validating scope and refining requirements for agile-based projects. These requirements constitute the product backlog. ‘Developing a strong scope baseline’ is not applicable for an Agile-managed project due to its very flexible nature of the same. ‘Creating WBS’ and ‘Collecting user stories’ are processes of scope definition and NOT scope validation. It’s very important that you understand the difference between the two.

Sometimes the concept of ‘prototyping’ is also used in waterfall-type projects by building miniature models. Eg. a new wind-resistant building design can be prototyped on a 1 : 1,000,000 scale and tested in a wind tunnel laboratory. Similarly, a robot pick & place machine with 20 arms can be prototyped in the lab with 1 arm to test reliability. This is often called the ‘Proof-of-Concept’ or ‘Proof-of-Principle’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

You are the product owner for an agile-based project which plans to develop the student database for King’s College, London. You are in the middle of an iteration and in one of your daily stand-ups, you get to know that a key approval from UK Government about Data Protection was missed and currently your project is non-compliant with UK’s Data Protection Act. What is your best step as a product owner here?

A Keep on executing the iteration. You can deal with the compliance issue in the next iteration
B Inform your sponsor about the issue and seek his help to get the approval on time
C You understand that it’s a legal non-compliance. While you keep working on the iteration, you deploy a core team to complete the required approvals at the earliest
D You do not take any action. It was nowhere mentioned in the project charter that you need to have UK Data Protection approval

A
  1. Option C:
    • In this scenario, the product owner recognizes that the project is non-compliant with the UK’s Data Protection Act, which represents a legal requirement. Legal compliance is a critical aspect of project management, especially in regulated environments like data protection.
    • The correct course of action is to acknowledge the non-compliance and take proactive steps to rectify it. Deploying a core team to work on obtaining the required approvals is the right approach, as it addresses the legal issue while the development work continues in parallel.
    • Agile practices encourage responding to change and addressing important issues promptly while maintaining project momentum.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Few days after the start of production for a newly installed shampoo packing line, it was identified that an important quality validation check that was to be done before product dispatch was skipped.

This resulted in a concern about the finished product quality and all the production units which were dispatched till date were put under quarantine. The sponsor directed the project manager to include this validation in the project plan immediately and revise the project schedule.

What should the project manager do first?

A Revise the Project Schedule and Start the Validation Process
B Start a Root-Cause Analysis on Why the Validation Was Missed
C Raise a Change Request to Revise the Project Schedule
D Update the Issue Log and Assign an Owner

A
  1. Raise a Change Request to Revise the Project Schedule (Option C - Correct Answer):
    • When a project experiences a significant change in scope, requirements, or deliverables, as in this case, the appropriate action is to raise a change request. This request initiates a formal process for evaluating and making necessary adjustments to the project plan and schedule.
    • In this scenario, the validation check was initially missed, and its inclusion in the project plan represents a change in scope. Raising a change request is the standard and formal approach to address such changes.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A telecom project is in the initiation phase now, and the project manager is currently developing the project charter. The project sponsor wants to review the plan which consists of a documented explanation for creating, maximizing & sustaining the advantages for your project. Which project artifact should the project manager refer to?

A Benefits Management Plan
2. Requirements Management Plan
3. Project Charter
4. Business Plan

A
  1. Benefits Management Plan (Option A - Correct Answer):
    • The Benefits Management Plan is a project management artifact that outlines how the project will create, maximize, and sustain the advantages and benefits described in the project charter. It details the strategies and actions needed to realize the expected benefits, track progress, and ensure that the project aligns with the organization’s objectives.
    • In the initiation phase, the project manager and the project sponsor should refer to the Benefits Management Plan to understand how the project will deliver the intended benefits.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Feature Driven Development (FDD) was designed to meet the specific needs of large software development projects. Which of the following are NOT one of the six primary roles for an FDD Project (select TWO OPTIONS)

Program Manager
Principal Designer
Project Manager
Chief Architect
Domain Expert

A

Program Manager, Principal Designer

17
Q

Roy is the project manager for an aviation turbine development project. She is currently in the ‘plan scope management’ process group and she is having a team meeting with her core team to determine the management approach for this project. Her team needs to finalize whether she will follow a waterfall, iterative, adaptive, agile, or hybrid development approach. What is she trying to strategize here and coach the team on?

A Management approach
B Development approach
C Value chain approach
D Sequential approach

A
  1. Development approach (Option B - Correct Answer):
    • In the context of the question, Roy and her core team are discussing whether to follow a waterfall, iterative, adaptive, agile, or hybrid development approach. This relates to how the project work will be executed, specifically focusing on the process and methodology for developing the aviation turbine.
    • The development approach encompasses the methodologies, practices, and strategies used to manage and deliver the project’s product or solution. It includes considerations related to project phases, iterative cycles, flexibility, and how work will be structured and executed.
18
Q

A project manager has recently completed an application development project for a client. But the client is still calling team members to solve technical issues, troubleshooting, etc. and requests are still coming for small changes and upgrades.

Client handover was an important task for the project which should have been completed on time. Which project artifact should have the baseline date of this task that will allow the project manager to check how off-track the project is when compared to the initial planned date?

A Milestone List
B Risk Register
C Scope baseline
D Communications Matrix

A
  1. Milestone list (Option A - Correct Answer):
    • In project management, a milestone represents a significant point or event in the project’s timeline. Milestones are used to track project progress and are typically associated with important tasks or deliverables.
    • The milestone list is a project artifact that documents all project milestones and their planned dates. It serves as a reference point for the project manager to assess whether the project is on track or off track.
    • In the context of the question, the client handover is an important task, and its baseline date in the milestone list would allow the project manager to compare the planned date with the actual completion date. If the handover task is delayed, it indicates that the project is off track in meeting this critical milestone.
19
Q

A team is transitioning from a waterfall based project management organization to an agile based organization. Unfortunately, some of the departments still lack proper training of agile.

How should the project manager respond to the lack of agile training with the specific teams?

  1. Identify and plan the most cost and time-efficient agile training for the teams.
  2. Organize a remote learning session
  3. Use project risk funds for training
  4. Reassign expert team members
A
  1. Identify and plan cost and time-efficient agile training (Option A - Correct Answer):
    • Agile transitions often require proper training to ensure that teams understand and implement agile practices effectively. Identifying and planning cost and time-efficient agile training is a proactive approach to address the training gap.
    • It aligns with best practices for assessing training needs, selecting suitable training options, and managing training as part of the project management process.
20
Q

A project manager has recently completed a software deployment project for a multi-national client. Next, the project manager confirms with the release manager that the software integration has been completed with all the departments of the organization in scope viz. Manufacturing, Engineering, Purchases, and Material Planning & Development.

The quality assurance team of the client has also verified the completed deliverables after the completion of the last & final sprint. What is the next step for the project manager?

1 Verify & Complete the Release Documentation:
2 Start Project Closeout Process:
3 Do a Cost & Schedule Review:
4 Lessons Learned and Organizational Knowledge Base:

A
  1. Lessons Learned and Organizational Knowledge Base:
    • Lessons learned are important insights and experiences gained during a project’s execution that can be used to improve future projects. If we consider this to be an agile project, lessons learned should be documented as well as part of the retrospective.
    • The organizational knowledge base is a repository of historical project information and lessons learned that can benefit the organization in managing future projects.
    • Updating the organizational knowledge base with lessons learned is the next logical step after project completion. This process involves documenting what went well, what didn’t go as expected, and any recommendations or insights gained during the project. These lessons can be valuable for future projects and help improve project management processes within the organization.
21
Q

Marta is a member of the delivery team for a large investment banking firm. The team has started to explore implementing agile in their projects instead of their current predictive waterfall technique. They noticed that several cross-functional teams have been using Scrum as a framework for Agile. Marta’s team nominated her as the scrum master. She has noticed that the team’s work intake is not a steady stream of plannable work. It is quite irregular with a lot of last-minute changes and bug fixes. This makes it difficult for the team to plan anything beyond 2 days. Which life cycle will Marta choose as the best fit for her team here?

Agile
Lean
Exploratory
Program

A

Option 2: Lean life cycle. Marta’s project has a lot of changing requirements and expedited items. This will make it difficult for the team to plan 1-2 weeks in advance which is required by Agile. The lean life cycle on the other hand will enable the team to plan JIT and allow them to plan as they go. They may face challenges as they start working with lean. However, learning to work with lean is far more realistic rather than changing stakeholder behavior or other elements to their external environment. Link to new ECO: Domain 2, Task 13: Determine appropriate project methodology/methods and practices (Agile/Hybrid/Predictive)

22
Q

In an agile project, there had been a multiple number of uncompleted stories at the end of iterations. Multiple team members worked on the stories and there were no impediments identified. Which of the following options can the agile team resort to, to resolve the situation?

A Insert the stories back into the product backlog and wait for a less intensive iteration to complete them
Further decompose the stories in the backlog by working with the product owner and update the definition of done
Insert the stories as part of Blocked Column and work with the product owner to remove the impediments
Use the next iteration to come out with a team spike that would help to determine the feasibility of completing the planned user stories

A

Option 2: The primary reason behind not being able to complete a story within the designed iteration is that the story had not been broken down into small manageable chunks. Also, it is very important to build a shared understanding for the definition of done (DoD) within the project team. Else, a particular story may seem complete to the product owner but will be incomplete for the scrum master. Inserting the stories back into the product backlog without clarifying the definition of done will cause the same result again. Hence that option is incorrect. There is no data in the question suggesting that the stories were not completed due to impediments. Hence, that is also a far-fetched assumption to make. Spikes are useful for learning and is used in circumstances to understand the flow of a user’s action through the product. Hence, this is not relevant to the scenario provided. Question based on Agile Practice Guide. Link to new PMP Exam ECO: Domain 2, Task 8: Plan and manage scope.

23
Q

Ferret is a project manager and he has completed the project management plan for his project recently. He submits his plan to the stakeholders for approval. He identifies a potential risk of delay in the approval process by the stakeholders. What would be his best course of action?

  1. Let the stakeholders know via email that if the approvals do not come on time, the project will be delayed
    2 Start the project in advance, stakeholder approval is secondary
    3 Plan a primary and a backup risk strategy for delays in approval and identify a risk owner for the same
    4 Update the risk register
A

Explanation
Option 3: The best way to mitigate this risk is to plan a primary and a secondary strategy. Ferret does not have full control over the approvals of the stakeholders. Emailing them does not guarantee an approval on time. Hence Option 1 is not correct. Also, in a scenario, always choose the option which addresses the issue at hand (or at least takes a step towards it). Here, just updating the risk register (option 4) will not move anything to solve the issue. If you do option 3, it will. Hence, option 3 is the right answer. Mind that ‘updating risk register’ is not wrong, but ‘Plan a primary and a backup risk strategy for delays in approval and identify a risk owner for the same’ is MORE CORRECT and attempts to address the issue at hand. Link to new ECO: Domain 2, Task - 3: Assess and manage risks

24
Q

Stewardship encompasses responsibilities both within and external to the organization and reflects understanding and acceptance of trust as well as actions and decisions that engender and sustain that trust. What are some other aspects of stewardship? (select all that apply)

Operating in alignment with the organization, its objectives, strategy vision, mission and sustainment of its long-term value
Leading daily stand-up meetings and prioritizing product backlog for teams
Understanding the appropriate use of authority, accountability, and responsibility particularly in leadership positions
Organization’s relationship with external stakeholders such as its partners and channels
Leading from the front and keeping the team motivated to deliver their best

A

Option 1,3,4. Options 1,3 and 4 are key aspects of stewardship in an organization. Option 2 is the role of a Scrum Master and does not necessarily convey the stewardship behaviour. Option 5 is the role of the Agile Coach/Project Manager and in a similar way does not convey the aspect of stewardship. Remember that stewardship is one of the many aspects of leadership behaviour, and often the Scrum Master or the Agile Coach is also expected to demonstrate those behaviours as well during their daily operations. Question based on The Standard for Project Management - Project Management Principles of PMBOK-7th edition (3.1 Be a diligent, respectful, and caring Steward). Link to new PMP Exam ECO: Domain 3, Task-1: Plan and Manage Project Compliance

25
Q

You have been appointed recently as a project manager in a project which is 6 months delayed from its baseline. The previous project manager had resigned without any notice & you didn’t have a chance to get any handover. The team morale is very low and there had been no set roles & responsibilities defined. So, everyone is trying to do everything which is resulting in utter chaos and rework. Which type of leadership style should you adopt here to manage the situation?

Democratic
Laissez-faire
Participative
Directive

A

Option 4. Directive. Effective leadership draws from or combines elements of various styles of leadership. effective leadership is shown when it best fits a given situation. In moments of chaos, directive action creates more clarity and momentum than collaborative problem-solving. Democratic, Participative or Laissez-faire leadership will not work here because implementing these types of leadership takes time and set team ground rules. Both of which is not available in the current scenario. Question based on The Standard for Project Management - Project Management Principles of PMBOK-7th edition (3.6 Demonstrate Leadership Behaviours). Link to new PMP Exam ECO: Domain 1, Task 2: Lead a Team

26
Q

How do you calculate Variance at Completion?

A

Forecasts the amount of budget deficit or surplus at the end of a project. BAC - EAC (estimate at completion/actual cost)

27
Q

You are the project manager for a highway construction project. The project has suffered a lot of delays and challenges during its course and it is currently running on a very tight schedule. Even a day of delay will now move your final handover date by a week. The client is monitoring the project very closely. Today you have received a notification from the local legal authorities that your project has violated one of the environmental laws and they have asked you to meet immediately to sort this out. However, you can’t leave the project site now, since that will invariably delay the phase of construction that’s going on. You don’t have anyone to supervise on your behalf as well. What is your best course of action here?

1 Complete the phase of construction that’s going on and then visit the legal authorities
2 Visit the legal authorities first and inform the client of a potential delay in the project
3 Ask one of the legal authority representatives to visit you at site
4 Inform the client about the situation and ask them to sort this out

A

Option 2: As a good project manager you should always keep project compliance ahead of project delivery. Things like safety, quality, internal controls, and stewardship come before the project deliverables. Hence, the best course of action here is to visit the legal authorities first and arrange for the necessary missed approvals. The client should understand this and support you as well. You should never break the law during project execution. You can later find out crashing/fast-tracking opportunities to make up for the delay as much as possible. Link to new ECO: Domain 3, Task-1: Plan and Manage Project Compliance

28
Q

Your project team has recently achieved a key milestone for an iteration-based agile project. To do this, the team met critical technical requirements on a new process and performed the demonstration with the product owner. As a part of the project status report to be sent out to the key stakeholders, you plan to add a screenshot of a chart that visually captures work (story points) completed vs. plan. Which chart is being referred to here?

  1. Iteration burndown chart
  2. Iteration burnup chart
  3. Iteration Gantt chart
  4. Spike display chart
A

Option 2: Iteration burnup charts show story points ‘completed’ vs. planned. Don’t confuse them with the iteration burndown chart that compares story points ‘remaining’ vs. planned over the sprint cycles. Check Pg. 63 of Agile Practice Guide for more details. Link to new ECO: Domain 2, Task 6: Plan and manage schedule

29
Q

This type of MBTI personality tends to be very practical and resourceful. They prefer to learn through hands-on experience and tend to dislike book learning and theoretical discussions. They live very much in the here-and-now and sometimes fail to think about how current actions will lead to long-term consequences. They also tend to dislike routine, enjoy new experiences, and are always looking for a new adventure. Which MBTI personality type is being referred to here?

INFP
ESFP
INTJ
ISTJ

A

Option 2: ESFP. This question can be very easily answered through the method of elimination. Most of the traits being talked about here are strong indicators of Extraversion (E). Hence, Option 1, 3, 4 get eliminated straight away.

30
Q

Anshul’s project has experienced some changes in performance, and some risks have occurred. EAC and BAC now differ as a result. His project sponsor is asking for an estimate of the cost of the project at completion. Which of the following is true?

  1. BAC may no longer be reasonable given the changes in performance, so Anshul should use EAC to forecast the cost at completion.
  2. EAC may no longer be reasonable given the changes in performance, so Anshul should use BAC to forecast the cost at completion.
  3. BAC may no longer be reasonable given the changes in performance, so Anshul should use ETC to forecast the cost at completion.
  4. EAC may no longer be reasonable given the changes in performance, so Anshul should use ETC to forecast the cost at completion.
A

Explanation
Option 1. Options 2, 3, and 4 are not viable responses because the question is asking for an estimate at completion (EAC), not an estimate to complete (ETC). Additionally, when changes in performance or risks occur on the project, it may cause BAC to no longer make sense. When that is the case, Anshul needs to switch to the EAC to project the cost at completion.

31
Q

What is the ideal type of project management methodology in a situation where the degree of change is very high but the frequency of delivery is low?

Agile
Iterative
Predictive
Incremental

A

Option 2: Iterative.
High degree of change, high frequency of delivery -> AGILE,
High degree of change, low frequency of delivery -> ITERATIVE,
Low degree of change, high frequency of delivery ->INCREMENTAL,
low degree of change, low frequency of delivery -> PREDICTIVE.

32
Q

High-level strategic and operational assumptions and constraints are normally identified in the business case before the project is initiated and are documented in the ‘Assumptions Log’. During which process the assumptions log for a project is created first?

  1. Develop project charter
  2. Develop risk management plan
  3. Develop project resilience
  4. Collect requirements
A

Option 1: The assumption log is first created during the ‘develop project charter’ process.

33
Q

You are a quality manager for a continuous improvement project. You would want to identify a sampling strategy for a population on basis of 3 categories of the standard of living (high, medium, low). Which type of sampling strategy would you be using here?

  1. Attribute sampling
  2. Variable sampling
  3. Control sampling
  4. Category sampling
A

Option 1: Attribute sampling. Since this is a population that is based on categories/attributes, hence attribute sampling.

34
Q

Misty is a project manager and she is currently in the planning stage of her project. She has finalized the team charter of the project and now she wishes to illustrate visually the project team members along with the work package that has been assigned to them. Which tool of the ‘Plan Resource Management’ process should she be using for this?

Organizational breakdown structure
Risk breakdown structure
Responsibility assignment matrix (ram)
resource planning chart

A

Option 3: A RAM shows the project resources assigned to each work package. It is used to illustrate the connections between work packages, or activities, and project team members. It is a T&T for the ‘Plan Resource Management’ process. Link to new ECO: Domain 2, Task 5: Plan and manage budget and resources

35
Q

You are having a project status review meeting with your sponsor at the final stages of an iteration-based agile project. Your sponsor is not very happy with the way the project has been executed. His primary concern is with schedule, which initially you committed to being 40 weeks but the whole project is now trending at 48 weeks. Still, there are about 3-4 weeks story points left. You know that there is a very strong reason behind this, which is scope creep. The customer has kept on adding new features for the application at regular intervals and the project which started with a baseline of 542 story points is now trending at 679 story points. Which is the best data representation to show to your sponsor in the context of this situation?

Feature chart
Iteration burndown chart
Iteration burnup chart
Gantt chart

A

Option 1: Feature chart. This will show how requirements grew during the project. It plots time on X axis vs. features (# of features remaining, # of features complete and # total of features) on Y axis.

36
Q

You are a project manager for an automation project and you are currently developing the scope baseline for the project. You have already done a thorough and timely job of identifying all the stakeholders and collecting their requirements. Whom should you involve now while developing the scope baseline?

Functional managers
Sponsor
Project team
Project stakeholders

A

Option 3: Since the stakeholders has already provided their inputs in the requirements collection process, the team should get involved now to develop the scope baseline = scope statement + WBS + WBS dictionary.

37
Q

You are in the direct and manage project work process for your project and your project sponsor suddenly replaces a key resource of your project with a newly hired person. This was done without your consultation and now this has totally caught you off-guard. What should you do as a project manager?

Stop all project work and setup a meeting with your sponsor to know why this change was done without your consent

Start the onboarding training for this person as fast as possible and get him into the job

Check the resource management plan to identify the next course of action

Do an analysis to identify what risks this new change will bring to your project in terms of scope, schedule or budget

A

Option D: This is the best course of action that could be taken in the current scenario to minimize the impact on the project performance. Option C is a close answer choice but wrong because the resource management plan may provide you with the process of onboarding for a new hire, but it will not help you in solving the problem at hand, which is to protect your project performance due to this unsolicited change. Link to new ECO: Domain 3, Task-4: Support organizational changes

38
Q

Which of the following document is created first in a project in comparison to the others?

Project Charter
Benefits Managements Plan
Issue Log
Assumptions Log

A

Option 2: Benefits management plan. It comes before the project charter. The assumptions log is an output of the project chartering process. Issue log comes much later.

39
Q

Your project is in the execution phase currently, and as a project manager, you have two of your stakeholders Mr. Jordan and Mrs. Shelly raising concerns with you that the information they are receiving through your status reports is incomplete. Even the project meetings are not able to resolve their concerns. You sense that if you delay this further, it may get escalated to your sponsor. What should you do as a servant leader/project manager here?

A

Call a meeting with Mr. Jordan and Mrs. Shelly and try to understand where exactly they are finding issues in the project communications

Follow the stakeholder engagement plan