PMP Terms: Risk Management Flashcards

1
Q

Risk

A

uncertainties in a project. Id the impact: individual vs overall. 21 ITTO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Non-Event Risk Categories

A

The first is variability risk, which looks at uncertainty in a planned event like there being more errors than expected or production is below target. The second is ambiguity risk. This is about what might be uncertain in the future. An example could be the complexity in the project. The third is project resilience, which deals with how well a project can bounce back from unknown risks. The project team might include extra contingency reserves for unknown risks and be flexible if they do happen. The last is integrated risk management. This goes beyond the project into the program or portfolio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Plan Risk Management

A

It is part of the Planning Proccess group. The key benefit of this process is that it describes how the project team will identify, evaluate, rank, and manage each risk. These risks will then be communicated to the stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Tools and Tech: Plan Risk Management

A

.1 Expert judgment
.2 Data analysis
• Stakeholder analysis the most important
.3 Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Output: Plan Risk Management

A

Risk Management Plan- a. Funding for the risk, b. methodology c. roles and responsibilities d. categories e. risk break down structure or RBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Definition of risk probability and impacts

A

The project
may generate specific definitions of probability and impact levels or it may start with general definitions provided by the organization. The number of levels reflects the degree of detail required for the Project Risk Management
process, with more levels used for a more detailed risk approach (typically five levels), and fewer for a simple
process (usually three).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Probability Impact Matrix

A

Opportunities and threats are represented in a common probability and impact matrix using
positive definitions of impact for opportunities and negative impact definitions for threats. Descriptive terms
(such as very high, high, medium, low, and very low) or numeric values can be used for probability and impact.
Where numeric values are used, these can be multiplied to give a probability-impact score for each risk, which
allows the relative priority of individual risks to be evaluated within each priority level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Identify Risk

A

The identify risk process falls under the planning process group and is the process of determining which risks may effect the project and documenting their characteristics

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Tools and Tech: Identify Risk

A
Expert judgment
.2 Data gathering
• Brainstorming
• Checklists
• Interviews
.3 Data analysis*
• Root cause analysis
• Assumption and constraint
analysis
• SWOT analysis
• Document analysis
.4 Interpersonal and team skills*
• Facilitation
.5 Prompt lists predefined risks 
.6 Meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Outputs: Identify Risk

A
1. Risk register- main output
.2 Risk report- main ouput 
.3 Project documents updates
• Assumption log
• Issue log
• Lessons learned register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Perform Qualitative Risk Analysis

A

is the process of prioritizing individual project risks for further analysis or action
by assessing their probability of occurrence and impact as well as other characteristics.

Planning process group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Risk Analysis: Main Inputs

A
Project management plan
• Risk management plan
.2 Project documents
• Assumption log
• Risk register
• Stakeholder register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Risk Analysis: Main Tools

A
• Interviews
.3 Data analysis
• Risk data quality
assessment
• Risk probability and impact
assessment
• Assessment of other risk
parameters
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Risk Analysis- Output

A
.1 Project documents updates
• Assumption log
• Issue log
• Risk register
• Risk report
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Perform Quantitative Risk Analysis (PQRA)

A

is the process of numerically analyzing the combined effect of identified individual
project risks and other sources of uncertainty on overall project objectives

Planning process group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

PQRA- Main Inputs

A
Project management plan
• Risk management plan
• Scope baseline
• Schedule baseline
• Cost baseline
• Duration estimates
• Resource requirements
• Risk register
17
Q

PQRA Main Tools-

A
.4 Representations of
uncertainty
.5 Data analysis
• Simulations
• Sensitivity analysis
• Decision tree analysis
18
Q

PQRA- Ouputs

A

.1 Project documents updates

• Risk report

19
Q

PLAN RISK RESPONSES (PRR)

A

Plan Risk Responses is the process of developing options, selecting strategies, and agreeing on actions to address
overall project risk exposure, as well as to treat individual project risks.

Planning process group

20
Q

PRR- Main Inputs

A
.1 Project management plan
• Resource management plan
• Risk management plan
• Cost baseline
.2 Project documents
• Resource calendars
• Risk register
• Risk report
• Stakeholder register
21
Q

PRR- Main Tools

A
.5 Strategies for opportunities
.6 Contingent response
strategies
.7 Strategies for overall project
risk
.8 Data analysis
• Alternatives analysis
• Cost-benefit analysis
22
Q

PRR- Main Outputs

A

.1 Change requests
.2 Project management plan
updates
3. Project Document Updates

23
Q

Residual Risk

A

that are expected to remain after planned responses have been taken, as well as those that
have been deliberately accepted; and

24
Q

Secondary risks

A

that arise as a direct outcome of implementing a risk response.

25
Q

Fallback plans

A

for use when a risk that has occurred and the primary response proves to be inadequate

26
Q

Implement Risk Responses (IRR)

A

the process of implementing agreed-upon risk response plans.

Executing Process Group

27
Q

IRR - Main Inputs

A

.1 Project management plan
• Risk management plan
.2 Project documents

  • Risk register
  • Risk report
28
Q

IRR- Main Tools

A

Expert judgment
.2 Interpersonal and team skills
• Influencing

29
Q

IRR- Main Outputs

A
.1 Change requests
.2 Project documents updates
• Issue log
• Lessons learned register
• Project team assignments
• Risk register
• Risk report
30
Q

Monitor Risks

A

is the process of monitoring the implementation of agreed-upon risk response plans, tracking identified
risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project.

31
Q

Monitor Risks- Main Inputs

A

.1 Project Management Plan
• Risk management plan
.2 Project documents

• Risk register
• Risk report
.3 Work performance data
.4 Work performance reports

32
Q

Monitor Risks- Main Tools

A

Data Analysis

Audits

33
Q

Monitor Risks- Main Outputs

A

Work Performance Information