PMP Terms Flashcards
A set of conditions that are met before deliverables are accepted by the customers or sponsors.
Acceptance Criteria
A distinct, scheduled portion of work performed during the project. Usually stored on the activity list.
Activity
The actual cost incurred for the work performed on an activity during a specific time period.
Actual Cost (AC)
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. Also known as top-down estimating.
Analogous Estimating
A factor in the planning processes considered to be true or real without proof or demonstration.
Assumption
A critical path method technique for computing the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
The accepted version of a work product that can be changed using formal change control processes and is used as the basis for comparison to actual results.
Baseline
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Bottom-Up Estimating
The amount of all budgets established for the work to be performed.
Budget at Completion (BAC)
A process whereby changes to documents, deliverables, or baselines related with the project are identified, documented, approved, or rejected.
Change Control
A formally commissioned group responsible for reviewing, assessing, approving, deferring, or rejecting change to the project, and for recording and communicating such decisions.
Change Control Board
A set of procedures that defines how modifications to the project deliverables and documentation are managed and controlled.
Change Control System
A formal proposal to change any document, deliverable, or baseline in the project management plan.
Change Request
a component of the project management plan that describes how, when, and by whom information will be administered and distributed.
Communications Management Plan
A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.
Configuration Management System
A restrictive feature that affects the execution of a projects.
Constraint
Time or money assigned in the schedule or cost baseline for known risks with response strategies
Contingency Reserve
A planned activity that restores the performance of the project work with the project management plan.
Corrective Action
The approved version of work package cost estimates and contingency reserve that can be changed using formal change control procedures.
Cost Baseline
A component of a project management plan that defines how costs will be planned and controlled.
Cost Management Plan
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual costs.
Cost Performance Index (CPI)
The amount of budget shortfall or surplus at a given point in time, expressed as the difference between the earned value and the actual costs.
Cost Variance (CV)
A schedule compression technique used to shorten the schedule duration by adding resources. This will generally increase cost on the projects.
Crashing
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources.
Critical Chain Method
The sequence of activities that represents the longest path through a project, which determines the shortest and longest possible duration. Activities on the critical path have no float.
Critical Path
Any activity on the critical path in a project schedule
Critical Path Activity
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network path within the schedule.
Critical Path Method
A technique used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule.
Decomposition
An intentional activity to modify a nonconforming product or product component.
Defect Repair
Deliverable is part of the product that is presented to the customer or stakeholders for acceptance
Deliverable
The total number of work periods required to complete an activity or work breakdown structure component, expressed in hours, days, or weeks.
Duration
The earliest an activity can finish without delaying the project end date.
Early Finish Date
The earliest an activity can start without delaying the project end date.
Early Start Date
The amount of money worth of work actually accomplished on the project.
Earned Value (EV)
A methodology that combines scope, schedule, and resource measurements to assess project performance.
Earned Value Management
Conditions, not under the immediate control of the team, that influence, constrain, or direct the project.
Enterprise Environment Factors
The forecast of the total cost of the project at the end based on the current spending rate of the project.
Estimate at Completion (EAC)
The amount of money that will be needed to complete the current project based on the current performance.
Estimate to Complete (ETC)
A schedule compression technique in which activities or phases are done in parallel for at least a portion of the entire duration. This can increase risk on the project.
Fast Tracking
A relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to-Finish
A relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-Start
A critical path method technique for calculating the early start and early finish dates by working forward through the schedule.
Forward Pass
An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority.
Functional Organization
A bar chart of schedule information where activities are listed. Generally part of the project schedule.
Gantt Chart
The amount of time whereby a successor activity will be delayed to a predecessor activity.
Lag
The latest an activity can finish without delaying the project end date
Late Finish Date
The latest an activity can start without delaying the project end date.
Late Start Date
The amount of time where a successor activity can be started before the predecessor activity finishes.
Lead
The data gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance.
Lessons Learned
A dependency between two activities.
Logical Relationship
Time or money that management puts aside in addition to the schedule or cost baseline and issues for unforeseen work that i s within the scope of the project. This is not under the control of the project manager and will need an approved change request to access it.
Management Reserve
An organization structure in which the project manager shares authority with the functional manager.
Matrix Organization
a significant point or event in a project.
Milestone
A type of schedule that presents milestones with planned dates.
Milestone Schedule
An estimate of the most probably activity duration that takes into account all of the known variables.
Most Likely Duration
A sequence of activities linked by logical relationship in a project schedule network diagram.
Network Path
A risk that would have a positive effect on one or more project objectives.
Opportunity