1
Q

____ is the process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics

The key benefit of this process is that it focuses efforts on high-priority risks. This process is performed throughout the project.

A

Perform Qualitative Risk Analysis

Risk, Planning

Output is: document updates (assumption log, issue log, risk register, risk report)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

____ is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

The key benefits are that it provides a direct link between the project and the strategic objectives of the organization, creates a formal record of the project, and shows the organizational commitment to the project.

Includes:
- Project Purpose
- Measurable project objectives and related success criteria
- High-level requirements
- overall project risk
- summary milestone schedule
- preapproved financial resources
- key stakeholder list
- Project approval requirements (i.e., what constitutes project success, who decides the project is successful, and who signs off on the project) kept?
- project exit criteria

A

Develop Project Charter

Integration, Initiation

This project is performed once or at predefined points in the project.

Inputs include:
- business documents (business case, benefits mgmt plan)
- agreements
- EEF, OPA

Outputs include:
- Assumption Log
- Project Charter

Note: Changes to the project charter are never approved by the Project Manager!

The project charter contains the project success criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

____ is the process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan.

The key benefit of this process is the production of a
comprehensive document that defines the basis of all project work and how the work will be performed.

A

Develop Project Management Plan

Integration, Planning

This process is performed once or at predefined points in the project.

Inputs:
- project charter
- outputs from other processes
- EEFs, OPAs

Outputs:
- Project Management Plan
- all 9 subsidiary management plans
- requirements management plan (establishes how the requirements will be analyzed, documented, and managed)
- change mgmt plan (how the change requests throughout the project will be formally authorized and incorporated)
- configuration management plan (how the information about the items of the project will be recorded and updated
- performance measurement baseline (An integrated scope-schedule-cost plan for the project work against which project execution is compared to measure and manage performance
- Project life cycle. Describes the series of phases that a project passes through from its initiation to its closure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

______ is the process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project’s objectives.

The key benefit of this process is that it provides overall management of the project work and deliverables, thus improving the probability of project success.

A

Direct and Manage Project Work

Integration, Executing

This process is performed throughout the project.

Inputs:
- Project management plan (any component)
- project documents
- approved change requests
- EEFs, OPAs

Outputs include
- Deliverables
- Work Performance Data
- Issue Log
- others such as change requests, updates, etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

_____ is the process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning.

The key benefits of this process are that prior organizational knowledge is leveraged to produce or improve the project outcomes, and knowledge created by the project is available to support organizational operations and future projects or phases. This process is performed throughout the project.

A

Manage Project Knowledge

Integration, Executing

Outputs include:
- Lessons Learned Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

____ is the process of tracking, reviewing, and reporting the overall progress to meet the performance objectives defined in the project management plan.

The key benefits of this process are that it allows stakeholders to understand the current state of the project, to recognize the actions taken to address any performance issues, and to have visibility into the future project status with cost and schedule forecasts.

A

Monitor and Control Project Work

Integration, Monitoring and controlling

Outputs include:
- work performance reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

_____ is the process of reviewing all change requests; approving changes and managing changes to deliverables, project documents, and the project management plan; and communicating the decisions.

This process reviews all requests for changes to project documents, deliverables, or the project management plan and determines the resolution of the change requests.

The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated manner while addressing overall project risk, which often arises from changes made without consideration of the overall project objectives or plans.

A

Perform Integrated Change Control

Integration, Monitoring & Controlling

Outputs:
- Approved change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What process involves implementing approved changes?

A

Direct and Manage Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What process outlines the project objectives?

A

Develop Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The key benefits of this process are that it provides a direct link between the project and the strategic objectives of the organization, creates a formal record of the project, and shows the organizational commitment to the project.

A

Develop Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The key benefit of this process is the production of a comprehensive document that defines the basis of all project work and how the work will be performed.

A

Develop Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

___ is the process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan.

A

Develop Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

__ is the process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project’s objectives.

A

Direct and Manage Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The key benefit of this process is that it provides overall management of the project work and deliverables, thus improving the probability of project success.

A

Direct and Manage Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

During this process, the work performance data is collected and communicated to the applicable controlling processes for analysis.

A

Direct and Manage Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

___ is the process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning.

A

Manage Project Knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The key benefits of this process are that prior organizational knowledge is leveraged to produce or improve the project outcomes, and knowledge created by the project is available to support organizational operations and future projects or phases.

A

Manage Project Knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

___ is the process of tracking, reviewing, and reporting the overall progress to meet the performance objectives defined in the project management plan.

A

Monitor and Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The key benefits of this process are that it allows stakeholders to understand the current state of the project, to recognize the actions taken to address any performance issues, and to have visibility into the future project status with cost and schedule forecasts.

A

Monitor & Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What process involves comparing actual project performance against the project management plan

A

Monitor & Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What process involves assessing performance periodically to determine whether any corrective or preventive actions are indicated, and then recommending those actions as necessary

A

Monitor & Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What process involves checking the status of individual project risks

A

Monitor & Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What process involves maintaining an accurate, timely information base concerning the project’s product(s) and their associated documentation through project completion;

A

Monitor & Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What process involves providing information to support status reporting, progress measurement, and forecasting

A

Monitor & Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What process involves providing forecasts to update current cost and current schedule information;

A

Monitor & Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What process involves monitoring implementation of approved changes as they occur

A

Monitor & Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What process involves providing appropriate reporting on project progress and status to program management when the project is part of an overall program

A

Monitor & Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What process involves ensuring that the project stays aligned with the business needs

A

Monitor & Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

___ is the process of reviewing all change requests; approving changes and managing changes to deliverables, project documents, and the project management plan; and communicating the decisions.

A

Perform Integrated Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

This process reviews all requests for changes to project documents, deliverables, or the project management plan and determines the resolution of the change requests.

A

Perform Integrated Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated manner while addressing overall project risk, which often arises from changes made without consideration of the overall project objectives or plans.

A

Perform Integrated Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

The key benefits of this process are the project or phase information is archived, the planned work is completed, and organizational team resources are released to pursue new endeavors.

A

Close Project or Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

The ___ process also establishes the procedures to investigate and document the reasons for actions taken if a project is terminated before completion. In order to successfully achieve this, the project manager needs to engage all the proper stakeholders in the process.

A

Close Project or Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What process involves confirming the delivery and formal acceptance of deliverables by the customer

A

Close Project or Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What process involves closing project accounts

A

Close Project or Phase

36
Q

What process involves:
- Confirming the formal acceptance of the seller’s work,
- Finalizing open claims

A

Close Project or Phase

37
Q

What process involves collecting any suggestions for improving or updating the policies and procedures of the organization, and sending them to the appropriate organizational unit.

A

Close Project or Phase

38
Q

___ is the process of creating a scope management plan that documents how the project and product scope will be defined, validated, and controlled.

A

Plan Scope Management

39
Q

The key benefit of this process is that it provides guidance and direction on how scope will be managed throughout the project.

A

Plan Scope Management

40
Q

___ is the process of determining, documenting, and managing stakeholder needs and requirements to meet objectives.

A

Collect Requirements

41
Q

___ is the process of developing a detailed description of the project and product.

A

Define Scope

42
Q

The key benefit of this process is that it describes the product, service, or result boundaries and acceptance criteria.

A

Define Scope

43
Q

In which process is a Scope Statement created?

A

Define Scope

44
Q

__ is the process of subdividing project deliverables and project work into smaller, more manageable components.

A

Create WBS

The key benefit of this process is that it provides a framework of what has to be delivered.

45
Q

___ is the process of formalizing acceptance of the completed project deliverables.

A

Validate Scope

The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service, or result acceptance by validating each deliverable.

46
Q

__ is the process of monitoring the status of the project and product scope and managing changes to the scope baseline.

A

Control Scope

The key benefit of this process is that the scope baseline is maintained throughout the project.

47
Q

What process ensures scope creep doesn’t happen?

A

Control Scope

Controlling the project scope ensures all requested changes and recommended corrective or preventive actions are processed through the Perform Integrated Change Control process (see Section 4.6). Control Scope is also used to manage the actual changes when they occur and is integrated with the other control processes. The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources is referred to as scope creep.

48
Q

___ is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

A

Plan Schedule Management

The key benefit of this process is that it provides guidance and direction on how the project schedule will be managed throughout the project. This process is performed once or at predefined points in the project.

49
Q

Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables.

A

Define Activities

50
Q

The key benefit of this process is that it decomposes work packages into schedule activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.

A

Define Activities

51
Q

___ is the process of identifying and documenting relationships among the project activities.

A

Sequence Activities

The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints. This process is performed throughout the project.

52
Q

___ is the process of estimating the number of work periods needed to complete individual activities with estimated resources.

A

Estimate Activity Durations

53
Q

The key benefit of this process is that it provides the amount of time each activity will take to complete. This process is performed throughout the project.

A

Estimate Activity Durations

54
Q

___ is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create a schedule model for project execution and monitoring and controlling.

A

Develop Schedule

The key benefit of this process is that it generates a schedule model with planned dates for completing project activities. This process is performed throughout the project.

55
Q

___ is the process of monitoring the status of the project to update the project schedule and managing changes to the schedule baseline.

A

Control Schedule

The key benefit of this process is that the schedule baseline is maintained throughout the project. This process is performed throughout the project.

56
Q

___ is the process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.

A

Plan Cost Management

The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project. This process is performed once or at predefined points in the project.

57
Q

__ is the process of developing an approximation of the cost of resources needed to complete project work.

A

Estimate Costs

The key benefit of this process is that it determines the monetary resources required for the project. This process is performed periodically throughout the project as needed.

58
Q

___ is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.

A

Determine Budget

The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled. This process is performed once or at predefined points in the project.

59
Q

___ is the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline. The key benefit of this process is that the cost baseline is maintained throughout the project. This process is performed throughout the project.

A

Control Costs

The key benefit of this process is that the cost baseline is maintained throughout the project. This process is performed throughout the project.

60
Q

___ is the process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with quality requirements and/or standards.

A

Plan Quality Management is the process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with quality requirements and/or standards.

The key benefit of this process is that it provides guidance and direction on how quality will be managed and verified throughout the project. This process is performed once or at predefined points in the project.

61
Q

__ is the process of translating the quality management plan into executable quality activities that incorporate the organization’s quality policies into the project.

The key benefits of this process are that it increases the probability of meeting the quality objectives as well as identifying ineffective processes and causes of poor quality.

A

Manage Quality is the process of translating the quality management plan into executable quality activities that incorporate the organization’s quality policies into the project.

The key benefits of this process are that it increases the probability of meeting the quality objectives as well as identifying ineffective processes and causes of poor quality.

Manage Quality uses the data and results from the control quality process to reflect the overall quality status of the project to the stakeholders. This process is performed throughout the project.

62
Q

___ is the process of monitoring and recording results of executing the quality management activities in order to assess performance and ensure the project outputs are complete, correct, and meet customer expectations.

The key benefit of this process is verifying that project deliverables and work meet the requirements specified by key stakeholders for final acceptance.

This process determines if the project outputs do what they were intended to do. Those outputs need to comply with all applicable standards, requirements, regulations, and specifications.

A

Control Quality is the process of monitoring and recording results of executing the quality management activities in order to assess performance and ensure the project outputs are complete, correct, and meet customer expectations.

The key benefit of this process is verifying that project deliverables and work meet the requirements specified by key stakeholders for final acceptance.

The Control Quality process determines if the project outputs do what they were intended to do. Those outputs need to comply with all applicable standards, requirements, regulations, and specifications.

63
Q

Which process verifies that project deliverables and work meet the requirements specified by key stakeholders for final acceptance?

A

Control Quality

64
Q

___ is the process of defining how to estimate, acquire, manage, and use team and physical resources.

The key benefit of this process is that it establishes the approach and level of management effort needed for managing project resources based on the type and complexity of the project. This process is performed once or at predefined points in the project.

A

Plan Resource Management is the process of defining how to estimate, acquire, manage, and use team and physical resources.

Resource planning is used to determine and identify an approach to ensure that sufficient resources are available for the successful completion of the project.

The key benefit of this process is that it establishes the approach and level of management effort needed for managing project resources based on the type and complexity of the project. This process is performed once or at predefined points in the project.

65
Q

___ is the process of estimating team resources and the type and quantities of materials, equipment, and supplies necessary to perform project work.

The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the project.

A

Estimate Activity Resources is the process of estimating team resources and the type and quantities of materials, equipment, and supplies necessary to perform project work.

The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the project.

66
Q

___ is the process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

The key benefit of this process is that it outlines and guides the selection of resources and assigns them to their respective activities. This process is performed periodically throughout the project as needed.

A

Acquire Resources is the process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

The key benefit of this process is that it outlines and guides the selection of resources and assigns them to their respective activities. This process is performed periodically throughout the project as needed.

67
Q

__ is the process of improving competencies, team member interaction, and the overall team environment to enhance project performance.

The key benefit of this process is that it results in improved teamwork, enhanced interpersonal skills and competencies, motivated employees, reduced attrition, and improved overall project performance.This process is performed throughout the project.

A

Develop Team is the process of improving competencies, team member interaction, and the overall team environment to enhance project performance.

The key benefit of this process is that it results in improved teamwork, enhanced interpersonal skills and competencies, motivated employees, reduced attrition, and improved overall project performance.This process is performed throughout the project.

68
Q

__ is the process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance.

The key benefit of this process is that it influences team behavior, manages conflict, and resolves issues. This process is performed throughout the project.

A

Manage Team is the process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance.

The key benefit of this process is that it influences team behavior, manages conflict, and resolves issues. This process is performed throughout the project.

69
Q

___ is the process of ensuring that the physical resources assigned and allocated to the project are available as planned, as well as monitoring the planned versus actual utilization of resources and taking corrective action as necessary.

The key benefit of this process is ensuring that the assigned resources are available to the project at the right time and in the right place and are released when no longer needed.

This process is performed throughout the project.

A

Control Resources is the process of ensuring that the physical resources assigned and allocated to the project are available as planned, as well as monitoring the planned versus actual utilization of resources and taking corrective action as necessary.

The key benefit of this process is ensuring that the assigned resources are available to the project at the right time and in the right place and are released when no longer needed.

This process is performed throughout the project.

70
Q

___ is the process of developing an appropriate approach and plan for project communications activities based on the information needs of each stakeholder or group, available organizational assets, and the needs of the project.

The key benefit of this process is a documented approach to effectively and efficiently engage stakeholders by presenting relevant information in a timely manner.

This process is performed periodically throughout the project as needed.

A

Plan Communications Management is the process of developing an appropriate approach and plan for project communications activities based on the information needs of each stakeholder or group, available organizational assets, and the needs of the project.

The key benefit of this process is a documented approach to effectively and efficiently engage stakeholders by presenting relevant information in a timely manner.

This process is performed periodically throughout the project as needed.

71
Q

___ is the process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information.

The key benefit of this process is that it enables an efficient and effective information flow between the project team and the stakeholders.

This process is performed throughout the project.

A

Manage Communications is the process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information.

The Manage Communications process identifies all aspects of effective communication, including choice of appropriate technologies, methods, and techniques. In addition, it should allow for flexibility in the communications activities, allowing adjustments in the methods and techniques to accommodate the changing needs of stakeholders and the project.

The key benefit of this process is that it enables an efficient and effective information flow between the project team and the stakeholders.

This process is performed throughout the project.

72
Q

___ is the process of ensuring the information needs of the project and its stakeholders are met.

The key benefit of this process is the optimal information flow as defined in the communications management plan and the stakeholder engagement plan. This process is performed throughout the project.

A

Monitor Communications is the process of ensuring the information needs of the project and its stakeholders are met.

The key benefit of this process is the optimal information flow as defined in the communications management plan and the stakeholder engagement plan. This process is performed throughout the project.

73
Q

Plan Risk Management is the process of defining how to conduct risk management activities for a project.

The key benefit of this process is that it ensures that the degree, type, and visibility of risk management are proportionate to both risks and the importance of the project to the organization and other stakeholders.

This process is performed once or at predefined points in the project.

A

___ is the process of defining how to conduct risk management activities for a project.

The key benefit of this process is that it ensures that the degree, type, and visibility of risk management are proportionate to both risks and the importance of the project to the organization and other stakeholders.

This process is performed once or at predefined points in the project.

74
Q

__ is the process of identifying individual project risks as well as sources of overall project risk, and documenting their characteristics.

The key benefit of this process is the documentation of existing individual project risks and the sources of overall project risk. It also brings together information so the project team can respond appropriately to identified risks.

This process is performed throughout the project.

A

Identify Risks is the process of identifying individual project risks as well as sources of overall project risk, and documenting their characteristics.

The key benefit of this process is the documentation of existing individual project risks and the sources of overall project risk. It also brings together information so the project team can respond appropriately to identified risks.

This process is performed throughout the project.

75
Q

___ is the process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.

The key benefit of this process is that it focuses efforts on high-priority risks. This process is performed throughout the project.

A

Perform Qualitative Risk Analysis is the process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.

The key benefit of this process is that it focuses efforts on high-priority risks. This process is performed throughout the project.

Perform Qualitative Risk Analysis establishes the relative priorities of individual project risks for Plan Risk Responses. It identifies a risk owner for each risk who will take responsibility for planning an appropriate risk response and ensuring that it is implemented. Perform Qualitative Risk Analysis also lays the foundation for Perform Quantitative Risk Analysis if this process is required.

76
Q

___ is the process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives.

The key benefit of this process is that it quantifies overall project risk exposure, and it can also provide additional quantitative risk information to support risk response planning.

This process is not required for every project, but where it is used, it is performed throughout the project.

A

Perform Quantitative Risk Analysis is the process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives.

The key benefit of this process is that it quantifies overall project risk exposure, and it can also provide additional quantitative risk information to support risk response planning.

This process is not required for every project, but where it is used, it is performed throughout the project.

77
Q

___ is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks.

The key benefit of this process is that it identifies appropriate ways to address overall project risk and individual project risks. This process also allocates resources and inserts activities into project documents and the project management plan as needed.

This process is performed throughout the project.

A

Plan Risk Responses is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks.

The key benefit of this process is that it identifies appropriate ways to address overall project risk and individual project risks. This process also allocates resources and inserts activities into project documents and the project management plan as needed.

This process is performed throughout the project.

78
Q

___ is the process of implementing agreed-upon risk response plans.

The key benefit of this process is that it ensures that agreed-upon risk responses are executed as planned in order to address overall project risk exposure, minimize individual project threats, and maximize individual project opportunities.

This process is performed throughout the project.

A

Implement Risk Responses is the process of implementing agreed-upon risk response plans.

The key benefit of this process is that it ensures that agreed-upon risk responses are executed as planned in order to address overall project risk exposure, minimize individual project threats, and maximize individual project opportunities.

This process is performed throughout the project.

79
Q

___ is the process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project.

The key benefit of this process is that it enables project decisions to be based on current information about overall project risk exposure and individual project risks.

This process is performed throughout the project.

A

Monitor Risks is the process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project.

The key benefit of this process is that it enables project decisions to be based on current information about overall project risk exposure and individual project risks.

This process is performed throughout the project.

80
Q

___ is the process of documenting project procurement decisions, specifying the approach and identifying potential sellers.

The key benefit of this process is that it determines whether to acquire goods and services from outside the project and, if so, what to acquire as well as how and when to acquire it. Goods and services may be procured from other parts of the performing organization or from external sources.

This process is performed once or at predefined points in the project.

A

Plan Procurement Management is the process of documenting project procurement decisions, specifying the approach and identifying potential sellers.

The key benefit of this process is that it determines whether to acquire goods and services from outside the project and, if so, what to acquire as well as how and when to acquire it. Goods and services may be procured from other parts of the performing organization or from external sources.

This process is performed once or at predefined points in the project.

81
Q

___ is the process of obtaining seller responses, selecting a seller, and awarding a contract.

The key benefit of this process is that it selects a qualified seller and implements the legal agreement for delivery. The end results of the process are the established agreements including formal contracts. This process is performed periodically throughout the project as needed.

A

Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a contract.

The key benefit of this process is that it selects a qualified seller and implements the legal agreement for delivery. The end results of the process are the established agreements including formal contracts. This process is performed periodically throughout the project as needed.

82
Q

___ is the process of managing procurement relationships; monitoring contract performance, and making changes and corrections as appropriate; and closing out contracts.

The key benefit of this process is that it ensures that both the seller’s and buyer’s performance meet the project’s requirements according to the terms of the legal agreement. This process is performed throughout the project as needed.

A

Control Procurements is the process of managing procurement relationships; monitoring contract performance, and making changes and corrections as appropriate; and closing out contracts.

The key benefit of this process is that it ensures that both the seller’s and buyer’s performance meet the project’s requirements according to the terms of the legal agreement. This process is performed throughout the project as needed.

83
Q

___ is the process of identifying project stakeholders regularly and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.

The key benefit of this process is that it enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders. This process is performed periodically throughout the project as needed.

A

Identify Stakeholders is the process of identifying project stakeholders regularly and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.

The key benefit of this process is that it enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders. This process is performed periodically throughout the project as needed.

84
Q

___ is the process of developing approaches to involve project stakeholders based on their needs, expectations, interests, and potential impact on the project.

The key benefit is that it provides an actionable plan to interact effectively with stakeholders. This process is performed periodically throughout the project as needed.

A

Plan Stakeholder Engagement is the process of developing approaches to involve project stakeholders based on their needs, expectations, interests, and potential impact on the project.

The key benefit is that it provides an actionable plan to interact effectively with stakeholders. This process is performed periodically throughout the project as needed.

85
Q

___ is the process of communicating and working with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement.

The key benefit of this process is that it allows the project manager to increase support and minimize resistance from stakeholders. This process is performed throughout the project.

A

Manage Stakeholder Engagement is the process of communicating and working with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement.

The key benefit of this process is that it allows the project manager to increase support and minimize resistance from stakeholders. This process is performed throughout the project.

86
Q

___ is the process of monitoring project stakeholder relationships and tailoring strategies for engaging stakeholders through modification of engagement strategies and plans.

The key benefit of this process is that it maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes. This process is performed throughout the project.

A

Monitor Stakeholder Engagement is the process of monitoring project stakeholder relationships and tailoring strategies for engaging stakeholders through modification of engagement strategies and plans.

The key benefit of this process is that it maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes. This process is performed throughout the project.