PMP formulas Flashcards
Learn formulas for the PMP exam
BAC formula in earned value management
No Formula.
PV formula in earned value management
No Formula. It is sometimes expressed as a %age of BAC.
EV formula in earned value management
No Formula. It is sometimes expressed as a %age of BAC or PV
AC formula in earned value management
No Formula.
SV formula in earned value management
SV = EV – PV
CV formula in earned value management
CV = EV – AC
SPI formula in earned value management
SPI = EV / PV
SPI cumulative formula in earned value management
SPIc = ΣEV / ΣPV
CPI formula in earned value management
CPI = EV / AC
CPI cumulative formula in earned value management
CPIc = ΣEV / ΣAC
Budget % Spent formula in earned schedule management
ΣAC / BAC x 100
TV (time variance) formula in earned schedule management
ES - AT
TPI formula in earned schedule management (time performance index)
ES / AT
Total Float formula in Network Diagram
TF = LS – ES | TF = LF - EF (late start mformula inus early start) (or late fformula inish mformula inus early fformula inish) (Top mformula inus bottom)
Free Float formula in Network Diagram
FF = ESsuccessor - ESpresent - DURpresent (if prev activity starts early and our activity starts early, mformula inus the duration) (need to defformula ine this better)
Present value or discounted cash flow equation formula in project selection methods
PV = FV * DF || PV = FV / (1+r)^n (future value * discount factor)(n is years, r is discount rate)(note that discount factor is the reverse of compounding interest to account for inflation over time)
NPV formula in project selection methods
ΣPV (higher is better all other things being equal)
ROI formula in project selection methods
Return / Formula investment (higher is better)
BCR formula in project selection methods
Benefits / Costs (higher is better)
CBR formula in project selection methods
Costs / Benefits (lower is better)
IRR formula in project selection methods
No formula, it’s estimated. (Higher is better)
PP formula in project selection methods
Price Point. (Market price, sale price, contract price) Lesser the better.
Opp Cost formula in project selection methods
No formula, it’s estimated. (Higher is better)
EMV for risk formula in expected monetary value
P * I (probability times Impact in dollars)
EMV for project formula in expected monetary value
ΣEVM (in risk)
Net Benefit formula in expected monetary value
EMV(project) - Cost
Project % Complete formula in earned value management
ΣEV/BAC x 100
ETC formula in earned value management(break into separate situations)
ETC = (BAC - EV) / CPI || ETC = (BAC - EV) || ETC = (BAC - EV) / CPIp
EAC formula in earned value management(break into separate situations)
EAC = AC + ETC || EAC = AC + (BAC - EV) || EAC = AC + (BAC - EV) / CPI || EAC = BAC / CPI || EAC = AC + [(BAC - EV) / (CPI * SPI)]
VAC (variance at completion) formula in earned value management
VAC = BAC - EAC || where EAC = AC + (BAC – EV)
TCPI formula in earned value management (break into separate situations)
TCPI = (BAC – EV) / (EAC – AC) || TCPI = (BAC – EV) / (BAC – AC)
Triangular formula in Estimation (optimistic, pessimistic, most likely)
E = (O + P + M) / 3 || σ = sqrt{[(P-O)^2 + (M - P)(M - O)]/(18)}
PERT formula in estimation (optimistic, pessimistic, most likely)
E = (O + P + 4*M) / 6 || σ = (P - O) / 6
Range formula in estimation
R = E ± (n * σ)
Sigma Values formula in estimation
1σ = 68.27% || 2σ = 95.45% || 3σ = 99.73% || 4σ - 99.994%
Path variance formula in estimation
VARpath = ΣVAR
variance
VAR = σ^2
Communication Channels formula in Communication
C = n*(n-1)/2
Percent of Total Assumption formula in procurement
PTA = (CP-TP)/(Buyers share ratio) + TC (this is in risk I think??)