PMP Acronyms Flashcards

1
Q

NOPAT

A

Net Operating Profits After Taxes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

NIAT

A

Net Income After Taxes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

RBS

A

Risk Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

RBS

A

Resource Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

IRR

A

Internal Rate of Return

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

EVM

A

Earned Value Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EMV

A

Expected Monetary Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

BAC

A

Budget at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC

A

Estimate at Completion (Budget Forecast)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EV

A

Earned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PV

A

Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

ETC

A

Estimate to Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

CV

A

Cost Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

SV

A

Schedule Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

CPI

A

Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

SPI

A

Schedule Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

AC

A

Actual Cost (Cost Incurred)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

VAC

A

Variance at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

BCR

A

Benefit Cost Ratio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

WBS

A

Work Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

AON

A

Activity on Node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

PDM

A

Precedence Diagramming Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

ADR

A

Alternative Dispute Resolution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

PDCA

A

Plan-Do-Check-Act Cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
ROM
Rough Order of Magnitude
26
TQM
Total Quality Management
27
PMO
Project Management Office
28
PBO
Project Based Organization
29
SOW
Statement of Work
30
SME
Subject Matter Expert
31
CCB
Change Control Board
32
FS
Finish to Start
33
SF
Start to Finish
34
SS
Start to Start
35
FF
Finish to Finish
36
CCM
Critical Chain Method
37
CPM
Critical Path Method
38
COQ
Cost of Quality
39
PMB
Performance Measurement Baseline
40
TCPI
To Complete Performance Index
41
7QC Tools
Seven Basic Quality Tools
42
DOE
Design of Experiments
43
PDPC
Process Decision Program Charts
44
OBS
Organization Breakdown Structure
45
PERT
Program Evaluation and Review Technique
46
RAM
Resource Assignment Matrix
47
RACI
Responsible, Accountable, Consult, Inform
48
SWOT
Strengths, Weaknesses, Opportunities, Threats
49
FFP
Fixed Firm Price
50
FP-EPA
Fixed Price - Economic Price Adjustment
51
CPFF
Cost Plus Fixed Fee
52
CPIF
Cost Plus Incentive Fee
53
CPAF
Cost Plus Award Fee
54
T&M
Time and Materials
55
RFI
Request for Information
56
RFP
Request for Proposal
57
IFB
Invitation for Bid
58
RFQ
Request for Quote
59
WAS
Work Authorization System
60
PMIS
Project Management Information System
61
EVA
Economic Value Added
62
PV
Present Value
63
NPV
Net Present Value
64
ROI
Return on Investment
65
ROIC
Return on Invested Capitol
66
ES
Early Start
67
EF
Early Finish
68
LS
Late Start
69
LF
Late Finish
70
JIT
Just in Time
71
ACWP
Actual Cost of Work Performed
72
BWCP
Budgeted Cost of Work Performed (EV)
73
BCWS
Budgeted Cost of Work Schedule (PV)
74
CAP
Control Account Plan
75
CRC
Cost-Reimbursable Contract
76
JAD
Joint Application Design/Development
77
LOE
Level of Effort
78
SIPOC
Supplier Input Process Output Customer
79
VOC
Voice of the Customer
80
PTA
Point of Total Assumption
81
FMEA
Failure Mode and Effect Analysis
82
IFB
Invitation for Bid
83
OBS
Organizational Breakdown Structure
84
QFD
Quality Function Deployment
85
MOU
Memorandum of Understanding
86
QC
Quality Control