PMBOK 5th Edition PM Process Groups and Knowledge Areas Matrix Flashcards
Name the SIX (6) processes of Project INTEGRATION Management.
(from INITIATING Process Group) - Develop Project Charter (from PLANNING Process Group) - Develop Project Management Plan (from EXECUTING Process Group) - Direct and Manage Project Work (from MONITORING & CONTROLLING Process Group) - Monitor and Control Project Work - Perform Integrated Change Control (from CLOSING Process Group) - Close Project or Phase
Name the FIVE (5) Project Management Process Groups.
- INITIATING Process Group
- PLANNING Process Group
- EXECUTING Process Group
- MONITORING & CONTROLLING Process Group
- CLOSING Process Group
(from top row of Matrix L to R)
Name the TEN (10) Project Management Knowledge Areas.
- Project INTEGRATION Management
- Project SCOPE Management
- Project TIME Management
- Project COST Management
- Project QUALITY Management
- Project HUMAN RESOURCE Management
- Project COMMUNICATIONS Management
- Project PROCUREMENT Management
- Project STAKEHOLDER Management
(from left vertical side of Matrix T to B)
Name the SIX (6) processes of Project SCOPE Management.
(from PLANNING Process Group)
- Plan Scope Management
- Collect Requirements
- Define Scope
- Create WBS (Work Breakdown Structure)
(from MONITORING & COLLECTING Process Group)
- Validate Scope
- Control Scope
Name the SEVEN (7) processes of Project TIME Management.
(from PLANNING Process Group) - Plan Schedule Management - Define Activities - Sequence Activities - Estimate Activity Resources - Estimate Activity Durations - Develop Schedule (from MONITORING & CONTROLLING Process Group) - Control Schedule
Name the FOUR (4) processes of Project COST Management.
(from PLANNING Process Group) - Plan Cost Management - Estimate Costs - Determine Budget (from MONITORING & CONTROLLING Process Group) - Control Costs
Name the THREE (3) processes of Project QUALITY Management.
(from PLANNING Process Group) - Plan Quality Management (from EXECUTING Process Group) - Perform Quality Assurance (from MONITORING & CONTROLLING Process Group) - Control Quality
Name the FOUR (4) processes of Project HUMAN RESOURCES Management.
(from PLANNING Process Group) - Plan Human Resources Management (from EXECUTING Process Group) - Acquire Project Team - Develop Project Team - Manage Project Team
Name the THREE (3) processes of Project COMMUNICATIONS Management.
(from PLANNING Process Group) - Plan Communications Management (from EXECUTING Process Group) - Manage Communications (from MONITORING & CONTROLLING Process Group) - Control Communications
Name the SIX (6) processes of Project RISK Management.
(from PLANNING Process Group) - Plan Risk Management - Identify Risks - Perform Qualitative Risk Analysis - Perform Quantitative Risk Analysis - Plan Risk Responses (from MONITORING & CONTROLLING Process Group) - Control Risks
Name the FOUR (4) processes of Project PROCUREMENT Management.
(from PLANNING Process Group) - Plan Procurement Management (from EXECUTING Process Group) - Conduct Procurements (from MONITORING & CONTROLLING Process Group) - Conduct Procurements (from CLOSING Process Group) - Close Procurements
Name the FOUR (4) processes of Project Stakeholder Management.
(from INITIATING Process Group) - Identify Stakeholders (from PLANNING Process Group) - Plan Stakeholder Management (from EXECUTING Process Group) - Manage Stakeholder Engagement (from MONITORING & CONTROLLING Process Group) - Control Stakeholder Engagement