PMP Abbreviations Flashcards

1
Q

SOW

A

Statement of Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

SF

A

Scheduled Finish date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CPI

A

Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

DU

A

Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

ADM

A

Arrow Diagramming Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

WBS

A

Work Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPPC

A

Cost Plus Percentage of Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

TC

A

Target Completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

CCB

A

Change Control Board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

TF

A

Total Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

AD

A

Activity Description

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

EV

A

Earned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

FMEA

A

Failure Mode and Effect Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

PMO

A

Program Management Office

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

TS

A

Target Start date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

PF

A

Planned Finish date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

AOA

A

Activity On Arrow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

CPFF

A

Cost Plus Fixed Fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

RFP

A

Request for Proposal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

RFQ

A

Request for Quotation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

SS

A

Start to Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

DD

A

Data Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

BAC

A

Budget At Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

BCWP

A

Budgeted Cost of Work Performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

EF

A

Early Finish date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

FF (not Free Float)

A

Finish To Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

EVT

A

Earned Value Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

EMV

A

Expected Monetary Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

PC

A

Percent Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

PMO

A

Project Management Office

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

LOE

A

Level of Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

FS

A

Finish to Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

ACWP

A

Actual Cost of Work Performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

OBS

A

Organizational Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

LS

A

Late Start date

36
Q

EVM

A

Earned Value Management

37
Q

IFB

A

Invitation For Bid

38
Q

AON

A

Activity On Node

39
Q

QA

A

Quality Assurance

40
Q

CPF

A

Cost Plus Fee

41
Q

AS

A

Actual Start date

42
Q

PMBOK

A

Project Management Body of Knowledge

43
Q

PM

A

Project Manager

44
Q

SPI

A

Schedule Performance Index

45
Q

LF

A

Late Finish date

46
Q

AF

A

Actual Finish date

47
Q

RAM

A

Responsibility Assignment Matrix

48
Q

PMIS

A

Project Management Information System

49
Q

CV

A

Cost Variance

50
Q

FPIF

A

Fixed Price Incentive Fee

51
Q

TQM

A

Total Quality Management

52
Q

AE

A

Apportioned Effort

53
Q

VE

A

Value Engineering

54
Q

PCT

A

Percent Complete

55
Q

ES

A

Early Start date

56
Q

CPM

A

Critical Path Method

57
Q

PDM

A

Precedence Diagramming Method

58
Q

SWOT

A

Strengths, Weaknesses, Opportunities and Threats

59
Q

CPIF

A

Cost Plus Incentive Fee

60
Q

RBS

A

Resource Breakdown Structure

61
Q

ETC

A

Estimate to Complete

62
Q

OD

A

Original Duration

63
Q

FFP

A

Firm Fixed Price

64
Q

PV

A

Planned Value

65
Q

T&M

A

Time and Material

66
Q

PMP

A

Project Management Professional

67
Q

SF

A

Start to Finish

68
Q

QC

A

Quality Control

69
Q

PS

A

Planned Start date

70
Q

SS

A

Scheduled Start date

71
Q

EAC

A

Estimate at Completion

72
Q

FF (not Finish to Finish)

A

Free Float

73
Q

PSWBS

A

Project Summary Work Breakdown Structure

74
Q

CAP

A

Control Account Plan

75
Q

DUR

A

Duration

76
Q

SV

A

Schedule Variance

77
Q

TF

A

Target Finish date

78
Q

CA

A

Control Account

79
Q

PM

A

Project Management

80
Q

BOM

A

Bill Of Materials

81
Q

RD

A

Remaining Duration

82
Q

AC

A

Actual Cost

83
Q

COQ

A

Cost of Quality

84
Q

CWBS

A

Contract Work Breakdown Structure

85
Q

RBS

A

Risk Breakdown Structure

86
Q

BCWS

A

Budgeted Cost of Work Scheduled