PMP Abbreviations Flashcards
SOW
Statement of Work
SF
Scheduled Finish date
CPI
Cost Performance Index
DU
Duration
ADM
Arrow Diagramming Method
WBS
Work Breakdown Structure
CPPC
Cost Plus Percentage of Cost
TC
Target Completion date
CCB
Change Control Board
TF
Total Float
AD
Activity Description
EV
Earned Value
FMEA
Failure Mode and Effect Analysis
PMO
Program Management Office
TS
Target Start date
PF
Planned Finish date
AOA
Activity On Arrow
CPFF
Cost Plus Fixed Fee
RFP
Request for Proposal
RFQ
Request for Quotation
SS
Start to Start
DD
Data Date
BAC
Budget At Completion
BCWP
Budgeted Cost of Work Performed
EF
Early Finish date
FF (not Free Float)
Finish To Finish
EVT
Earned Value Technique
EMV
Expected Monetary Value
PC
Percent Complete
PMO
Project Management Office
LOE
Level of Effort
FS
Finish to Start
ACWP
Actual Cost of Work Performed
OBS
Organizational Breakdown Structure