PMP Abbreviations Flashcards
SOW
Statement of Work
SF
Scheduled Finish date
CPI
Cost Performance Index
DU
Duration
ADM
Arrow Diagramming Method
WBS
Work Breakdown Structure
CPPC
Cost Plus Percentage of Cost
TC
Target Completion date
CCB
Change Control Board
TF
Total Float
AD
Activity Description
EV
Earned Value
FMEA
Failure Mode and Effect Analysis
PMO
Program Management Office
TS
Target Start date
PF
Planned Finish date
AOA
Activity On Arrow
CPFF
Cost Plus Fixed Fee
RFP
Request for Proposal
RFQ
Request for Quotation
SS
Start to Start
DD
Data Date
BAC
Budget At Completion
BCWP
Budgeted Cost of Work Performed
EF
Early Finish date
FF (not Free Float)
Finish To Finish
EVT
Earned Value Technique
EMV
Expected Monetary Value
PC
Percent Complete
PMO
Project Management Office
LOE
Level of Effort
FS
Finish to Start
ACWP
Actual Cost of Work Performed
OBS
Organizational Breakdown Structure
LS
Late Start date
EVM
Earned Value Management
IFB
Invitation For Bid
AON
Activity On Node
QA
Quality Assurance
CPF
Cost Plus Fee
AS
Actual Start date
PMBOK
Project Management Body of Knowledge
PM
Project Manager
SPI
Schedule Performance Index
LF
Late Finish date
AF
Actual Finish date
RAM
Responsibility Assignment Matrix
PMIS
Project Management Information System
CV
Cost Variance
FPIF
Fixed Price Incentive Fee
TQM
Total Quality Management
AE
Apportioned Effort
VE
Value Engineering
PCT
Percent Complete
ES
Early Start date
CPM
Critical Path Method
PDM
Precedence Diagramming Method
SWOT
Strengths, Weaknesses, Opportunities and Threats
CPIF
Cost Plus Incentive Fee
RBS
Resource Breakdown Structure
ETC
Estimate to Complete
OD
Original Duration
FFP
Firm Fixed Price
PV
Planned Value
T&M
Time and Material
PMP
Project Management Professional
SF
Start to Finish
QC
Quality Control
PS
Planned Start date
SS
Scheduled Start date
EAC
Estimate at Completion
FF (not Finish to Finish)
Free Float
PSWBS
Project Summary Work Breakdown Structure
CAP
Control Account Plan
DUR
Duration
SV
Schedule Variance
TF
Target Finish date
CA
Control Account
PM
Project Management
BOM
Bill Of Materials
RD
Remaining Duration
AC
Actual Cost
COQ
Cost of Quality
CWBS
Contract Work Breakdown Structure
RBS
Risk Breakdown Structure
BCWS
Budgeted Cost of Work Scheduled