PMBOK Vocabulary Flashcards

1
Q

Acceptance Criteria

A

A set of conditions that is required to be met before deliverables are accepted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Accepted Deliverables

A

Products, Results, or capabilities produced by a project and validated by the project customer or sponsors as meeting their specified acceptance criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Accuracy

A

Within the quality management system, accuracy is an assessment of correctness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Acquire Resources

A

The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Acquisition

A

Obtaining human and material resources necessary to perform activities. Acquisition implies a cost of resources, and is not necessarily financial

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Activity

A

A distinct, scheduled portion of work performed during the course of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Activity Attributes

A

Multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Activity Duration

A

The time in calendar units between the start and finish of a schedule activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Activity Duration Estimates

A

The quantitative assessments of the likely number of time periods that are required to complete and activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Activity List

A

A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Activity-on-Node (AON)

A

project management term that refers to a precedence diagramming method which uses boxes to denote schedule activities. These various boxes or “nodes” are connected from beginning to end with arrows to depict a logical progression of the dependencies between the schedule activities. Each node is coded with a letter or number that correlates to an activity on the project schedule. FINISH to START

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Actual Cost (AC)

A

the realized cost incurred for the work performed on an activity during a specific time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Actual Duration

A

The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Adaptive Life Cycle

A

A project life cycle that is iterative or inceremental

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Affinity Diagrams

A

A technique that allows large numbers of ideas to be classified into groups for review and analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Agreements

A

Any document or communication that defines the initial intentions of a project. This can take the form of a contract, memorandum of understanding (MOU), letters of agreement, verbal agreements, email, etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Alternative Analysis

A

A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Analogous Estimating

A

A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Analytical Techniques

A

Various techniques used to evaluate, analyze, or forecast potential outcomes based on possible variations of project or environmental variables and their relationships with other variables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Assumption

A

A factor in the planning process that is considered to be true, real, or certain, without proof of demonstration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Assumption Log

A

A project Document used to record all assumptions and constraints throughout the project life cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Attribute Sampling

A

Method of measuring quality that consists of noting the presence (or absence) of some characteristic (attribute) in each of the units under consideration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Authority

A

the right to apply project resources, expend funds, make decisions, or give approvals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

backward pass

A

a critical path method technique for calculating the late start and the late finish dates by working backward through the schedule model from the project end date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Bar Chart

A

A graphic display of schedule-related information. In the typical bar chart, schedule activities or work breakdown structure components are listed down the left side of the chart, dates are shown across the top, and activity durations are shown across the top, and the activity durations are shown as date-place horizontal bars. See also Gantt chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Baseline

A

The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Basis of Estimates

A

Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level of details, ranges, and confidence levels

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Basis of Estimates

A

Supporting documentation outlining the details used in establishing project estimates such as assumptions, constraints, level of detail, ranges, and confidence levels.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Benchmarking

A

The comparison of actual or planned products, processes, and practices to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measureing performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Benefits Management Plan

A

The documented explanations defining the process for creating, maximizing and sustaining the benefits provided by a project or program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Bid Documents

A

All documents used to solicit information, quotations, or proposals from prospective sellers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Bidder Conference

A

The meetings with prospective sellers prior to the preparations of a bid or proposal to ensure all prospective vendors have a clear and common understanding of the procurement. Also known as contractor conferences, vendor conferences, or pre-bid conferences.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Bottom-Up Estimating

A

A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Budget

A

The approved estimate for the project or any work breakdown structure component or any schedule activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Budget at Completion (BAC)

A

The sum of all budgets established for the work to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Buffer

A

A buffer gives project managers a leeway when unforeseen events occur and is often associated with scheduling in project management. A buffer can be temporal, financial or qualitative in nature, i.e. you have additional time, money or people available for difficult project phases. Buffers can be assigned either to the whole project or to individual activities (work packages).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Business Case

A

A documented economic feasibility study used to establish validity of the benefirts of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Business Value

A

The net quantifiable benefit derived from a business endeavor. The benefit may be tangible, intangible, or both

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Cause and Effect Diagram

A

A decomposition Technique that helps trace an undesirable effect back to its root cause

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Change

A

a modification to any formally controlled deliverable, project management plan component, or project document

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Change Control

A

A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Change Control System

A

A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Change Controlled Board

A

A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for the recording and communicating such decisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Change Control Tools

A

Manual or automated tools to assist with change and/or configuration management. At a minimum the tools should support the activities of the CCB

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Change Log

A

A comprehensive list of changes submitted during the project and their current status.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Change Management Plan

A

A component of the project management plan that establishes the change control board, documents the extent of its authority, and describes how the change control system will be implemented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Change Request

A

A formal proposal to modify a document, deliverable, or baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Checklist Analysis

A

A technique for systemically reviewing materials using a list for accuracy and completeness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Check Sheet

A

A tally sheet that can be used as a checklist when gathering data.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Claim

A

A request, demand, or assertion of rights by a seller against a buyer, or vice versa, for consideration, compensation, or payment under the terms of a legally binding contract, such as for a disputed charge.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Claims Administration

A

The process of processing, adjudicating, and communicating contract claims.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Close Project or Phase

A

The process of finalizing all activities for the project, phase, or contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Closing Process Group

A

The process(es) performed to formally complete or close a project, phase, or contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Code of Accounts

A

A numbering system used to uniquely identify each component of the work breakdown structure (WBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Collect Requirements

A

The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Colocation

A

An organizational placement strategy where the project team members are physically located close to one another in order to improve communication, working relationships, and productivity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Communication Methods

A

A systematic procedure, technique process used to transfer information among project stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Communication Models

A

A description, analogy, or schematic used to represent how the communication process will be performed for the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Communication Requirements Analysis

A

An analytical technique to determine the information needs of the project stakeholders through interview, workshops, study of lessons learned from previous projects, etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Communications Management Plan

A

A component of the project, program, or portfolio management plan that describes how, when, and by whom information about the project will be administered and disseminated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Communication Styles Assessment

A

A technique to identify the preferred communication method, format, and content for stakeholders for planned communication activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Communication Technology

A

Specific tools, systems, computer programs, etc used to transfer information among project stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

Conduct Procurements

A

The process of obtaining seller responses, selecting, and awarding a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Configuration Management Plan

A

A component of the project management plan that describes how to identify and account for project artifacts under configuration control, and how to record and report changes to them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Configuration Management System

A

A collection of procedures used to track project artifacts and monitor and control changes to these artifacts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Conformance

A

Within the quality management system, conformance is a general concept of delivering results that fall within the limits that define acceptable variation for a quality requirement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Constraint

A

A limiting factor that affects the execution of a project, program, portfolio, or process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Context Diagrams

A

A visual depiction of the product scope showing a business system (process, equipment, computer, system, etc) and how people and other systems (actors) interact with it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Contingency

A

An event or occurrence that could affect the execution of the project that may be accounted for with a reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Contingency Reserve

A

Time or money allocated in the schedule or cost baseline for known risks with active response strategies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Contingent Response Strategy

A

Responses provided which may be used in the event that a specific trigger occurs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

Contract

A

A contract is a mutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the buyer to pay for it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Contract Change Control System

A

The system used to collect, track, adjudicate, and communicate changes to a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Control

A

Comparing actually performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives, and recommending appropriate corrective action as needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Control Account

A

A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Control Chart

A

A graphic display of process data over time and against established control limits, which has a centerline that assists in detecting a trend of plotted values toward either control limit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

Control Costs

A

The process of monitoring the status of the project to update the project costs and manage changes to the cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

Control limits

A

The area composed of three standard deviations on either side of the centerline or mean of a normal distribution of data plotted on a control chart which reflects the expected variation in the data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Control Procurements

A

The process of managing procurement relationships, monitoring contract performance, making changes and corrections as appropriate, and closing out contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Control Quality

A

the process of monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

Control resources

A

The process of ensuring that the physical resources assigned and allocated to the project are available as planned, as well as monitoring the planned versus actual utilization of resources and performing corrective action as necessary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Control Schedule

A

The process of monitoring the status of the project to update the project schedule and manage changed to the schedule baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

Control Scope

A

The process of monitoring the status of the project and product scope and managing changes to the scope baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

Corrective Action

A

An intentional activity that realigns the performance of the project work with the project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

Cost Aggregation

A

Summing the lower-level cost estimates associated with the various work packages for a given level within the project’s WBS of for a given cost control account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

Cost Baseline

A

The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

Cost-Benefit Analysis

A

A financial analysis tool used to determine the benefits provided by a project against its costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

Cost-Management Plan

A

A component of a project or program management plan that describes how costs will be planned, structured, and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

Cost of Quality (CoQ)

A

All costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraisal for the product or service for conformance to requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

Cost Performance index (CPI)

A

A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

Cost Plus Award Fee Contract (CPAF)

A

A category of contract that involves payments to the seller for all legitimate actual costs incurred for completed work, plus an award fee representing seller profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

Cost Plus Fixed Fee Contract (CPFF)

A

A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract) Plus a fixed amount of profit (fee)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

Cost Plus Incentive Fee Contract (CPIF)

A

A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract) and the seller earns its profit if it meets define performance criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

Cost-reimbursable Contract

A

A type of contract involving payment to the seller for the seller’s actual costs, plus a fee typically representing the seller’s profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

Cost Variance (CV)

A

the amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

Crashing

A

A technique used to shorten the schedule duration for the least incremental cost by adding resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

Create WBS

A

the process of subdividing project deliverables and project work in to smaller, more manageable components

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Criteria

A

Standards, rules, or tests on which a judgement or decision can be based or by which a product, service, result, or process can be evaluated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

Critical Path

A

The sequence of activities that represents the longest path through a project which determines the shortest possible duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

Critical Path Activity

A

Any activity on the critical path in a project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

Critical Path Method (CPM)

A

A method used to estimate the minimum project duration and determine the amount of schedule flexibility on the logical network paths within the schedule model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

Data

A

Discrete, unorganized, unprocessed measurements or raw observations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

Data Analysis Techniques

A

Techniques used to organize assess and evaluate data and information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

Data Date

A

A point in time when the status of the project is recorded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

Data Gathering Techniques

A

Techniques used to collect data a information from a variety of sources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

Data Representation Techniques

A

Graphic representations or other methods used to convey data and information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

Decision-Making Techniques

A

Techniques used to select a course of action from different alternatives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

Decision Tree Analysis

A

A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

Decomposition

A

A Technique used for dividing and subdividing the project scope and project deliverables into smaller more manageable parts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

Defect

A

An imperfection or deficiency in a project component where that component does not meet its requirements or specifications and needs to be either repaired or replaced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

Defect Repair

A

An intentional activity to modify a nonconforming product or product component

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

Define Activities

A

The process of identifying and documenting the specific actions to be performed to produce the project deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

Define Scope

A

The process of developing a detailed description of the project and product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

Deliverable

A

Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

Dependency

A

Max Wideman’s Glossary defines as the “relationships between products or tasks”, i.e. tasks that require input from other tasks to be completed, or activities that can’t start until a previous activity is done. There are often several sequences to a task, and they’re all dependent on each other. The scope of a project requires these tasks to be completed in order.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

Determine Budget

A

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

Development Approach

A

The method used to create and evolve the product, service, or result during the project life cycle, such as predictive, iterative, incremental, agile. or hybrid method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

Develop Project Charter

A

The process of developing a document that formally authorizes the existence of a project and provided the project manager with the authority to apply organizational resources to project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

Develop Project Management Plan

A

The process of defining, preparing, and coordinating, all plan components and consolidating them into an integrated project management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

Develop Schedule

A

The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

Develop Team

A

The process of improving competences, team member interaction, and overall team environment to enhance project performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

Diagramming Techniques

A

Approaches to presenting information with logical linkages that aid in understanding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

Direct and Manage Project Work

A

The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project’s objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

Discrete Effort

A

An activity that can be planned and measured and that yields a specific output [Note: Discrete effort is one of three earned value management (EVM) types of activities used to measure work performance]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

Discretionary Dependency

A

A relationship that is established based on knowledge of best practices within a particular application area or an aspect of the project where a specific sequence is desired

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

Documentation Reviews

A

The process of gathering a corpus of information and reviewing it to determine accuracy of completeness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

Duration

A

The total number of work periods required to complete an activity or work breakdown structure component expressed in hours, days, or weeks. Contrast with effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

Early finish Date (EF)

A

In the critical path method, the earlies possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and any schedule constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

Early Start Date (ES)

A

In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

Earned Value (EV)

A

The measure of work performed expressed in terms of the budget authorized for that work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

Earned Value Management

A

A methodology that combines scope, schedule, and resource measurement to assess project performance and progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

Effort

A

The number of labor units required to complete a schedule activity or work breakdown structure component often expressed in hours, days, or weeks. Contrast with duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

Emotional Intelligence

A

The ability to identify, assess, and manage the personal emotions of oneself and other people, as well as the collective emotions of groups of people

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

Enterprise Environmental Factors

A

Conditions, not under the immediate control of the team, that influence, constrain, or direct the project, program or portfolio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

Estimate

A

A quantitative assessment of the likely amount or outcome of a variable, such as project costs, resources, effort, or durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

Estimate Activity Duration

A

The process of estimating the number of work periods needed to complete the individual activities with the estimated resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

Estimate Activity Resources

A

The process of estimating team resources and the type and quantities of material, equipment, and supplies necessary to perform project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

Estimate at Completion (EAC)

A

The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

Estimate Costs

A

The process of developing an approximation of the monetary resources needed to complete project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

Estimate to Complete (ETC)

A

The expected cost to finish all of the remaining project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

Execute

A

Directing, managing, performing, and accomplishing the project work; providing the deliverables; and providing work performance information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

Executing Process Group

A

Those processes performed to complete the work defined in the project management plan to satisfy the project requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

Expert Judgement

A

Judgement provided based upon expertise in an application area, knowledge area, discipline, industry, etc., as appropriate for the activity being performed. Such expertise may be provided by any group or person with specialized education, knowledge, skill, experience, or training.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

Explicit Knowledge

A

Knowledge that can be codified using symbols such as words, numbers, and pictures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

External Dependency

A

A relationship between projec activities and non-project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

Fallback Plan

A

An alternative set of actions and tasks available in the even that the primary plan needs to be abandoned because of issues, risks or other causes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

Fast Tracking

A

A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

Fee

A

Represents profit as a component of compensation to a seller

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

Finish Date

A

A point in time associated with a schedule activity’s completion. Usually qualified by one of the following actual, planned, estimated, scheduled, early, late, baseline, target, or current

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

Finish-to-Finish (FF)

A

A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
151
Q

Finish-to-start (FS)

A

A logical relationship in which a successor activity cannot start until a predecessor activity has finished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

Firm fixed Price Contract (FFP)

A

A type of fixed price contract where the buyer pays the seller a set amount (as defined by the contract),regardless of the seller’s cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
153
Q

Fishbone Diagram

A

The fishbone diagram or Ishikawa diagram is a cause-and-effect diagram that helps managers to track down the reasons for imperfections, variations, defects, or failures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

Fixed-Price Contract

A

An agreement that sets the fee that will be paid for a defined scope of work regardless of the cost or effort to deliver it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

Fixed-Price Incentive Fee Contract (FPIF)

A

A type of contract where the buyer pays the seller a set amount (as defined by the contract) and the seller can earn an additional amount if the seller meets defined performance criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
156
Q

Fixed Price with Economic Price Adjustment Contract (FPEPA)

A

A fixed-price contract, but with a special provision showing for predefined final adjustments to the contract price due to changed conditions, such as inflation changes, or cost increases (or decreases) for specific commodities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
157
Q

Float

A

Also called slack. In project management, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to:

subsequent tasks ("free float")
project completion date ("total float").
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
158
Q

Flowchart

A

The depiction in a diagram format of the inputs, process actions, and outputs of one or more processes within a system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
159
Q

Focus Groups

A

An elicitation technique that brings together prequalified stakeholders and subject matter experts to learn about their expectations and attitudes about a proposed product, service, or result

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
160
Q

Forecast

A

An estimate or prediction of conditions and events in the project’s future based on information and knowledge available at the time of the forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
161
Q

Forward Pass

A

A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or given point in time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
162
Q

Free Float

A

The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
163
Q

Functional Organization

A

An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority to assign work an apply resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
164
Q

Funding Limit Reconciliation

A

The process of comparing the planned expenditure of project funds against any limits on the commitment of funds for the project to identify any variances between the funding limits and the planned expenditures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
165
Q

Gantt Chart

A

A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars places according to start and finish dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
166
Q

Grade A

A

A category or rank used to distinguish items that have the same functional use but do not share the same requirements for quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
167
Q

Ground Rules

A

Expectations regarding acceptable behavior by project team members

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
168
Q

Histogram

A

A bar chart that shows the graphical representation of numerical data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
169
Q

Historical Information

A

Documents an data on prior projects including project files, records, correspondence, closed, contracts, and closed projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
170
Q

Identify Risks

A

The process of identifying individual risks as well as sources of overall risk and documenting their characteristics

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
171
Q

Identify Stakeholders

A

The process of identifying project stakeholders regularly and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
172
Q

Implement Risk Reponses

A

The process of implementing agreed-upon risk response plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
173
Q

Imposed Date

A

A fixed date imposed on a schedule activity or schedule milestone, usually in the form of a “start no earlier than” and “finish no later than” date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
174
Q

Incentive Fee

A

A set of financial incentives related to cost, schedule, or technical performance of the seller

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
175
Q

Incremental Life Cycle

A

An adaptive project life cycle in which the deliverable is produced through a series of iterations, that successively add functionality within a predetermined time frame. The deliverable contains the necessary and sufficient capability to be considered to complete only after the final iteration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
176
Q

Independent Estimates

A

A process of using a third party to obtain and analyze information to support the prediction of cost, schedule, or other items

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
177
Q

Influence Diagram

A

A graphical representation of situation showing causal influences, time ordering of events, and other relationships among variables and outcomes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
178
Q

Information

A

Organized or structured data, processed for a specific purpose to make it meaningful, valuable, and useful in specific contexts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
179
Q

Information Management Systems

A

Facilities, processes, and procedures used to collect, store, and distribute information between producers and consumers of information in physical or electronic format.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
180
Q

Initiating Process Group

A

Those processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project of phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
181
Q

Input

A

any item whether internal or external to the project, which is required by a process before that process proceeds. May be an output from a predecessor process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
182
Q

Inspection

A

Examination of a work product to determine whether it conforms to documented standards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
183
Q

Interpersonal and Team skills

A

Skills used to effectively lead and interact with team members and other stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
184
Q

Interpersonal skills

A

Skills used to establish and maintain relationships with other people

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
185
Q

Interviews

A

A forma or informal approach to elicit information from stakeholders by talking to them directly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
186
Q

Invitation for Bid (IFB)

A

Generally, this term is equivalent to request for proposal. However, in some application areas, it may have a narrower or more specific meaning.

187
Q

Issue

A

A current condition or situation that may have an impact on the project objectives

188
Q

Iterative Life Cycle

A

A project life cycle where the project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as the project team’s understanding of the product increases. Iterations develop the product through a series of repeated cycles, while increments successiely add to the functionality of the product

189
Q

Knowledge

A

A mixture of experience, values, and beliefs, contextual information, intuition, and insight that people use to make sense of new experiences and information

190
Q

Lag

A

The amount of time whereby a successor activity will be delayed with respect to a predecessor activity

191
Q

Late Finish Date (LF)

A

in the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network, the project completion date, and any schedule constraints

192
Q

Late Start Date (LS)

A

In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network loic, the project completion date, and any schedule constraints

193
Q

Lead

A

The amount of time whereby a successor activity can be advanced with respect to a predecessor activity

194
Q

Lessons Learned

A

The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance

195
Q

Lessons Learned Register

A

A project document used to record knowledge gained during a project so that it can be used in the current project and entered into the lessons learned repository

196
Q

Lessons Learned Repository

A

A store of historical information about lessons learned in projects

197
Q

Level of Effort (LOE)

A

An activity that does not produce definitive end products and is measured by the passage of time

198
Q

Log

A

A document used to record and describe or denote selected items identified during execution of a process or activity. Usually used with a modifier, such as issue, change, or assumption

199
Q

Logical Relationships

A

A dependency between two activities, or between an activity and a milestone.

200
Q

Make-or-Buy Analysis

A

The process of gathering and organizing data about product requirements and analyzing them against available alternatives including the purchase of internal manufacture or the product

201
Q

Make-or-Buy Decisions

A

Decision made regarding the external purchase or internal manufacture of a product

202
Q

Manage Communications

A

Manage Communications is the process of ensuring timely and appropriate collection, creating, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information

203
Q

Management Reserve

A

An amount of the project budget or project schedule held outside of the performance measurement baseline (PMB) for management control purposes, that is reserved for unforeseen work that is within the scope of the project

204
Q

Management Skills

A

The ability to plan, organize, direct, and control individuals or groups of people to achieve specific goals.

205
Q

Manage Project Knowledge

A

The process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning

206
Q

Manage Quality

A

The process of translating the quality management plan into executable quality activities that incorporate the organization’s quality policies into the project

207
Q

Manage Stakeholder Engagement

A

The process of communicating and working with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement.

208
Q

Manage Team

A

The process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance

209
Q

Mandatory Dependency

A

A relationship that is contractually required or inherent in the nature of the work

210
Q

Master Schedule

A

A summary-level project schedule that identifies the major deliverables and work breakdown structure components and key schedule milestones.

211
Q

Matrix Diagrams

A

A quality management and control tool used to perform data analysis within the organizational structure created in the matrix. The matrix diagram seeks to show the strength of relationships between factors, causes, and objectives that exist between the rows and columns that form the matrix

212
Q

Matrix Organization

A

Any organizational structure in which the project manager shares responsibility with the functional managers for assigning priorities and for directing the work of persons assigned to the project.

213
Q

Methodology

A

A system of practices, techniques, procedures, and rules used by those who work in a discipline

214
Q

Milestone

A

A significant point or event in a project, program, or portfolio

215
Q

Milestone Schedule

A

A type of schedule that presents milestones with planned dates. See also master schedule

216
Q

Mind-Mapping

A

A technique used to consolidate ideas created through individual brainstorming sessions into a single map to reflect commonality and differences in undersanding and to generate new ideas.

217
Q

Monitor

A

Collect project performance data, produce performance measures, and report and disseminate performance information

218
Q

Monitor and Control Project Work

A

The process of tracking, reviewing, and reporting overall progress to meet the performance objectives defined in the project management plan

219
Q

Monitor Communications

A

The process of ensuring that the information needs of the project and its stakeholders are met

220
Q

Monitoring and Controlling process Group

A

Those processes required to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes

221
Q

Monitor Risks

A

The process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project

222
Q

Monitor Stakeholder Engagement

A

The process of monitoring project stakeholder relationships, and tailoring strategies for engaging stakeholders through the modification of engagement strategies and plans

223
Q

Monte Carlo Simulation

A

An analysis technique where a computer model is iterated many times with the input values chosen at random for each iteration driven by te input data, including probability distributions and probabilistic branches. Outputs are generated to represent the range of possible outcomes for the project.

224
Q

Multicriteria Decision Analysis

A

This technique utilizes a decision matrix to provide a systematic analytical approach for establishing criteria, such as risk levels, uncertainty, and valuation, to evaluate and rank many ideas.

225
Q

Network Logic

A

All activity dependencies in a project schedule network diagram

226
Q

Network Path

A

A sequence of activities connected by logical relationships in a project schedule network diagram

227
Q

Networking

A

Establishing connections and relationship with other people from the same or other organizations

228
Q

Node

A

A point at which dependency lines connect on a schedule network diagram.

229
Q

Nominal Group Technique

A

A technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization

230
Q

Objective

A

Something toward which work is to be directed, a strategic position to be attained, a purpose to be achieved, a result to be obtained, a product to be produced, or a service to be performed

231
Q

Opportunity

A

A risk that would have a positive effect on one or more project objectives

232
Q

Organizational Breakdown Structure (OBS)

A

A hierarchical representation of the project organization, which illustrates the relationship between project activities and the organizational units that will perform those activities.

233
Q

Organizational Learning

A

A discipline concerned with the way individuals, groups, and organizations develop knowledge.

234
Q

Organizational Process Assets

A

Plan, processes, policies, procedures, and knowledge bases that are specific to and used by the performing organization

235
Q

Output

A

A product, result, or service generated by a process. May be an input to a successor process.

236
Q

Overall Project Risk

A

The effect of uncertainty on the project as a whole, arising from all sources of uncertainty including individual risks, representing the exposure of stakeholders to the implications of variations in project outcome, both positive and negative.

237
Q

Parametric Estimating

A

An estimating technique in which an algorithim is used to calculate cost or duration based on historical data and project parameters

238
Q

Path Convergence

A

A relationship in which a schedule activity has more than one predecessor

239
Q

Path Divergence

A

A relationship in which a schedule activity has more than one successor

240
Q

Percent Complete

A

An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component

241
Q

Performance Measurement Baseline (PMB)

A

integrated scope, schedule, and cost baselines used for comparison to manage, measure, and control project executions

242
Q

Performance Reviews

A

A technique that is used to measure compare, and analyze actual performance of work in progress on the project against the baseline

243
Q

Perform Integrated Change Control

A

The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating the decisions

244
Q

Perform Qualitative Risk Analysis

A

The process of prioritizing individual projects risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics

245
Q

Perform Quantitative Risk Analysis

A

The process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives

246
Q

Phase Gate

A

A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or program

247
Q

Plan Communications Management

A

The process of developing an appropriate approach and plan for project communication activities based on the information needs of each stakeholder or group, available organizational assets, and the needs of the project.

248
Q

Plan Cost Management

A

The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.

249
Q

Planned Value (PV)

A

the authorized budge assigned to scheduled work

250
Q

Planning Package

A

A work breakdown structure component below the control account with known work contenet but without detailed scheduled activities

251
Q

Planning Process Group

A

Those processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to acheive.

252
Q

Plan Procurement Management

A

The process of documenting project procurement procurement decisions, specifying the approach, and identifying potential sellers

253
Q

Plan Quality Management

A

The process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with quality requirements and/or standards

254
Q

Plan Resource Management

A

The process of defining how to estimate, acquire, manage, and utilize physical and team resources

255
Q

Plan Risk Management

A

The process of defining how to conduct risk management activities for a project.

256
Q

Plan Risk Responses

A

the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks

257
Q

Plan Schedule Management

A

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule

258
Q

Plan Scope Management

A

The process of creating a scope management plan that documents how the project and product scop will be defined, validated, and controlled

259
Q

Plan Stakeholder Engagement

A

The process of developing approaches to invovle project stakeholders, based on their needs, expectations, interests, and potential impact on the project

260
Q

Plurality

A

Decisions made by the largest block in a group, even if a majority is not achieved

261
Q

Policy

A

A structured pattern of actions adopted by an organizations such that the organization’s policy can be explained as a set of basic principles that govern the organization’s conduct

262
Q

Portfolio

A

Projects, Programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives

263
Q

Portfolio Management

A

The centralized management of one or more portfolios to achieve strategic objectives

264
Q

Practice

A

A specific type of professional or management activity that contributes to the execution of a process and that may employ one or more techniques and tools

265
Q

Precedence Diagramming Method (PDM)

A

A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed

266
Q

Precedence Relationship

A

A logical dependency used in the precedence diagramming method

267
Q

Predecessor Activity

A

An activity that logically comes before a dependent activity in a schedule

268
Q

Predictive Life Cycle

A

A form of project life cycle in which the project scope, time, and cost are determined in the early phases of the life cycle

269
Q

Preventive Action

A

An intentional activity that ensures the future performance of the project work is aligned with the project management plan

270
Q

Probability and Impact Matrix

A

A grid for mapping the probability of occurrence of each risk and its impact on project management objectives if that risk occurs

271
Q

Procedure

A

An established method of accomplishing a consistent performance or result, a procedure typically can be described as the sequence of steps that will be used to execute a process

272
Q

Process

A

A systematic series of activities directed towards causing and end result such that one of more inputs will be acted upon to create one more more outputs

273
Q

Procurement Audits

A

The review of contracts and contracting processes for completeness, accuracy, and effectiveness

274
Q

Procurement Documentation

A

All documents used in signing, executing, and closing an agreement. Procurement documentation may include documents predating the project

275
Q

Procurement Management Plan

A

A component of the project or program management plan that describes how a project team will acquire goods and services from outside of the performing organization

276
Q

Procurement Statement of Work

A

Describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results

277
Q

Procurement Strategy

A

The approach by the buyer to determine the project delivery method and the type of legally binding agreement(s) that should be used to deliver the desired results

278
Q

Product

A

An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item. Additional words for products are material and goods

279
Q

Product Analysis

A

For projects that have a product as a deliverable, it is a tool to define scope that generally means asking questions about a product and forming answers to describe the use, characteristics, and other relevant aspects of what is going to be manufactured.

280
Q

Product Life Cycle

A

The series of phases that represent the evolutions of a product, from concept through delivery, growth, maturity, and to retirement.

281
Q

Product Scope

A

The features and functions that characterize a product, service, or results

282
Q

Product Scope Description

A

The documented narrative description of the product scope

283
Q

Program

A

Related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually

284
Q

Program Management

A

The application of knowledge, skills, and principles to a program to achieve the program objectives and obtain benefits and control not available by managing program components individually

285
Q

Progressive Elaboration

A

The iterative process of increasing the level of detail in a project management plan as a greater amounts of information and more accurate estimates become available.

286
Q

Project

A

A temporary endeavor undertaken to create a unique product, service, or result

287
Q

Project Charter

A

A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities

288
Q

Project Communications Management

A

Project Communications Management includes the processes require to ensure timely and appropriate planning, collection, creating, distribution, storage, retrieval, management, control, monitoring, and ultimate disposition of project information

289
Q

Project Cost Maangement

A

Project Cost Management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so the project can be completed within the approved budget

290
Q

Project Funding Requirements

A

Forecast project costs to be paid that are derived from the cost baseline for total or periodic requirements, including projected expenditures plus anticipated liabilites

291
Q

Project Governance

A

The framework, functions, and processes that guide project management activites in order to create a unique product, service, or result to meet organizational, strategic, and operational goals.

292
Q

Project Initiation

A

Launching a process that can result in the authorization of a new project.

293
Q

Project Integration Management

A

Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups

294
Q

Project Life Cycle

A

The series of phases that a project passes through from its start to its completion

295
Q

Project Management

A

The application of knowledge, skills, tools, and techniques to project activities and meet the project requirements

296
Q

Project Management Body of Knowledge

A

A term that describes the knowledge within the profession of project management . The project management body of knowledge includes proven traditional practices that are widely applied as well as innovative practices that are emerging in the profession

297
Q

Project Management Information System

A

An information system consisting of the tools and techniques used to gather, integrate, and disseminate the outputs of project management processes.

298
Q

Project Management Knowledge Area

A

An identified area of project management defined by its knowledge requirements and described in terms of its component processes, practices, inputs, outputs, tools and techniques

299
Q

Project Management Office (PMO)

A

A management structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools and techniques

300
Q

Project Management Plan

A

The document that describes how the project will be executed, monitored and controlled and closed

301
Q

Project Management Process Group

A

A logical grouping of project management inputs, tools and techniques, and outputs. The project Management Process Groups include initiating processes, planning processes, executing processes, monitoring and controlling processes, and closing processes. Project Management Process Groups are not project phases

302
Q

Project Management System

A

The aggregation of the processes, tools, techniques, methodologies, resources, and procedures to manage a project

303
Q

Project Management Team

A

The members of the project team who are directly involved in project management activities.

304
Q

Project Manager (PM)

A

The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives

305
Q

Project Organization Chart

A

A document that graphically depicts the project team members and their interrelationships for a specific project

306
Q

Project Phase

A

A collection of logically related project activities that culminates in the completion of one or more deliverables

307
Q

Project Procurement Management

A

Project Procurement Management includes the processes necessary to purchase or acquire products, services, or results needed from outside the project team

308
Q

Project Quality Management

A

Project Quality Management includes the processes for incorporating the organizations quality policy regarding planning, managing, and controlling project and product quality requirements, in order to meet stakeholders’ expectations

309
Q

Project Resource Management

A

Project Resource Management includes the processes to identify, acquire, and manage the resources needed for the successful completions of the project.

310
Q

Project Risk Management

A

Project Risk Management includes the processes of conducting risk management planning identification, identification, analysis, response planning, response implementation, and monitoring risk on a project

311
Q

Project Schedule

A

An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources

312
Q

Project Schedule Management

A

Project Management includes the processes required to manage the timely completion of the project

313
Q

Project Schedule Network Diagram

A

A graphical representation of the logical relationships among the project schedule activities

314
Q

Project Scope

A

The work performed to deliver a product, service, or result with the specified features and functions

315
Q

Project Scope Management

A

Project Scope Management includes the processes required to ensure that the project includes all the work required, and only, and only the work required, to complete the project successfully

316
Q

Project Scope Statement

A

The description of the project scope, major deliverables, and exclusions.

317
Q

Project Stakeholder Management

A

Project Stakeholder Management includes the processes required to identify the people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project, and to develop appropriate management strategies for effectively engaging stakeholders in project decisions and execution

318
Q

Project Team

A

A set of individuals who support the project manager in performing the work of the project to achieve its objectives

319
Q

Project Team Directory

A

A documented list of project team members, their project roles, and communication information

320
Q

Proposal Evaluation Techniques

A

The process of reviewing proposals provided by suppliers to support contract award decisions

321
Q

Prototypes

A

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building it

322
Q

Quality

A

The degree to which a set of inherent characteristics fulfills requirements

323
Q

Quality Audits

A

A quality audit is a structured, independent process to determine if project activities comply with organizational and project policies, processes, and procedures

324
Q

Quality Checklists

A

A structured tool used to verify that a set of required steps has been performed

325
Q

Quality Control Measurements

A

the documented results of control quality activities

326
Q

Quality Management Plan

A

A component of the project or program management plan that describes how applicable policies, procedures, and guidelines will be implemented to achieve the quality objectives

327
Q

Quality Management System

A

The organizational framework whose structure provides the policies, processes, procedures, and resources required to implement the quality management plan. The typical project quality management plan should be compatible to the organization’s quality management system

328
Q

Quality Metrics

A

A description of a project or product attribute and how to measure it

329
Q

Quality Policy

A

A policy specific to the project quality management knowledge area, it establishes the basic principles that should govern the organization’s actions as it implements its system for quality management

330
Q

Quality Report

A

A project document that includes quality management issues, recommendations for corrective actions, and a summary of findings from quality control activities and may include recommendations for process, project, and product improvements

331
Q

Quality Requirement

A

A condition or capability that will be used to assess conformance by validating the acceptability of an attribute for the quality of a result

332
Q

Questionnaires

A

Written sets of questions designed to quickly accumulate information from a large number of respondents

333
Q

RACI Chart

A

a common type of responsibility matrix that uses responsible, accountable, consult, and inform statuses to define the involvement of stakeholders in project activities

334
Q

Regression Analysis

A

An analytical technique where a series of input variables are examined in relation to their corresponding output results in order to develop a mathematical or statistical relationship

335
Q

Regulations

A

Requirements imposed by a governmental body. These requirements can establish product, process, or service characteristics, including applicable administrative provisions that have government-mandated compliance

336
Q

Request for Information (RFI)

A

A type of procurement document whereby the buyer requests a potential seller to provide various pieces of information related to a product or service or seller capability

337
Q

Request for Proposal (RFP)

A

A type of procurement document used to request proposals from prospective sellers of products or services in some application areas, it may have a narrower or more specific meaning.

338
Q

Request for Quotation (RFQ)

A

A type of procurement document used to request price quotations from prospective sellers of common or standard products or services. Sometimes used in place of request for proposal and, in some application areas, it may have a narrower or more specific meaning

339
Q

Requirement

A

A condition or capability that is necessary to be present in a product, service or result to satisfy a business need

340
Q

Requirements Documentation

A

A description of how individual requirements meet the business need for the project

341
Q

Requirements Management Plan

A

A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed

342
Q

Requirements Traceability Matrix

A

A grid that links product requirements from their origin to the deliverables that satisfy them

343
Q

Reserve

A

A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g. management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated.

344
Q

Reserve Analysis

A

An Analytical technique to determine the essential features and relationship of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project

345
Q

Residual Risk

A

The risk that remains after risk responses have been implemented

346
Q

Resource

A

A team member or any physical item needed to complete the project

347
Q

Resource Breakdown Structure

A

A hierarchical representation of resources by category and type

348
Q

Resource Calendar

A

A calendar that identifies the working days and shifts upon which each specific resource is available

349
Q

Resource Histogram

A

a bar chart showing the amount of time that a resource is scheduled to work over a series of time periods

350
Q

Resource Leveling

A

A resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect critical path.

351
Q

Resource Management Plan

A

A component of the project management plan that describes how project resources are acquired, allocated, monitored, and controlled

352
Q

Resource Manager

A

An individual with management authority over one or more resources

353
Q

Resource Optimization Technique

A

A technique in which activity start and finish dates are adjusted to balance demand for resources with the available supply.

354
Q

Resource Requirements

A

The types and quantities of resources for each activity in a work package

355
Q

Resource Smoothing

A

A resource optimization technique in which free ant total float are used without affecting the critical path.

356
Q

Responsibility

A

An assignment that can be delegated within a project management plan such that the assigned resource incurs a duty to perform the requirements of the assignment

357
Q

Responsibility Assignment Matrix (RAM)

A

A grid that shows the project resources assigned to each work package

358
Q

Result

A

An output from performing project management processes and activities. Results include outcomes (e.g. integrated systems, revised process, restructured organization, tests, trained personnel, etc.) and documents (e.g. policies, plans, studies, procedures, specifications, reports, etc.)

359
Q

Rework

A

Action taken to bring a defective or nonconforming components into compliance with requirements or specifications

360
Q

Risk

A

An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.

361
Q

Risk Acceptance

A

A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs

362
Q

Risk Appetite

A

The degree of uncertainty an organization or individual is willing to accept in anticipation of a reward

363
Q

Risk Audit

A

Type of audit used to consider the effectiveness of the risk management process

364
Q

Risk Avoidance

A

A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact

365
Q

Risk Breakdown Structure (RBS)

A

A hierarchical representation of potential sources of risk

366
Q

Risk Categorization

A

Organization by sources of risk (e.g., using the RBS) , the area of the project affected (e.g. using the WBS) or other useful category (e.g. project phase) to determine the areas of the project most exposed to the effects of uncertainty

367
Q

Risk Category

A

a group of potential causes of risk

368
Q

Risk Data Quality Assessment

A

Technique to evaluate the degree to which the data about risks is useful for risk management

369
Q

Risk Enhancement

A

A risk response strategy whereby the project team acts to increase the probability of occurrence or impact of an opportunity

370
Q

Risk Escalation

A

A risk response strategy whereby the team acknowledges that a risk is outside of its sphere of influence and shifts the ownership of the risk to a higher level of the organization where it is more effectively managed

371
Q

Risk Exploiting

A

A risk response strategy whereby the project team acts to ensure that an opportunity occurs

372
Q

Risk Exposure

A

An aggregate measure of the potential impact of all risks at any given point in time in a project, program or portfolio

373
Q

Risk Management Plan

A

A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed

374
Q

Risk Mitigation

A

A risk response strategy whereby the project team acts to decrease the probability of occurrence or impact of a threat

375
Q

Risk Owner

A

The person responsible for monitoring the risks and for selecting and implementing an appropriate risk response strategy

376
Q

Risk Register

A

A repository in which outputs of risk management processes are recorded

377
Q

Risk Report

A

A project document developed progressively throughout the Project Risk Management processes, which summarizes information on individual project risks and the level of overall project risk

378
Q

Risk Review

A

A meeting to examine and document the effectiveness of risk responses in dealing with overall project risk and with identified individual project risks

379
Q

Risk Sharing

A

A risk response strategy whereby the project team allocates ownership of an opportunity to a third party who is best able to capture the benefit of that opportunity

380
Q

Risk Threshold

A

The measure of acceptable variation around an objective that reflects the risk appetite of the organization and stakeholders (risk appetite)

381
Q

Risk Transference

A

A risk response strategy whereby the project team shifts the impact of a threat to a third party together with ownership of the response

382
Q

Role

A

A defined function to be performed by a project team member , such as testing, filing, inspecting, or coding

383
Q

Rolling Wave Planning

A

An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level

384
Q

Root Cause Analysis

A

An analytical technique used to determine the basic underlying reason that causes a variance or a defect or a risk. A root cause may underlie more than one variance or defect or risk

385
Q

Schedule Baseline

A

The approved version of a schedule model that can be changed using formal change control procedures and is used as the basis for comparison to actual results

386
Q

Schedule compression

A

A technique used to shorten the schedule duration without reducing the project scope

387
Q

Schedule Data

A

The collection of information for describing and controlling the schedule

388
Q

Schedule Forecasts

A

Estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time the schedule is calculated

389
Q

Schedule Management Plan

A

A component of the project or program management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule

390
Q

Schedule Model

A

A representation of the plan for executing the project’s activities including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling events

391
Q

Schedule Network Analysis

A

A technique to identify early and late start dates, as well as early and late finish dates, for the uncompleted portions of project activities

392
Q

Schedule Performance Index (SPI)

A

A measure of schedule efficiency expressed as te ratio of earned value to planned value

393
Q

Schedule Variance (SV)

A

A measure of schedule performance expressed as the difference between the earned value and the planned value

394
Q

Scheduling Tool

A

A tool that provides schedule component names, definitions, structural relationships, and formulas that support the application of a scheduling method

395
Q

Scope

A

The sum of the product, services, and results to be provided as a project

396
Q

Scope Baseline

A

The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed using formal change control procedures and is used as a basis for comparison to actual results

397
Q

Scope Creep

A

The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources

398
Q

Scope Management Plan

A

A component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and validated

399
Q

Secondary Risk

A

A risk that arises as a direct result of implementing a risk response

400
Q

Self -Organizing Teams

A

A team formation where the team functions with an absence of centralized control

401
Q

Seller

A

A provider or supplier of products, services, or results to an organization

402
Q

Seller Proposals

A

Formal responses from sellers to a request for proposal or other procurement document specifying the price, commercial terms of sale, and technical specifications or capabilities the seller will do for the requesting organization that, if accepted, would bind the seller to perform the resulting agreement

403
Q

Sensitivity Analysis

A

An Analysis technique to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes, by correlating variation in project outcomes with variations in elements of quantitative risk analysis model

404
Q

Sequence Activities

A

The process of identifying and documenting among the project activities

405
Q

Service Level Agreement (SLA)

A

A contract between a service provider (either internal or external) and the end user that defines the level of service expected from the service provider

406
Q

Simulation

A

An analytical technique that models the combined effect of uncertainties to evaluate their potential impact on objectives.

407
Q

Source Selection Criteria

A

A set of attributes desired by the buyer which a seller is required to meet or exceed to be selected for a contract

408
Q

Specification

A

A precise statement of the needs to be satisfied and the essential characteristics that are required

409
Q

Specification Limits

A

The area, on either side of the centerline, or mean, of data plotted on a control chart that meets the customer’s requirements for a product or service. This area may be greater than or less than the area defined by the control limits

410
Q

Sponsor

A

A person or group who provides resources and support for the project, program, or portfolio and is accountable for enabling success

411
Q

Sponsoring Organization

A

The entity responsible for providing the project’s sponsor and a conduit for project funding or other project resources

412
Q

Stakeholder

A

An individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project, program, or portfolio

413
Q

Stakeholder Analysis

A

A technique of systematically gathering and analyzing quantitative and qualitative information to determine whose interest should be taken into account throughout the project.

414
Q

Stakeholder Engagement Assessment Matrix

A

A matrix that compares current and desired stakeholder engagement levels

415
Q

Stakeholder Engagement Plan

A

A component of the project management plan that identifies the strategies and actions required to promote productive involvement of stakeholders in project or program decision making and execution

416
Q

Stakeholder Register

A

A project document including the identification, assessment, and classification of project stakeholders

417
Q

Standard

A

a document established by an authority, custom, or general consent as a model or example

418
Q

Start Date

A

A point in time associated with a schedule activity’s start, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline, or current

419
Q

Start-to-Finish (SF)

A

a logical relationship in which a predecessor activity cannot finish until a successor activity has started

420
Q

Start-to-Start (SS)

A

A logical relationship in which a successor activity cannot start until a predecessor activity has started

421
Q

Statement of Work (SOW)

A

A narrative description of products, services, or results to be delivered by the project

422
Q

Statistical Sampling

A

Choosing part of a population of interest for inspection

423
Q

Successor Activity

A

A dependent activity that logically comes after another activity in a schedule

424
Q

Summary Activity

A

A group of related schedule activities aggregated and displayed as a single activity

425
Q

SWOT Analysis

A

Analysis of strengths, weaknesses, opportunities, and threats of an organization, project, or option

426
Q

Tacit Knowledge

A

Personal knowledge that can be difficult to articulate and share such as beliefs, experience, and insights

427
Q

Tailoring

A

Determining the appropriate combination of processes, inputs, tools, techniques, outputs, and life cycle phases to manage a project

428
Q

Team Charter

A

a document that records the team values, agreements, and operating guidelines, as well as establishing clear expectation regarding acceptable behavior by project team members

429
Q

Team Management Plan

A

A component of the resource Management plan that describes when and how team members will be acquired and how long they will be needed

430
Q

Technique

A

A defined systematic procedure employed by a human resource to perform and activity to produce a product or result or deliver a service, and that may employ one or more tools

431
Q

Templates

A

A partially complete document in a predefined format that provides a defined structure for collecting, organizing, and presenting information and data.

432
Q

Test and Evaluation Documents

A

Project documents that describe the activities used to determine if the product meets the quality objectives stated in the quality management plan

433
Q

Threat

A

A risk that would have a negative effect on one or more project objectives

434
Q

Three-Point Estimating

A

A technique used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates

435
Q

Threshold

A

A predetermined value of a measurable project variable that represents a limit that requires action to be taken if it is reached

436
Q

Time and Material Contract (T&M)

A

A type of contract that is a hybrid contractual arrangement containing aspects of both cost-reimbursable and fixed-price contracts

437
Q

To-Complete Performance Index (TCPI)

A

a measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget

438
Q

Tolerance

A

the quantified description of acceptable variation for a quality requirement

439
Q

Tool

A

Something tangible, such as a template or software program, used in performing an activity to produce a product or result

440
Q

Tornado Diagram

A

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables

441
Q

Total Float

A

The amount of time tht a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint

442
Q

Trend Analysis

A

An analytical technique that uses mathematical models to forecast future outcomes based on historical results

443
Q

Trigger Conditions

A

An event or situation that indicates that a risk is about to occur

444
Q

Unanimity

A

Agreement by everyone in the group on a single course of action

445
Q

Update

A

A modification to any deliverable, project management plan component, or project document that is not under formal change control.

446
Q

Validate Scope

A

The process of formalizing acceptance of the completed project deliverables

447
Q

Validation

A

The assurance that a product, service, or result meets the needs of the customer and other identified stakeholders. Contrast with verification

448
Q

Variance

A

A quantifiable deviation, departure, or divergence away from a known baseline or expected result

449
Q

Variance Analysis

A

A technique for determining the cause and degree of difference between the baseline and actual performance

450
Q

Variance At Completion (VAC)

A

A projection of the amount of budget deficit or surplus expressed as the difference between the budget at completion and the estimate at completion

451
Q

Variation

A

an actual condition that is different from the expected condition that is contained in the baseline plan

452
Q

Verification

A

The evaluation of whether or not a product, service, or result complies with a regulation, requirement, specification, or imposed condition. Contrast with Validation

453
Q

Verified Deliverables

A

Completed project deliverables that have been checked and confirmed for correctness through the Control Quality Process

454
Q

Virtual Teams

A

Groups of people with a shared goal who fulfill their roles with little or not time spent meeting face to face

455
Q

Voice of the customer

A

A planning technique used to provide products, services, and results that truly reflect customer requirements by translating those customer requirements into the appropriate technical requirements for each phase of project product development

456
Q

WBS Distionary

A

A document that provides detailed deliverable, activity, and scheduling information about each component in the work breakdown structure

457
Q

What-if Scenario Analysis

A

the process of evaluating scenarios in order to predict their effect on project objectives

458
Q

Work Breakdown Structure (WBS)

A

a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables

459
Q

Work Breakdown Structure Component

A

An entry in the work breakdown structure that can be at any level

460
Q

Work Package

A

The work defined at the lowest level of the work breakdown structure for which cost and duration are estimated and managed

461
Q

Work Performance Data

A

the raw observations and measurement identified during activities being performed to carry out the project work

462
Q

Work performance Information

A

The performance data collected from controlling processes, analyzed in comparison with project management plan components, project documents, and other work performance information

463
Q

Work Performance Reports

A

The physical or electronic representation of work performance information compiled in project documents, intended to generate decisions, actions, or awareness