PMBOK Vocabulary Flashcards
Acceptance Criteria
A set of conditions that is required to be met before deliverables are accepted.
Accepted Deliverables
Products, Results, or capabilities produced by a project and validated by the project customer or sponsors as meeting their specified acceptance criteria
Accuracy
Within the quality management system, accuracy is an assessment of correctness
Acquire Resources
The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work
Acquisition
Obtaining human and material resources necessary to perform activities. Acquisition implies a cost of resources, and is not necessarily financial
Activity
A distinct, scheduled portion of work performed during the course of a project
Activity Attributes
Multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
Activity Duration
The time in calendar units between the start and finish of a schedule activity
Activity Duration Estimates
The quantitative assessments of the likely number of time periods that are required to complete and activity
Activity List
A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.
Activity-on-Node (AON)
project management term that refers to a precedence diagramming method which uses boxes to denote schedule activities. These various boxes or “nodes” are connected from beginning to end with arrows to depict a logical progression of the dependencies between the schedule activities. Each node is coded with a letter or number that correlates to an activity on the project schedule. FINISH to START
Actual Cost (AC)
the realized cost incurred for the work performed on an activity during a specific time period.
Actual Duration
The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete.
Adaptive Life Cycle
A project life cycle that is iterative or inceremental
Affinity Diagrams
A technique that allows large numbers of ideas to be classified into groups for review and analysis
Agreements
Any document or communication that defines the initial intentions of a project. This can take the form of a contract, memorandum of understanding (MOU), letters of agreement, verbal agreements, email, etc
Alternative Analysis
A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project
Analogous Estimating
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
Analytical Techniques
Various techniques used to evaluate, analyze, or forecast potential outcomes based on possible variations of project or environmental variables and their relationships with other variables.
Assumption
A factor in the planning process that is considered to be true, real, or certain, without proof of demonstration
Assumption Log
A project Document used to record all assumptions and constraints throughout the project life cycle
Attribute Sampling
Method of measuring quality that consists of noting the presence (or absence) of some characteristic (attribute) in each of the units under consideration.
Authority
the right to apply project resources, expend funds, make decisions, or give approvals
backward pass
a critical path method technique for calculating the late start and the late finish dates by working backward through the schedule model from the project end date