Earned Value Formulas Flashcards
1
Q
EV
What IS done
A
Actual % x BAC
2
Q
PV
work to be done
A
Planned % x BAC
3
Q
AC
Actual Spend
A
Sum of Actual Costs
4
Q
CV
A
EV-AC
5
Q
EAC
A
BAC/CPI
6
Q
ETC
A
EAC-AC
7
Q
TCPI
A
(BAC-EV)/(BAC-AC)
8
Q
VAC
A
BAC-EAC
9
Q
SV
A
EV-PV
10
Q
CPI
A
EV/AC
Less than 1 is unfavorable conditions
11
Q
SPI
A
EV/PV
Greater than or equal to 1 is favorable
12
Q
BAC
Total Budget
A
Budget at completion