PMBOK Chapter 7 - Project Cost Management Flashcards

1
Q

<p>Project Cost Management (knowledge area)</p>

A

<p>includes the processes involved managing the costs so that the project can be completed within the approved budget</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

<p>Plan Cost Management (process)</p>

A

<p>the process that establishes the policies, procedures, and documentation for managing and controlling project costs</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

<p>Estimate costs (process)</p>

A

<p>the process of developing an approximation of the monetary resources needed to complete project activities</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

<p>Determine Budget (process)</p>

A

<p>the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

<p>Control Costs (process)</p>

A

<p>the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

<p>What is the cost management plan?</p>

A

<p>component of the project management plan and describes how the project costs will be planned, structured, and controlled.</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

<p>What is the human resource management plan?</p>

A

<p>provides project staffing attributes, personnel rates and related rewards/recognition which are necessary components for developing the project cost estimates</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

<p>What is the Cost of Quality (COQ)?</p>

A

<p>assumptions about costs of quality may be used to prepare the activity cost estimate</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

<p>What is Vendor Bid Analysis?</p>

A

<p>cost estimating methods may include analysis of what the project should cost, based on the responsive bids from qualified vendors</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

<p>What are Activity Cost Estimates?</p>

A

<p>quantitative assessments of the probable costs required to complete project work, can be in summary form or in detail</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

<p>What is the Basis of Estimates?</p>

A

<p>supporting documentation that should provide a clear and complete understanding of how the cost estimate was delivered</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

<p>What is cost aggregation?</p>

A

<p>cost estimates are aggregated by work packages in accordance with the WBS, the work package cost estimates are then aggregated for the higher component levels of the WBS and ultimately for the entire project</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

<p>What are historical relationships?</p>

A

<p>any historical relationships that result in parametric estimates or analogous estimates involve the use of project characteristics to develop mathematical models to predict total project costs</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

<p>What is a funding limit reconciliation?</p>

A

<p>the expenditure of funds should be reconciled with any funding limits on the commitment of funds for the project</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

<p>What is a cost baseline?</p>

A

<p>the approved version of the time-phased project budget, excluding any management reserves, which can only be changed through formal change control procedures</p>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

<p>What are project funding requirements?</p>

A

<p>total funding requirements and periodic funding requirements are derived from the cost baseline</p>

17
Q

<p>What is Earned Value Management (EVM)?</p>

A

<p>methodology that combines scope, schedule and resource measurements to assess project performance and progress. It integrates the three baselines to create the performance measurement baseline</p>

18
Q

<p>What is Planned Value (PV)?</p>

A

<p>the authorized budget assigned to scheduled work</p>

19
Q

<p>What is Earned Value (EV)?</p>

A

<p>a measure of work performed expressed in terms of the budget authorized for that work</p>

20
Q

<p>What is Actual Cost (AC)?</p>

A

<p>the realized cost incurred for the work performed on an activity during a specific time period</p>

21
Q

<p>What is Schedule Variance (SV)?</p>

A

<p>a measure of schedule performance expressed as the difference between the earned value and the planned value

SV = EV - PV</p>

22
Q

<p>What is Cost Variance (CV)?</p>

A

<p>the amount of budget deficit or surplus at a given point in time; expressed as the difference between earned value and actual cost

CV = EV - AC</p>

23
Q

<p>What is Schedule Performance Index (SPI)?</p>

A

<p>a measure of schedule efficiency expressed as the ratio of earned value to planned value

SPI = EV / PV</p>

24
Q

<p>What is Cost Performance Index (CPI)?</p>

A

<p>a measure of the cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost

CPI = EV / AC</p>

25
Q

<p>What is forecasting?</p>

A

<p>the project team may develop a forecast for the estimate at completion (EAC) that may differ from the budget at completion (BAC) based on the project performance</p>

26
Q

<p>Three common ways to develop EACs:</p>

A

<p>1) EAC forecast for ETC work performed at the budgeted rate: EAC = AC + (BAC - EV)

2) EAC forecast for ETC work performed at the present CPI: EAC = BAC / CPI
3) EAC forecast for ETC work considering both SPI and CPI factors: EAC = AC + [(BAC - EV) / ( CPI * SPI)]</p>

27
Q

<p>What is To-Complete-Performance-Index (TCPI)?</p>

A

<p>a measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as a ratio of the cost to finish the outstanding work to the remaining budget.

TCPI based on the BAC: TCPI = (BAC - EV) / (BAC - AC)
TCPI based on the EAC: TCPI = (BAC - EV ) / (EAC - AC)</p>

28
Q

<p>ITTO's for Plan Cost Management</p>

A

<p>Inputs: (Project Charter, OPA, Project Management Plan, EEF)
TT: (Expert Judgment, Data Analysis, Meeting)
Output: (Cost Management Plan)</p>

29
Q

<p>ITTO's for Estimate Cost</p>

A

<p>Inputs: (Project Management Plan, EEF, OPA, Project Documents)
TT: (Analogous Estimating, Parametric Estimating, Expert Judgement, Bottom-Up Estimating, Three-Point Estimate)
Output: (Estimate Cost)</p>

30
Q

<p>Level of Cost Estimating Accuracy</p>

A

<p>1. ROM - Rought Order of Magnitude (-25% to +75%)

2. Budget Estimate - (Must have Scope) (-10% to +25%)
3. Definitive Estimate (Bottom Up Estimate) (-5% to +10%)</p>

31
Q

<p>Types of Cost</p>

A

<p>1. Direct Cost

2. Indirect Cost
3. Variable Cost
4. Fixed Cost</p>

32
Q

<p>ITTO's for Budget Estimate</p>

A

<p>Inputs: (Project Management Plan, EEF, OPA, Project Documents, Business Documents, Project Schedule, Agreements)
TT: (Cost Aggregation, Data Analysis, Historical Information, Funding Limit Reconciliation, Financing)
Output: (Determine Budget, Cost Baseline, Project Funding Requirements, Update Project Management Plan)</p>

33
Q

Processes in Project Cost Management

A
  1. Plan Cost Management
  2. Estimate Cost
  3. Determine Budget
  4. Cost Control
34
Q

ITTO’s for Cost Control

A

Inputs: (Project Management Plan, EEF, OPA, Project Documents, Business Documents, Project Funding Requirements, WP Data)
TT: (Data Analysis, Expert Judgement, To Complete Performance Index)
Output: (Cost Forecast, Work Performance Information, Change Request Project Document Updates, Update Project Management Plan)