PM Processes and Role of the Project Manager Flashcards

1
Q

Which statement is FALSE regarding the initiating process group?

A. Cost and staffing start low, increase toward the end, and drop rapidly near closing.
B. Project risk is highest at the beginning of the project and reduces as the project
approaches its end.
C. Stakeholder influence is highest at the start and diminishes as the project proceeds.
D. The project manager and team are always identified as part of the initiating process
group.

A
  1. D: The project manager is assigned during project initiating, but some of the team members will be acquired during executing process group.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

All of the following will occur during project initiating EXCEPT:

A. Creation of a project scope statement.
B. Identification of internal and external stakeholders.
C. Development and review of the business case and a feasibility study.
D. Assignment of the project manager to lead a project.

A
  1. A: The project scope statement is an output of the Define Scope process and is part of the planning process group.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Which of the following will occur only during the planning process group?

A. Identify stakeholders
B. Develop schedule
C. Acquire project team
D. Validate scope

A
  1. B: Only Develop Schedule will occur during the planning process group. Identify Stakeholders occurs during initiating, Acquire Project Team occurs during executing, and Validate Scope occurs during monitoring & controlling.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Which of the following process groups consists of the processes to complete the
    work defined in the project management plan and ultimately satisfies the project
    specifications and objectives?

A. Planning process group
B. Executing process group
C. Initiating process group
D. Closing process group

A
  1. B: The executing process group is intended to ensure that the work defined in the project plan is performed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. A knowledge area represents a complete set of activities, concepts, and terms that make up an area of specialization, project management field, or professional field. Each project management knowledge area is subdivided into which of the following?

A. Best practices
B. Policies
C. Processes
D. Guidelines

A
  1. C: Each project management knowledge area is subdivided into specific processes, each of which is characterized by its inputs, tools & techniques, and outputs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. All of the following should be done during the closing process group EXCEPT:

A. Formal sign-off and formal acceptance are received from the customers.
B. Customer acceptance criteria are determined.
C. Final versions of the lessons learned are compiled and made available for future
projects.
D. Completed project deliverables are handed off to operations and maintenance.

A
  1. B: Customer acceptance criteria are determined during the initiating process group.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. In which process group does the team track, measure, inspect, monitor, verify, review, compare, and regulate the progress and performance of the project; ensure that the
    plan is working; identify any areas in which changes to the plan are required; and initiate
    the corresponding changes?

A. Monitoring & Controlling
B. Closing
C. Initiating
D. Executing

A
  1. A: During the monitoring & controlling process group, project performance is measured and analyzed, and needed changes are identified and approved.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. You are overseeing a project for your organization to implement a web-based
    application for accessing pay and tax information online. Currently, you are in the
    process of implementing approved changes, corrective actions, preventive actions, and defect repairs in the project. You are in which of the following process groups?

A. Executing
B. Monitoring & Controlling
C. Planning
D. Closing

A
  1. A: Usually a project will enter the executing process group when the planning is completed or the project management plan has been updated due to change requests, including defect repairs and corrective and preventive actions. The executing process group involves coordinating people and resources as well as integrating and performing the activities of the project in accordance with the project management plan. These approved change requests for corrective actions, preventive actions, and defect repairs
    are implemented in the executing process group.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Which one of the following statements is FALSE about the executing process group?

A. This process group usually takes the most time and resources.
B. The processes in this process group measure and analyze the progress and
performance of the project, ensure that the plan is working, identify any areas in
which changes to the plan are required, and initiate the corresponding changes.
C. Corrective actions, preventive actions, and defect repairs are implemented in this
process group.
D. This process group consists of processes to complete the work defined in the project
management plan and ultimately satisfies the project specifications and objectives.

A
  1. B: The processes in the monitoring & controlling process group track, measure, inspect, monitor, verify, review, compare, and regulate the progress and performance of the project; ensure that the plan is working; identify any areas in which changes to the plan are required; and initiate the corresponding changes.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. The sponsor has just signed the project charter and assigned you as a project manager to oversee a project to implement a simulator for a local golf club. What should you do FIRST as the project manager?

A. Focus on identifying and classifying the stakeholders in the project.
B. Start working on the project management plan.
C. Develop the project schedule.
D. Create the WBS.

A
  1. A: The project charter is created and the project manager is assigned during the initiating process group. Stakeholder identification is also started during initiating and carried on throughout the project life cycle. It is essential to classify stakeholders according to their level of interest, influence, importance, and expectation at the early stage of the project as much as possible. Prior to jumping on planning, creating the WBS, and developing the project schedule, the project manager should focus on identifying and classifying the internal and external stakeholders in the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. You have been assigned to manage a project to design a new type of vinyl-based
    resilient floor material. You came up with a few orders of magnitude estimates, highlevel
    risks, constraints, and assumptions for the project. What project management
    process group are you in?

A. Monitoring & Controlling
B. Closing
C. Initiating
D. Planning

A
  1. C: High-level risks, constraints, and assumptions are identified in the project charter,
    which is created during project initiating. Usually, orders of magnitude estimates are
    done during the initiating process group when not much information is available about
    the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Which one of the following process groups consists of iterative and ongoing processes to establish the total scope of effort, to define the objectives, and to identify the course of action required to attain those objectives?

A. Planning
B. Executing
C. Initiating
D. Monitoring & Controlling

A

A: The planning process group consists of iterative and ongoing processes to establish the total scope of effort to define the objectives and to identify the course of action required to attain those objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. You are overseeing a construction project to construct a new fitness center at a local university. Currently, the team is working on collecting requirements and establishing estimates for the project. Which process group are you in?

A. Initiating
B. Executing
C. Monitoring & Controlling
D. Planning

A
  1. D: Requirements are collected from the customers and other stakeholders, and estimates on time, cost, resources, and other things are made during the planning process group.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. Which one of the following is not an outcome when a project is initiated properly in the initiating process group?

A. Authorizing the project manager to manage the project
B. Defining the scope of the project
C. Identifying the key stakeholders
D. Understanding the goal, objective, and business need of the project

A
  1. B: Detailed project scope will be defined during the planning process group. The success of subsequent processes and activities greatly depends on the way a project is initiated. If a project is initiated properly, it would have a clear business need and feasibility, a clear goal, objective reasons for selecting this project over other possibilities, a clear direction for the scope, a project manager assigned, and a list of stakeholders for the project. On the other hand, if a project is not initiated properly, it could result in limited or a total lack of authority for the project manager as well as ambiguous goals or uncertainties as to why the project was initiated.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. Which one of the following is NOT a planning process?

A. Create WBS
B. Perform Qualitative Risk Analysis
C. Estimate Costs
D. Develop Project Team

A
  1. D: Develop project team is a process in the executing process group. All three remaining processes belong to the planning process group.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. Steve has been overseeing a project to implement a new wireless media streaming
    device for a local networking company. The team has completed all the technical work
    in the project. The senior management asked Steve to report on the remaining activities
    in the project. Which one of the following will Steve report as the remaining work?

A. Completion of the lessons learned
B. Validation of the project scope
C. Completion of the quality management plan
D. Completion of risk response planning

A
  1. A: The lessons learned are usually done once the work is completed in the project. The quality management plan and the risk response plan are created during the planning process group. The validate scope process is done, not during closing, but in the monitoring & controlling process group.
17
Q
  1. You just finished creating your project charter. Which of the following will NOT be included in the charter?

A. Detailed work package descriptions
B. High-level roadmap and milestones
C. Assumptions and constraints
D. Authority level of the project manager

A
  1. A: High-level roadmap and milestones, assumptions and constraints, and authority level of the project manager should be included in the project charter. A project charter is created during initiating process group, but a project scope statement is created during planning process group. The scope baseline will have the scope statement, WBS, and details on WBS work packages.
18
Q
  1. While working in the initiating process group, you are mainly focusing on creating a
    project charter and a stakeholder register. You will use all of the following as inputs
    EXCEPT:

A. Organizational values and work ethics
B. Project scope statement
C. Configuration management knowledgebase
D. Historical information and past lessons learned

A
  1. B: Organizational process assets such as configuration management, knowledge base, historical information, and past lessons learned as well as enterprise environmental factors such as organizational values and work ethics are inputs in initiating process group. Project scope statement is an output of the planning process group.
19
Q
  1. Which one of the following is NOT a component of a change request?

A. Corrective actions
B. Preventive actions
C. Defect repairs
D. Issue Log

A
  1. D: A change request consists of corrective actions, preventive actions, and defect repairs. Corrective actions are taken to bring expected future performance of the project work in line with the project management plan. Preventive actions are taken to reduce the probability of risk items in the project. Defect repairs are taken to repair defects or entirely replace components that are faulty or dysfunctional. An issue is an obstacle that
    threatens project progress and can block the team from achieving its goals. An issue log
    is a written log to record issues that require solutions. It helps monitor who is responsible for resolving specific issues by a target date.
20
Q
  1. While working on the operating system upgrade project, the project manager realizes that he cannot estimate the time needed to upgrade a particular server due to the complexity of its build. He enrolls the help Mary who has been working on servers for over 20 years. What tool or techniques is the project manager using :

A. Subject Matter Expert
B. System Administrator
C. Expert Judgement
D. Data analysis

A
  1. C: Expert judgment is a common tool used by most processes. It’s where the project manager uses a subject matter expert to help with the process. Subject matter expert is not a name of a tool in the PMBOK.
21
Q

Project Documents

A
  1. Activity attributes
  2. Activity list
  3. Assumption log
  4. Basis of estimates
  5. Change log
  6. Cost estimates
  7. Cost forecasts
  8. Duration estimates
  9. Issue log
  10. Lessons learned register
  11. Milestone list
  12. Physical resource assignments
  13. Project calendars
  14. Project communications
  15. Project schedule
  16. Project schedule network diagram
  17. Project scope statement
  18. Project team assignments
  19. Quality control measurements
  20. Quality metrics
  21. Quality report
  22. Requirements documentation
  23. Requirements traceability matrix
  24. Resource breakdown structure
  25. Resource calendars
  26. Resource requirements
  27. Risk register
  28. Risk report
  29. Schedule data
  30. Schedule forecasts
  31. Stakeholder register
  32. Team charter
  33. Test and evaluation documents