Plans Theme Flashcards
1
Q
Who approves the project, stage and exception plans with tolerances?
A
Exec/ board
2
Q
Who commits business resources to stages? e.g. finances?
A
Senior User and Senior Supplier
3
Q
Who design the plans?
Prepares project and stage plans, and if required, an exception plan
A
PM
4
Q
Who contributes specific expertise to the PM when possible?
A
Project Support
5
Q
Who prepares the Team Plan?
A
TM
6
Q
Is the Team Plan mandatory?
A
No
7
Q
What is minimum number of stages?
A
- Initiation
2. Further Stage