Business Case Theme Flashcards
Mandate contains
the reason
the project tolerances
D________, V________, A_________
desirable
viable
achievable
Three actions taken throughout project
Develop
Verify OBC
Verify Detailed BC
Verify Updated BC
Maintain
Confirm Benefits
When do we finalise the BMA
Closing a Project process
When and by who is the OBC created?
Exec
during SU process
When do we create the BMA
IP process
What is the output v the outcome
Output is our deliverable
Outcome is the change (in behaviour, way of working or doing things)
What is a negative outcome?
A disbenefit
how is the BC used in controlling a stage for risks, issues and change?
For impact analysis
What must be created and maintained throughout the project
Business justification for the project
What happens to the business justification after an event?
It is reviewed and updated
What must to defined in order to ensure project outcomes are achieved?
Management actions
In what must the R&Rs be defined and documented?
BC
BMA
If the project is part of a programme will the BC content be increased or reduced?
Reduced.
The BC is likely to be aggregated into the programme’s business case
Who is accountable for the supplier’s business case?
Senior Supplier