Planning law Flashcards

1
Q

What is planning permission needed for?

A

Any development of land

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Definition of “development”

A
  • building/engineering/mining/other operations on/under/over land, OR
  • making material change to the use of any buildings or other land
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is NOT a “development”

A
  • anything affecting only the interior, or if there’s no material effect on external appearance,
  • excluded material changes of use (change within same class)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are “sui generis” uses?

A

Uses that could have a bad effect on their locality
Have their own class
So, changing to/from sui generis code requires planning permission
eg. cinemas, bars, hot takeaways…

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When must planning permission be implemented?

A

Usually:
England: within 3 years of permission
Wales: within 5 years of permission

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Time limit on completing a development with planning permission

A

Usually no limit
BUT: Local Planning Authority can serve a completion notice (permission lapses if not completed by certain date)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Does planning permission authorise the breach of an enforceable covenant?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When is an application for planning permission not necessary, despite there being a “development”?

A

GDPO 2015 (England)/GDPO 1995 (Wales):
- developments within curtilage of dwelling house/minor operations,
- specified changes between classes,
- changes from some sui generis uses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How can a GDPO concession be negated?

A

Secretary of State issues an Article 4 Direction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What to do if in doubt about whether a development falls under GDPO exception, or amounts to a “development”?

A

Apply to LPA for a Certificate of Lawfulness

If denied: must apply for planning permission!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Punishment for failing to comply with a LPA notice?

A

Fine

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

LPA may serve an enforcement notice if:

A
  • there’s been a breach of planning control
    It must specify the steps to be taken to comply
    OR: can issue enforcement warning notice (allows retrospective planning permission application)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When can a stop notice be served?

A

ONLY after an enforcement notice was served

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When is a breach of condition notice served?

A

When a condition of planning permission was breached

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Injunction time limits in England + Wales

A

England: 10 years
BUT: if breach involves development or a change of use to a dwelling house BEFORE April 2024, 4 years

Wales: 10 years
BUT: if involves development or a change of use to a dwelling house it’s 4 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who is responsible for the lack of planning permission?

A

Current owner (not whoever didn’t obtain it!)

17
Q

When is an injunction granted?

A

Discretionary: if LPA shows it’s necessary and appropriate

18
Q

What is building regulation control?

A

It requires consent to be obtained for many works, even if planning permission isn’t required
Apply for consent before work starts, and the work’s inspected once it’s done
Then receive certificate of compliance

19
Q

Time limit in England + Wales for building control prosecution

A

England: no limit
Wales: within 2 years of offence

20
Q

Time limit in England + Wales for building control enforcement notice for alteration/removal

A

England: 10 years from completion
Wales: 1 year from completion

21
Q

Time limit for building control injunctions if the building is unsafe

A

None

22
Q

Extra permission required to demolish/alter/extend a listed building

A

listed building consent

the higher the listing, the harder to get consent (grades 1, 2*, and 2)

23
Q

What are conservation areas?

A

Areas of special architectural or historic interest, the appearance or character of which it’s desirable to preserve/enhance

24
Q

Procedure for doing work on a tree in a conservation area

A

LPA must be notified 6 weeks in advance
LPA decides whether/how works should happen